Nottingham City Council
Executive Board, Tuesday 22 September 2026 at 2.00pm

HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoists

Approved Executive 1 paper

AI summaryNottingham City Council Executive Board approves a £3.1 million four-year framework for specialist mechanical lifting equipment, including stairlifts and hoists, in council housing.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSpecialist lifting equipment for HRA tenants
Money£3.1 millionTotal aggregated contract value over four years
What happens nextProcurement exercise to followAward via delegated authority to director
Who it affectsHRA tenants with assessed needsAround 874 council properties already have equipment

What was decided

The Executive Board approved the procurement and award of a four-year framework for HRA specialist mechanical equipment, covering stairlifts, step lifts, through-floor lifts and hoists. Report 2.1

Authority was delegated to the Corporate Director of Growth and City Development, in consultation with the Executive Member for Housing and Planning, to award the framework and call off contracts up to £3.1million. Report 2.6

Requirements of the Mechanical and Electrical Team will be combined with those of the Adaptations and Renewals Agency under a single integrated contract. Report 2.5

Why

The Council has a statutory duty under the Housing Act 1985, Care Act 2014, Chronically Sick and Disabled Persons Act 1970 and Equality Act 2010 to provide specialist adaptations to residents with assessed needs. Report 1.2, P3, 2.1, 6.1

A review of existing corporate contracts and frameworks found no suitable arrangement covering the full lifecycle, so a standalone procurement exercise is required. Report 2.4, 1.13

Combining the requirements into a single contract is expected to improve value for money, simplify contract management, ensure procurement compliance and support timely access to equipment for tenants. Report 2.5, P21

What happens next

A compliant procurement exercise will be undertaken in line with the Procurement Act 2023 and the Council's Contract Procedure Rules, with support from Procurement and Legal teams. Report 6.2, 7.1, 7.2

The framework will be awarded by the Corporate Director of Growth and City Development under delegated authority, with contract management supported by key performance indicators and review meetings. Report P32, 7.3

The money

  • £3.1million Aggregated value of the framework over its four-year term, requiring Executive Board approval Report 2.6, 5.1
  • £1.25m Already approved for servicing, repair and maintenance of stairlifts, hoists and disabled access equipment through the Housing Services Procurement Plan 2025 to 2029 Report 2.2

Options considered

  • Chosen: Approve a four-year integrated framework covering supply, installation, servicing, maintenance, repair and recycling. Combines requirements, improves value for money, ensures procurement compliance and supports statutory duties Report 2.5, P21
  • Rejected: Do nothing and let existing arrangements and contracts expire without replacement. Would expose the Council to non-compliance with procurement legislation and failure to meet statutory duties Report 3.1
  • Rejected: Insource the installation of specialist equipment. Highly specialist work would require significant investment in training, tools, vehicles and compliance systems Report 3.2
  • Rejected: Use short-term contracts instead of a four-year procurement period. Would require frequent reports and approvals and would not provide the same value, stability or efficiency Report 3.3

Implications

  • Legal: Procurement must comply with the Procurement Act 2023, Contract Procedure Rules and Financial Regulations, with Legal and Procurement support to mitigate challenge risk. Report 6.2, 7.1, 7.2
  • Equalities: The published Equality Impact Assessment for the Adaptations Policy for Council Tenants with Disabilities and Long-term Health Conditions covers this decision. Report 8.2
  • Financial: No additional budget approval is needed, as funding is already available within the Housing Revenue Account under Project Code 113099. Report 2.7, 5.1
  • Risk: Identified risks include procurement delays, non-compliant processes, contractor failure, equipment failure and mobilisation disruption, with mitigations set out for each. Report P30, P31, P32, P33, P34
  • Climate: A Carbon Impact Assessment has been completed and signed off by the climate change team, with positive impacts recorded in Built Environment and Resilience and Adaptation. Report 8.3, P58, P59, P60
  • Staffing: Future Local Government Reorganisation may change how adaptation services are commissioned and delivered, with this procurement intended to ensure continuity in the interim. Report P35

Who and where

  • Council housing tenants with assessed needs for specialist mechanical lifting equipment Report 1.1, 1.10, P12
  • Adaptations and Renewals Agency and Housing Services Mechanical and Electrical Team Report 1.8, 1.9
  • All wards in Nottingham Report P68

Timeline

  • 2021/22 to 2025/26: Recorded demand by equipment type, used as a basis to forecast future requirements Report P13
  • 13 May 2025: Commissioning and Procurement Executive Committee approved the Housing Services (Property Services) Procurement Plan 2025 to 2029 Report P65
  • Four years: Proposed duration of the new framework arrangement Report 2.6

Plain English for the jargon

  • HRA: Housing Revenue Account, the ringfenced account used to manage income and spending on council housing
  • ARA: Adaptations and Renewals Agency, responsible for ordering and installing specialist equipment in council properties
  • DFG: Disabled Facilities Grant, a means-tested grant used to fund adaptations, mainly in owner-occupied and private rented homes
  • OT assessment: Assessment by an Occupational Therapist to identify a resident's needs and recommend appropriate adaptations
  • LOLER: Lifting Operations and Lifting Equipment Regulations, covering the inspection and maintenance of lifting equipment
  • KPI: Key Performance Indicator, used to monitor contractor performance against agreed standards
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item68

Resolved

Resolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stairlifts, step lifts, through-floor lifts and hoists for a four-year period; (2) delegate authority to the Corporate Director of Growth and City Development, in consultation with the Executive Member for Housing and Planning, to award the framework and to call off contracts to the value of £3.1million. Reason for decisions: the Council has a statutory responsibility to provide specialist mechanical lifting equipment for residents with assessed needs. To ensure the continued delivery of this essential service, approval is required to undertake a compliant procurement process for the supply, installation, servicing, maintenance, repair and recycling of equipment such as hoists and stairlifts. Existing approvals already provide funding for some related services, but a broader procurement approach is now proposed; to improve efficiency and value for money, the Council plans to combine the requirements of the Mechanical and Electrical Team with those of the Adaptations and Renewals Agency under a single contract. A review of existing frameworks found no suitable arrangement that could meet all requirements, making a standalone procurement exercise necessary. A unified contract would simplify contract management, strengthen accountability, ensure procurement compliance and support timely access to equipment for tenants; the proposed contract has an aggregated value of £3.1 million over its term, requiring Executive Board approval. No additional budget approval is needed, as funding is already available within the Housing Revenue Account. This integrated approach will help the Council meet its statutory obligations, achieve greater operational efficiency and deliver improved outcomes for tenants who rely on specialist equipment. Other options considered: do nothing and allow existing arrangements and contracts to expire without replacement. This option was rejected as this would expose the Council to either failing to be compliant with procurement legislation or failure to meet its statutory duties to support residents with assessed needs; insource the installation of specialist equipment. This option was rejected due to complexity, cost and risk. The highly specialised nature of the equipment and associated works would require significant investment in training and workforce development, specialist tools, equipment and vehicles and compliance systems; opting for short-term contracts instead of a four-year procurement period. This option was rejected as it would necessitate the frequent submission of various reports for approval. Given the ongoing and foreseeable demand for specialist equipment a longer-term arrangement provides better value, stability and efficiency.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Executive Board – 22 September 2026

Subject: Housing Revenue Account (HRA) funded capital adaptations - Specialist Mechanical Lifting Equipment – Key Decision Executive Member(s): Councillor Jay Hayes – Executive Member for Housing and Planning Corporate Nicki Jenkins – Corporate Director of Growth and City Director(s)/Director(s): Development Charlotte McGraw - Strategic Director of Housing Services Summary of issues:

This report seeks approval to procure and award a contract for the provision of Specialist Mechanical Lifting Equipment for Council tenants, including stairlifts, through-floor lifts, step/platform lifts and hoists, together with associated installation, servicing, maintenance, repair and recycling services.

The provision of this equipment is a statutory requirement, supporting the Council’s duties to enable residents with assessed needs to safely access and remain in their homes. These adaptations are funded through the Housing Revenue Account. The Adaptations and Renewals Agency within Adult Social Care oversee the purchasing of these items and the Mechanical and Electrical Team oversee the ongoing maintenance and repair service.

Approval is sought to undertake a compliant procurement exercise and award a four-year framework. The recommended approach is a single, integrated procurement covering the full lifecycle of the equipment, which will improve value for money, strengthen contract management and deliver better outcomes for tenants.

Approval to procure and award up to £1.25m for the servicing, repair and maintenance of stairlifts, hoists and disabled access equipment has already been secured by the Mechanical and Electrical Team through the Housing Services (Property Services) Procurement Plan 2025–2029, approved by the Commissioning and Procurement Executive Committee (as in place at the time). However, in line with the Council's commitment to delivering efficient, joined-up services and maximising value for the Housing Revenue Account, it is proposed that the procurement requirements of Housing Services’ Mechanical and Electrical Team are combined with those of the Adaptations and Renewals Agency within Adult Social Care. This integrated procurement approach will create economies of scale, simplify contract management, strengthen supplier accountability and support a more integrated service for tenants. The combined contract value is £3.1million; this increased amount therefore requires Executive Board approval. The budget for this expenditure is already in place within the Housing Revenue Account.

Further supporting Nottingham City Council’s statutory functions and service delivery obligations, the procurement arrangements will facilitate fulfilment of the Council’s statutory duty under • Housing Act 1985 (landlord duties) • Care Act 2014 (meeting assessed needs) • Chronically Sick and Disabled Persons Act 1970 (duty to provide adaptations) • Equality Act 2010 (reasonable adjustments) Recommendation(s): 1 To approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stairlifts, step lifts, through-floor lifts and hoists for a four-year period.

2 To delegate authority to the Corporate Director of Growth and City Development, in consultation with the Executive Member, to award the framework and to call off contracts to the value of £3.1million

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HRA funded capital adaptations: Stairlifts, Step lifts, through-floor lifts and hoistsReport 166 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 20 attended
BB
Beth BrownOfficer, expected
MC
Michael CareyClerk, expected
SF
Stuart FairOfficer, expected
JH
Councillor Jay HayesCommittee Member, expected
PU
Councillor Patience Uloma IfedioraCommittee Member, expected
NJ
Nicki JenkinsOfficer, expected
HK
Councillor Helen KalsiCommittee Member, expected
NK
Councillor Neghat KhanChair, expected
LL
Lucy LeeOfficer, expected
SL
Councillor Sam LuxCommittee Member, expected
SM
Councillor Sulcan MahmoodCommittee Member, expected
NM
Neil McArthurOfficer, expected

All 20 on the meeting page

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open
22 Sep 2026 2026/27 Budget Monitoring Report – Quarter 1Resolved to: (1) note the Quarter 1 (ending 30 June 2026) General Fund forecast overspend of £0.3m against an approve... Noted Open