Aspley, Bilborough and Leen Valley Area Committee approved this item on Wednesday 31 March 2021. Below is the council's own wording, with the papers it was decided on.
Resolved to approve the prioritised Area Capital schemes for Aspley Ward as set out in the Appendix to the report, including four Local Transport Plan schemes at a total cost of £81,157 and five Public Realm schemes at a total cost of £37,600.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Report to Aspley, Bilborough and Leen Valley Area Committee
Reasons for recommendations
1.1The Nottingham Local Transport Plan (LTP) 2011-2026 maintains a commitment to deliver local transport improvements across Nottingham’s neighbourhoods and prioritises small-scale transport improvements of importance to local communities. 1.2 As part of the budget process, the Executive Board meeting on 18 February 2020 approved a LTP capital allocation of £1.25million citywide for 2020-21. At the same meeting, a citywide allocation of a General Fund Element (public realm) of £750,000 was agreed. At the subsequent Executive Board meeting on 21 July 2020, as part of the budget update, a top-slice of 20% was made to the General Fund Element (public realm) reducing it to £600,000.
2 Background (including outcomes of consultation)
2.1The Area Capital Programme was established to improve the environment of the neighbourhoods and to create a sense of place for residents in order to improve the quality of life of local people. Since its establishment in 2006 to meet the then corporate priority of ‘Transforming Neighbourhoods’, the Area Capital Fund has included a total programme expenditure portfolio of £40million. The improvements that have been carried out to date using the programme have included footpath construction and repairs, fences, visual enhancements to public realm, refurbishment of parks and improvements to public buildings.
2.2Resources are allocated from the Council’s general fund, the LTP and from the Housing Revenue Account. To achieve a joint approach to environmental improvements in neighbourhoods, a greater degree of flexibility has been established to prioritise and deliver improvements so that there is a synergy in local solutions for local issues across neighbourhoods.
2.3The programme of works is a rolling programme. There have been instances where schemes are started, with strong community involvement and interest, only to be altered at a later stage due to changing circumstances such as economic conditions and changes in land values.
2.4The Area Committee, particularly community representatives, are invited to comment specifically on those schemes identified in the proposals column and to consider whether certain schemes can be linked to other programmes of work in order to generate best value and create a greater impact on the local area.
3 Other options considered in making recommendations
3.1None.
4 Finance colleague comments (including implications and value for money/VAT)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Aspley, Bilborough and Leen Valley Area Committee at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.