CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Nottingham City Council
Area 8 Committee, Wednesday 10 September 2014 at 7.00pm

AREA CAPITAL FUND 2013-15

Approved Committee 1 paper

Area 8 Committee approved this item on Wednesday 10 September 2014. Below is the council's own wording, with the papers it was decided on.

Item23

Resolved

RESOLVED to approve the following schemes and note the money available: Bridge Ward: Location Type Amount Start Date Details Local Transport Plan (LTP) Schemes None Public Realm Schemes Ryeland Gardens subway Subway painting £573 Painting of the subway Area Capital Decommitments None 2013-15 LTP allocation £120,000 LTP carried forward from 2011-13 £0 2013-14 Public Realm allocation ££36,000 Public Realm carried forward £0 2014-15 Public Realm allocation £36,000 Total available 2013-15 £192,000 Less LTP schemes £115,275 Less Public Realm schemes £32,788 Decommitted funds £0 Remaining available balance £43,937 LTP element remaining £4,725 Public Realm element remaining £39,212 Clifton North Ward: Location Type Amount Start Date Details Local Transport Plan (LTP) Schemes Main Road , Wilford Footpath £30,000 Footpath resurfacing Grove Estate Footpath £14,665 Continuation of large scale footpath patching around Locksley Lane/Wichnor Close Midhurst Way Parking £20,136 Implementation of a parking scheme (jointly funded with NCH) Clifton Grove Parking £4,000 Research and installation of a parking restriction scheme Public Realm Schemes Bridgenorth Drive/Carew Park Gating £1,300 Installation on 2 gates on alleyways (partly funded with NCH) Main Road/Cribb Close Area improvement £17,934 Protect Wilford Village Green by installing an overrun strip and carriage way overlay. Also at the rear of Cribb Close remove slabs and replace with tarmac and create a new footpath Clifton Central Park Area improvement £5,000 Installation of park benches and other improvements Area Capital Decommitments Glapton Lane Lining £500 Scheme not progressing 2013-15 LTP allocation £96,000 LTP carried forward from 2011-13 £10,026 2013-14 Public Realm allocation £28,800 Public Realm carried forward £0 2014-15 Public Realm allocation £28,800 Total available 2013-15 £163,626 Less LTP schemes £92,001 Less Public Realm schemes £53,128 Decommitted funds £594 Remaining available balance £19,091 LTP element remaining £14,525 Public Realm element remaining £4,566 Clifton South Ward: Location Type Amount Start Date Details Local Transport Plan (LTP) Schemes Summerwood Lane Footpath £49,459 Resurface the footpath on the east side from Farnborough Road to Breckswood Drive Barbury Drive Feasibility Study £3,000 Study to develop options for organised parking facilities and associated environmental improvements (joint with NCH) Public Realm Schemes Summerwood Lane Footpath £4,531 Resurface the footpath on the east side from Farnborough Road to Breckswood Drive Area Capital Decommitments Tintagel Green Footpath £9,800 Work completed as part of an earlier scheme 2013-15 LTP allocation £118,000 LTP carried forward from 2011-13 -£1,237 2013-14 Public Realm allocation £35,400 Public Realm carried forward £4,655 2014-15 Public Realm allocation £35,400 Total available 2013-15 £192,218 Less LTP schemes £126,563 Less Public Realm schemes £36,007 Decommitted funds £9,800 Remaining available balance £39,448 LTP element remaining £0 Public Realm element remaining £39,448
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Area 8 Committee

Reasons for recommendations

1.1The Nottingham LTP 2011-2026 maintains a commitment to deliver local transport improvements across Nottingham’s Neighbourhoods and prioritises small scale transport improvements of importance to local communities

As part of the budget process Nottingham City Council has approved an LTP capital allocation of £2.5 million citywide for the next two years 2013-2015.

To give opportunity for the Area Committee to make comment on suggested schemes and their progress

Area Capital Fund schemes, including the Local Transport Plan (LTP) element, have been identified through various methods including consultation, Citizen feedback via Councillors Casework and partnership working.

2 BACKGROUND (INCLUDING OUTCOMES OF CONSULTATION)

2.1The Area Capital Programme was established to improve the environment of the neighbourhoods and to create a sense of place for residents in order to improve the quality of life of local people. Since it was established in 2006 to meet the then corporate priority of “Transforming Neighbourhoods” the Area Capital Fund has included a total programme expenditure portfolio of £40 million. The improvements that have been carried out to date using this programmed have included footpath, fences, visual enhancements to public realm, refurbishment of parks and improvements to public buildings.

2.2Resources are allocated from the Nottingham City Council general fund, the Local Transport Plan (LTP) and from the Housing revenue Account. To achieve a joint approach to environmental improvements in neighbourhoods, a greater degree of flexibility has been established to prioritise and deliver improvements so that there is a synergy in local solutions for local issues across neighbourhoods.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AREA CAPITAL FUND 2013-15Report 497 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 16 attended
PS
Parbinder SinghOfficer, in attendance
AG
Abdul GhaffarOfficer, in attendance
PB
Prairie BryantOfficer, in attendance
MD
Mary DalyPublic, in attendance
MS
Margaret SpencerPublic, in attendance
JD
Jacky DobsonPublic, in attendance
IN
Inspector Nick WaldramPublic, in attendance
ME
Councillor Michael EdwardsChair, present
CG
Councillor Chris GibsonCommittee Member, present
IM
Councillor Ian MalcolmCommittee Member, apologies (council business)
JP
Councillor Jeannie PackerCommittee Member, absent
NH
Councillor Nicola HeatonCommittee Member, present

All 16 on the meeting page

On this subject at Nottingham

Search all
  1. AREA CAPITAL FUND 2013-15This decision
  2. Area Capital Fund Allocation for Highways and Transport - Key DecisionApproved
  3. Area Capital FundApproved
  4. Area Capital Fund ReportNoted
  5. Area Capital Fund 2020/21Approved
  6. Area Capital Fund ReportApproved

More from Nottingham Area 8 Committee

All decisions
MeetingDecisionOutcome
13 Mar 2019 Police updateRESOLVED to thank PCSO Holden for the information provided. Decided Open
13 Mar 2019 Community Protection updateRESOLVED to thank CPO Clancy for the information provided. Decided Open
13 Mar 2019 Ward ReportsRESOLVED to note the progress on ward priorities and other supporting information including the issues being addresse... Noted Open
13 Mar 2019 Nottingham City Homes updates and approvalsRESOLVED to (1) note the update and performance information in the report and its appendices; (2) note the allocation... Noted Open
13 Mar 2019 Clifton Town Centre updateRESOLVED to thank Mark for the information provided and his hard work improving Clifton in recent years. Decided Open