Carrington Street Area Townscape Heritage Project - Key Decision

Approved Executive 7 papers

Executive Board approved this item on Tuesday 21 July 2015. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

RESOLVED to (1) approve the submission of the Stage Two Heritage Lottery Fund bid to seek funding to the value of £682,450 and delegate authority to the Deputy Chief Executive/Corporate Director for Development and Growth to accept the grant if the bid is successful; (2) agree to the City Council providing match funding of £373,375, detailed in Appendix D of the report, to be managed through the identified funding below, noting that further approval will be sought for between 25% and 45% match funding contributions if grant assistance is taken up for capital works to buildings owned by the City Council: Capital Works to properties in the Townscape Heritage area £1,270,100 Revenue Running costs (over 5 years) £202,700 TOTAL COST £1,472,800 Financed by: Heritage Lottery Fund grant £682,450 Property owners match contribution £416,975 Good to Great resources £50,000 Existing Development Management revenue budget (over 5 years) £323,375 (3) delegate authority to the Deputy Chief Executive/Corporate Director for Development and Growth, in consultation with the Portfolio Holder for Jobs, Growth and Transport, to approve grants up to the value of £200,000 for capital works on buildings within the designated area, as detailed in Appendix A of the report; (4) delegate authority to the Head of Development Management to approve spend and enter into any contracts that relate to the activities outlined within the activity statement in Appendix B of the report; (5) approve the budget of £131,000 to appoint a Townscape Heritage Project Manager, as outlined in Appendix E of the report, noting that a separate staffing decision will be taken to establish the post. Reasons for decisions The project will improve the physical appearance of buildings in the area and support the regeneration of an economically disadvantaged historic area, for the benefit of local residents, workers and visitors. The buildings in the area are in need of investment and improvement and the project will help to encourage property owners to restore the heritage character of their buildings. Private owners have expressed strong interest in grant funding of between 60% and 75% and discussions have confirmed that the grant would comfortably be spent. Other options considered Not submitting the Stage Two bid was rejected as the Council already passed the first round and failure to submit the bid would prevent an award of £682,450 grant funding.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Equality Impact Assessment Form (Page 1 of 2)

Title of EIA/ Executive Board Report: Approval to proceed with Heritage Lottery Stage Two Bid Name of Author: Helen Wallace Department: Development and Growth Director: David Bishop Service Area: Planning Services Strategic Budget EIA Y/N (please underline) Author (assigned to Covalent):

Brief description of proposal / policy / service being assessed: To deliver a Townscape Heritage Pr oject in the Carrington Street Area of the City. The aims of which will be to undertake capital grant works to reinstate and restore architectural features to properties in and around the Carrington Street Area.

I t i s p r o p o s e d t h a t t h e w o r k s w i ll i m p r o v e t h e f i r s t i m p r e s s i o n s of vi s i t o r s t o t h e C i t y C e n t r e , i n c r e a s e t h e f o o t f a l l a n d p r o v i d e training and development opportunities to a number of local people, businesses’ and community groups. This will be u n d e r t a k e n t h r o u g h t h e d e l i v e r y o f t h e a c ti v i t y p l a n , w h i c h w i l l a ll o w a n u m b e r o f o r g a n i s e d , a c c e s s i b l e a n d f u n d e d a c t i v it i e s to take place.

I f t h e s u b m i s s i o n o f t h e S t a g e T w o H e r i t a g e L o t t e r y F u n d ( H L F ) g r a n t i s s u c c e s s f u l i t w i ll a ll o w b o t h t h e C i t y C o u n c i l t o c o n s i d e r g r a n t a p p l i c a t i o n s f o r c a p i t a l w o r k s a n d c o m m e n c e w it h t h e d e l i v e r y o f t h e a c t i v i ti e s i n c l u d e d w i t h i n t h e p l a n .

This is a 5 year programme to which a specialist and experienced member of staff will be recruited to, which will ensure both e q u a l i t y a n d d i v e r s i t y i s a d d r e s s e d w h e n d e l i v e r i n g a c t i v i ti e s a n d t r a i n i n g e v e n t s .

Information used to analyse the effects on equality: nd rd Click once and type. Note any relevant consultation and who took part; refer to or hyperlink to document(s) if needed. 2 and 3 June 2015 (initially but more to follow during the life of the project)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Carrington Street Area Townscape Heritage Designated AreaAppendix A 249 KB Download
PDF
Draft Activity StatementAppendix B 298 KB Download
PDF
Estimates for Capital Works and PrioritiesAppendix C 195 KB Download
PDF
Financial BreakdownAppendix D 98 KB Download
PDF
Project Running CostsAppendix E 7 KB Download
PDF
Carrington Street Area Townscape Heritage Project: Key DecisionDecisions 202 KB Download
PDF
Equality Impact AssessmentReport 123 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
GC
Councillor Graham ChapmanVice Chair, present
AC
Councillor Alan ClarkCommittee Member, present
JC
Councillor Jon CollinsChair, apologies (on leave)
NH
Councillor Nicola HeatonCommittee Member, apologies (unwell)
NM
Councillor Nick McDonaldCommittee Member, present
DM
Councillor David MellenCommittee Member, present
AN
Councillor Alex NorrisCommittee Member, present
DT
Councillor Dave TrimbleCommittee Member, present
JU
Councillor Jane UrquhartCommittee Member, present
SW
Councillor Sam WebsterCommittee Member, present
LW
Laura Wilson - Constitutional ServicesClerk, in attendance

On this subject at Nottingham

Search all
  1. Carrington Street Area Townscape Heritage Project - Key DecisionThis decision
  2. Letting of premises at 3, 5, 7, 9 & 11 Carrington Street, Nottingham, NG1 7EQApproved
  3. Former industrial site to west of car park, oak street, carringtonDecided

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open