RESOLVED (1) to approve the following committed schemes for Aspley, Bilborough and Leen Valley wards and the decommitted scheme for Bilborough ward: Location Scheme Cost Aspley Parking Bay Scheme 1 Parking bays 60,000 Snickett Scheme 3 & 4 Vehicle access 119,500 Minver Crescent Footpaths 58,800 Landfield Road Phase 2 Wall scheme 60,454 Bilborough Wigman Road Feasibility study 3,000 Birchover Road Survey 600 Various (parking) Consultation 1,000 Various (Decommitted scheme) Benches 12,000 Leen Valley Beechdale Road Traffic order 6,800 (2) to note the remaining ward balances of £0 (Aspley), £60,867 (Bilborough) and £91,188 (Leen Valley).
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Title of paper: AREA CAPITAL FUND - 2013/15 Programme
Director(s)/ Andy Vaughan Wards affected: Corporate Director(s): Director of Neighbourhood Services Aspley, Bilborough, Leen Valley Report author(s) and Julianne Christou contact details: Neighbourhood Development Officer –Bilborough Ward 0115 8833739 [email protected]
Other colleagues who Nancy Hudson, Projects Officer, Highway Services have provided input: Tel: 0115 8765633 [email protected] Sioban Campbell Neighbourhood Development Officer – Aspley Ward 0115 8833738 [email protected] Deborah Wilson Neighbourhood Development Officer –Leen Valley Ward 0115 8833741 [email protected]
Date of consultation with Portfolio Holder(s) (if relevant)
Relevant Council Plan Strategic Priority: Cutting unemployment by a quarter Cut crime and anti-social behaviour Ensure more school leavers get a job, training or further education than any other City Your neighbourhood as clean as the City Centre Help keep your energy bills down Good access to public transport Nottingham has a good mix of housing Nottingham is a good place to do business, invest and create jobs Nottingham offers a wide range of leisure activities, parks and sporting events Support early intervention activities Deliver effective, value for money services to our citizens
Summary of issues (including benefits to citizens/service users):
This report provides Councillors with: Latest spend proposals under the Area Capital Fund including highways and footpaths.
Recommendation(s): 1 a) Note the monies available to Aspley, Bilborough and Leen Valley as outlined in Appendix 1. b) That West Area Committee approves the committed schemes for the Leen Valley and Bilborough Wards and the decommitted scheme in the Bilborough Ward highlighted in Appendix 1. 1. REASONS FOR RECOMMENDATIONS
1.1The Nottingham LTP strategy 2011-2026 maintains a commitment to deliver local transport improvements across Nottingham’s Neighbourhoods and prioritises small scale transport improvements of importance to local communities. 1.2 As part of the budget process Nottingham City Council approved in March 2013 an LTP capital allocation of £2.5 million citywide between 2013-2015.
1.3To give opportunity for the Area Committee to make comment on suggested schemes and their progress.
2. BACKGROUND (INCLUDING OUTCOMES OF CONSULTATION)
2.1The Area Capital Programme was established to improve the environment of the neighbourhoods and to create a sense of place for residents in order to improve the quality of life of local people. Since it was established in 2006 to meet the then corporate priority of ‘Transforming Neighbourhoods’, the Area Capital Fund has included a total programme expenditure portfolio of £40 million. The improvements that have been carried out to date using this programme, have included: footpaths, fences, visual enhancements to public realm, refurbishment of parks and improvements to public buildings.
2.2Resources are allocated from the Nottingham City Council general fund, the Local Transport Plan (LTP) and from the Housing revenue Account. To achieve a joint approach to environmental improvements in neighbourhoods, a greater degree of flexibility has been established to prioritise and deliver improvements so that there is a synergy in local solutions for local issues across neighbourhoods.
2.3The programme of works is a rolling programme. There have been instances where schemes are started, with strong community involvement and interest, only to be altered at a later stage due to changing circumstances such as economic conditions and changes in land values.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.