AREA CAPITAL FUND - 2013/15 PROGRAMME

Approved Committee 1 paper

Area Committee East (A.C.E) Dales, St Ann's & Mapperley approved this item on Tuesday 13 May 2014. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

RESOLVED to (1) note that the following money is available: Dales £37,225 Mapperley £39,451 St Ann’s £121,933 (2) approve the following new schemes: Dales Public Realm Schemes: Location Type Estimate Details St Christopher’s Church Contribution £2,000 Contribution to the resurfacing of the path at St Stephen’s Church Greens Mill Contribution £5,000 Contribution to the replacement of windmill sails at Greens Mill Mapperley Local Transport Plan Schemes: Location Type Estimate Details Mapperley ward Footpaths £26,385 Continuation of the large-scale patching programme on Warwick Drive, Tavistock Drive and Cyprus Road Mapperley ward Footpaths £7,000 Additional contribution to complete the large-scale patching of footpaths on Mapperley Road Belvoir Street H-bars £1,750 Further contribution to the H-bar installation programme to cover further requests Mapperley ward H-bars (additional) £450 Additional traffic management costs for the ward H-bar programme Mapperley Public Realm Schemes: Location Type Estimate Details Mapperley ward Footpaths £23,615 Contribution to the large-scale patching works on Warwick drive, Tavistock Drive and Cyprus Road Albert Road Traffic calming £8,000 Introduction of traffic calming measures on Albert Road to improve pedestrian and cyclist safety Kelvin Road / Wheatfields Road Bollards £1,700 Installation of bollards on corners to improve pedestrian safety Hungerhill Road Fencing £1,513 Contribution to the provision of mesh security fencing with gates for fire access at the Scout Hut on Hungerhill Road. This is a joint scheme with St Ann’s ward Albert Road Tree works £1,200 Tree planting works on Albert Road St Ann ’s Local Transport Plan Schemes: Location Type Estimate Details St Ann ’s Well Road Wall refurbishment £792 Refurbishment of the wall adjacent to the pedestrian crossing on St Ann’s Well Road St Ann ’s Public Realm Schemes: Location Type Estimate Details Greens Mill Contribution £5,000 Contribution to the replacement of windmill sails at Greens Mill Sycamore School Floodlighting £29,645 Contribution to floodlight works at Sycamore School for the community football club Hungerhill Road Fencing £1,513 Contribution to the provision of mesh security fencing with gates for fire access at the Scout Hut on Hungerhill Road. This is a joint scheme with Mapperley ward Hudson Street Gating £891 Realignment of the gate on Hudson Street for security purposes Bellvue Court Mobility access £870 Widening of the gate for mobility access to the shared area at Bellvue Court
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Area Committee East (A.C.E) Dales, St Ann's & Mapperley

AREA COMMITTEE EAST (ACE) (Dales, Mapperley, St Ann’s) – 13 MAY 2014

Title of paper: AREA CAPITAL FUND - 2013/15 Programme Director(s)/ Andy Vaughan Wards affected: Corporate Director(s): Director of Neighbourhood Services Dales, Mapperley & St Ann’s Contact Officer(s) and contact Dorothy Holmes Locality Manager details: 0115 8839804 [email protected] Greg Foister Neighbourhood Development Officer – Dales Ward 0115 8839807 [email protected] Fi Cusick Neighbourhood Development Officer – Mapperley Ward 0115 8839728 [email protected] Michelle Graley Neighbourhood Development Officer – St Ann’s Ward 0115 8839808 [email protected]

Other officers who have Nancy Hudson, Projects Officer, Highway Services provided input: Tel: 0115 8765633 Nancy. [email protected]

Relevant Council Plan Strategic Priority: Cutting unemployment by a quarter  Cut crime and anti-social behaviour  Ensure more school leavers get a job, training or further education than any other City  Your neighbourhood as clean as the City Centre  Help keep your energy bills down  Good access to local transport  Nottingham has a good mix of housing  Nottingham is a good place to do business, invest and create jobs  Nottingham offers a wide range of leisure activities, parks and sporting events  Support early intervention activities  Deliver effective, value for money services to our citizens 

Summary of issues (including benefits to customers/service users): This report provides Councillors with :-  Latest spend proposals under the Area Capital Fund including highways and footways

Recommendation(s): 1 a) Note the monies available to Dales, Mapperley and St Ann’s Wards as outlined in Appendix 1 b) That the Area Capital programme of schemes for Dales, Mapperley and St Ann’s, as set out in Appendix 1 approved.

1 REASONS FOR RECOMMENDATIONS (INCLUDING OUTCOMES OF CONSULTATION) 1.1 The Nottingham LTP 2011-2026 maintains a commitment to deliver local transport improvements across Nottingham’s Neighbourhoods and prioritises small scale transport improvements of importance to local communities

As part of the budget process Nottingham City Council approved in March 2011 an LTP capital allocation of £2.5 million citywide between 2011-2013.

To give opportunity for the Area Committee to make comment on suggested schemes and their progress

2 BACKGROUND (INCLUDING OUTCOMES OF CONSULTATION)

2.1The Area Capital Programme was established to improve the environment of the neighbourhoods and to create a sense of place for residents in order to improve the quality of life of local people. Since it was established in 2006 to meet the then corporate priority of “Transforming Neighbourhoods” the Area Capital Fund has included a total programme expenditure portfolio of £40 million. The improvements that have been carried out to date using this programme have included footpath, fences, visual enhancements to public realm, refurbishment of parks and improvements to public buildings.

2.2Resources are allocated from the Nottingham City Council general fund, the Local Transport Plan (LTP) and from the Housing revenue Account. To achieve a joint approach to environmental improvements in neighbourhoods, a greater degree of flexibility has been established to prioritise and deliver improvements so that there is a synergy in local solutions for local issues across neighbourhoods.

2.3The programme of works is a rolling programme. There have been instances where schemes are started, with strong community involvement and interest, only to be altered at a later stage due to changing circumstances such as economic conditions and changes in land values.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AREA CAPITAL FUND: 2013/15 PROGRAMMEReport 355 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 11 attended
JC
Councillor Jon CollinsCommittee Member, present
ED
Councillor Emma DewintonCommittee Member, present
RH
Councillor Rosemary HealyCommittee Member, present
SJ
Councillor Sue JohnsonChair, present
RK
Rav KalsiConstitutional Services, absent
GN
Councillor Gul Nawaz KhanCommittee Member, present
NN
Councillor Neghat Nawaz KhanVice Chair, present
DL
Councillor Dave LiversidgeCommittee Member, present
DM
Councillor David MellenCommittee Member, present
TM
Councillor Thulani MolifeCommittee Member, present
JS
Janet SummersPublic, in attendance

On this subject at Nottingham

Search all
  1. AREA CAPITAL FUND - 2013/15 PROGRAMMEThis decision
  2. Area Capital Fund Allocation for Highways and Transport - Key DecisionApproved
  3. Area Capital FundApproved
  4. Area Capital Fund ReportNoted
  5. Area Capital Fund 2020/21Approved
  6. Area Capital Fund ReportApproved

More from Nottingham Area Committee East (A.C.E) Dales, St Ann's & Mapperley

All decisions
MeetingDecisionOutcome
12 Mar 2019 Issues and Good News StoriesRESOLVED to thanks the Community Representatives for their updates and to note their content. Noted Open
12 Mar 2019 Area Policing UpdateRESOLVED to thank Inspector Walker for his update and to note its content. Noted Open
12 Mar 2019 Nottingham City Homes UpdateRESOLVED to: (1) Note the update and performance information in appendices 1 and 2 of the report published with the a... Noted Open
12 Mar 2019 Lead Organisation Update - Renewal TrustRESOLVED to thank Emma Lucas to for her presentation and to note its content Noted Open
12 Mar 2019 Area Capital Fund 2018/19 ProgrammeRESOLVED to: (1) Approve the new schemes prioritised by Ward Councillors since the last area committee as detailed be... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies