RESOLVED (1) to approve the following schemes: Location Scheme Cost (£) Aspley Green Parking Bay 1 Green Parking Bay 4 ) ) Aspley Parking Programme - - 60,000 34,000 Bilborough Oakmead Avenue - Improvement - 17,912 Leen Valley Ennismore Gardens ) Footpath - 18,394 Cherrywood Drive Area ) - 9,198 School Road Safety - Signage / lining - 1,300 Canterbury Road - Signage - 1,250 (2) to note the remaining unallocated Area Capital Fund 2015/16 and NCH Environmental Improvement monies of Aspley (£39,945), Bilborough (£110,531) and Leen Valley (£36,499).
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
1.1The Nottingham Local Transport Plan (LTP) Strategy 2011-2026 maintains a commitment to deliver local transport improvements across Nottingham’s Neighbourhoods and prioritises small scale transport improvements of importance to local communities.
1.2As part of the budget process Nottingham City Council approved in March 2015 a Local Transport Plan capital allocation of £1.25 million citywide between 2015-2016.
1.3To give opportunity for the Area Committee to make comment on suggested schemes and their progress.
2. BACKGROUND (INCLUDING OUTCOMES OF CONSULTATION)
2.1The Area Capital Programme was established to improve the environment of the neighbourhoods and to create a sense of place for residents in order to improve the quality of life of local people. Since it was established in 2006 to meet the then corporate priority of ‘Transforming Neighbourhoods’, the Area Capital Fund has included a total programme expenditure portfolio of £40 million. The improvements that have been carried out to date using this programme have included: footpaths, fences, visual enhancements to public realm, refurbishment of parks and improvements to public buildings.
2.2Resources are allocated from the Nottingham City Council general fund, the Local Transport Plan and from the Housing Revenue Account. To achieve a joint approach to environmental improvements in neighbourhoods, a greater degree of flexibility has been established to prioritise and deliver improvements so that there is a synergy in local solutions for local issues across neighbourhoods.
2.3The programme of works is a rolling programme. There have been instances where schemes are started, with strong community involvement and interest, only to be altered at a later stage due to changing circumstances such as economic conditions and changes in land values.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.