Expanding the installation programme of solar panels on commercial sites in Nottingham - Key Decision

Approved Executive 2 papers

Executive Board approved this item on Tuesday 18 March 2014. Below is the council's own wording, with the papers it was decided on.

Item128

Resolved

RESOLVED to (1) approve provision in the capital programme for the schemes detailed in the report with costs detailed in the exempt appendix and delegate authority to the Director of Neighbourhood Services, in consultation with the Portfolio Holder for Energy and Sustainability, to utilise funds from the capital programme for the production of the final business case; (2) approve that the delivery of construction works will be through the Council’s in-house teams and through the established Highway Framework for specialist activities and delegate authority to the Director of Neighbourhood Services, in consultation with the Portfolio Holder for Energy and Sustainability, to commence procurement processes and award contracts; (3) approve the procurement of solar photovoltaic solutions through a compliant route, as outlined in site specific business cases, and delegate authority to the Director of Neighbourhood Services, in consultation with the Director of Legal and Democratic Services, the Portfolio Holder for Energy and Sustainability and the Deputy Leader/Portfolio Holder for Resources and Neighbourhood Regeneration, to commence the procurement processes and award contracts. Reasons for decisions The schemes and procuring the solar photovoltaic solutions provides the following advantages: · it supports the plan to reduce the Council’s carbon emissions by 31% by 2020 which forms part of the Council’s Carbon Management Plan; · it helps to realise the targets set out in the Energy Strategy to have 20% of the City’s own energy generated from low or zero carbon sources and a 26% reduction of carbon dioxide emissions against 2005 levels; · it has been designed to take advantage of the Government’s Feed In Tariff, electricity cost savings and export tariff revenue and will generate a long term revenue stream for the Council; · it will be a regional statement for Nottingham’s ambitions and the chosen site is a key gateway to the City which is seen by 81,000 motorists and bus users per day; · once installed, the site will be the largest urban solar park array in the UK, generating approximately 1.3GWh annually of renewable electricity which will offset 741 tonnes of carbon dioxide; · it will help reduce the Council’s dependency on fossil fuels, reduce utility costs and contribute to energy security; · it will work in partnership with the electric bus project and provide up to 50% of the buses fuel requirements on site. The park and ride sites will have charging points for the buses where they can quickly charge through the day; · it will help develop a template for delivery of these types of schemes that can be utilised for future programmes, enabling growth and contributing to the commercialisation agenda; · the canopy will provide additional shading and shelter for 480,000 park and rider users per annum. Delivering the construction works through the Council’s in-house team and the established Highway Framework provides the following advantages: · it maximises the Neighbourhood Services teams and utilises their technical resources; · it enables local green job creation and training opportunities through utilising City Council frameworks and the skilled labour force of Neighbourhood Services operational teams; · it creates training opportunities, stimulating the local economy, which is demonstrated through up-skilling in-house teams and the recent intake of 50 apprentices. Other options considered Procuring full design, supply and installation through the existing commercial solar photovoltaic framework was rejected because it would add additional cost to the scheme through procuring a third party contractor for the installation, which would reduce the return on investment and it could possibly reduce the opportunity to create local jobs. Doing nothing was rejected as it would offer no contribution to Council policy or the Energy Strategy and it would not take advantage of the Feed In Tariff subsidy, export tariff payments and energy savings associated with solar photovoltaic installation.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Equality Impact Assessment Form Name and brief description of proposal / policy / service being assessed Expanding the installation programme of solar panels on Commercial sites in Nottingham A solar panel installation programme to deliver solar panel car park canopy solutions to park and ride sites in Nottingham Information used to analyse the effects on equality Discussions with the Equality and Diversity Team.

Could May Details of actions to reduce negative How different groups could be affected: particularly adversely or increase positive impact (or why Summary of impacts benefit (X) impact (X) action not possible) People from different ethnic This scheme will deliver energy savings to the City We will continually assess the impact of groups Council and provide a revenue return by accessing the measures to citizens that are Men, women (including external subsidies such as the Feed In Tariff. directly affected. maternity/pregnancy The canopy solution will also improve customer These shall be met by impact impact), transgender people satisfaction at each site such as shelter from the rain consultations with citizens through the Disabled people or carers design and planning process. People from different faith groups This scheme will require planning Lesbian, gay or bisexual permission to proceed which will people naturally measure the response by the Older or younger people citizens to the proposed installations Other (e.g. marriage/civil partnership, looked after children, cohesion/good relations, vulnerable children/adults) Outcome(s) of equality impact assessment: No major change needed  Adjust the policy/proposal Adverse impact but continue Stop and remove the policy/proposal Arrangements for future monitoring of equality impact of this proposal / policy / service: Assessment to be reviewed at time of regular scheduled audits of the systems

Approved by (manager signature): Gail Scholes Date sent to equality team for publishing: March 2014

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Expanding the installation programme of solar panels on commercial sites in Nottingham: Key DecisionDecisions 63 KB Download
PDF
Solar Panels EIAReport 30 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
GC
Councillor Graham ChapmanVice Chair, present
AC
Councillor Alan ClarkCommittee Member, present
JC
Councillor Jon CollinsChair, present
NH
Councillor Nicola HeatonCommittee Member, present
DL
Councillor Dave LiversidgeCommittee Member, present
NM
Councillor Nick McDonaldCommittee Member, present
DM
Councillor David MellenCommittee Member, present
AN
Councillor Alex NorrisCommittee Member, present
DT
Councillor Dave TrimbleCommittee Member, present
JU
Councillor Jane UrquhartCommittee Member, present

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies