Customer Access Programme - Business Case - Key Decision

Agreed Executive 2 papers

Executive Board agreed this item on Tuesday 25 February 2014. Below is the council's own wording, with the papers it was decided on.

Item114

Resolved

RESOLVED to (1) agree the business case to allow the Customer Access Programme to progress to design and implementation; (2) agree the following: (a) total expenditure of £4.206 million over years 1-4 of the programme: · £2 million one off funding from the IT Efficiency Fund; · £2.206 million to be funded from the savings delivered by the programme; (b) a capital one off expenditure being added to the Capital Programme once the amount is known; (c) net potential savings totalling £1.973 million per annum form year 4 onwards. Reasons for decisions The business case shows that there is a need for change as the current structure of Customer Services does not support the Citizens at the Heart agenda and leads to: · variable/disjointed/inconsistent provision of Customer Services across all access points; · duplication of processes, effort, data and costs; · no co-ordinated understanding of customer needs underpinned by performance data; · no strategy for customer contact or channel shift; · no customer contact function owning the relationship with customers; · creating unnecessary demand and cost and making the customer journey confusing; · no easy way to deliver services to customers with partner agencies; · missed opportunities. The Programme contains structural, cultural and technical improvements which address the issues and design services around the needs of the customer whilst also making efficiency savings. Other options considered No other options were considered as the business case builds on the decision taken by the Board on 18 June 2013.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Customer Access Programme

Final Outline Business Case Contents

1. Executive summary 2. Purpose and decisions required 3. Current position 4. Options appraisal 5. Proposed option 6. Strategic fit 7. Cost/benefits case 8. Underpinning assumptions and findings 9. Flexing and timing 10. Recommendations 11. Next steps

1 1. Executive summary

The Strategic Outline Case (SOC) for the Customer Access Programme (CAP) has previously been endorsed at the Citizen First board. This SOC introduced the strategic direction, project concept and a high level consideration of possible options. The Outline Business Case (OBC) contains a more comprehensive analysis of the preferred options to assess whether there is a compelling imperative to progress.

The current position and the need to change This OBC provides an overview assessment of the Council’s current provision of customer service compared to other authorities and recognised customers expectations. It depicts that there are significant opportunities to reduce contact demand and then provide a more joined up, digital-led provision of service. This would lead to increased customer satisfaction by interacting in a manner that suits them better plus allows the Council to gain efficiencies by wider usage of self-service channels.

Narrowing SOC options The OBC provides a rationale to filter to one option to base the assessment on. This filtering leads to the option that: incorporates all services for transformation; is implemented by establishing the necessary foundations early but then phasing the introduction of services. It recognises to achieve the principles agreed in the SOC a single customer service function is required – but this does not necessarily mean a single physical entity. This assessment also recognises the Council’s desire to create and operate its own function prior to increasing links to partners or considering other parties to operate this function on their behalf.

2 1. Executive summary

Proposed option A potential operating model has been developed. This is based on three levels of interaction – self-service to cater for simple interactions, a customer management layer for the complex and service delivery/back office for the unique ones. On this basis we encourage customers to help themselves, then to provide maximum first time resolution when they to contact us and when required have the necessary expertise for those involved cases. We have also considered that different customer groups need different pathways through this model e.g. business customers may need to contact a more income-generation based team.

Assessing the strategic fit of the proposed option The option has been assessed for strategic fit against the design principles; which it does and in doing so aids development of those principles into more tangible considerations in terms of channels, process, people and technology.

Assessing the financial benefits of the proposed option The option has been assessed against leading practice from other local authorities to understand what the true opportunity is here. As befits an OBC this assessment uses our data and makes assumptions where required. The financial assessment is based on two factors: 1.how our current telephony good practice areas could be expanded to take on additional services and how we could deepen what we do at this first contact (fulfilment) 2.how we could shift the balance of our channels to web self-service (where appropriate).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Customer Access Programme: Business Case: Key DecisionDecisions 821 KB Download
PDF
Item 7: Customer Access Programme Background PapersReport 1.1 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
GC
Councillor Graham ChapmanVice Chair, present
AC
Councillor Alan ClarkCommittee Member, present
JC
Councillor Jon CollinsChair, apologies (council business)
NH
Councillor Nicola HeatonCommittee Member, apologies (on leave)
DL
Councillor Dave LiversidgeCommittee Member, present
NM
Councillor Nick McDonaldCommittee Member, present
DM
Councillor David MellenCommittee Member, present
AN
Councillor Alex NorrisCommittee Member, present
DT
Councillor Dave TrimbleCommittee Member, present
JU
Councillor Jane UrquhartCommittee Member, present

On this subject at Nottingham

Search all
  1. Customer Access Programme - Business Case - Key DecisionThis decision
  2. Customer access programmeDecided

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies