New Build Tender Awards for sites in the Building a Better Nottingham Council House Programme - Key Decision

Approved Executive 2 papers

Executive Board approved this item on Tuesday 20 October 2015. Below is the council's own wording, with the papers it was decided on.

Item40

Resolved

RESOLVED to (1) approve the additions of four new build schemes and associated costs to the Public Sector Housing Revenue Account (HRA) Capital Programme: (a) Hazel Hill - £2.890 million; (b) Oakford Close - £2.500 million; (c) Conway Close - £1.315 million; (d) Hazel Hill Crescent - £0.395 million; (e) Nottingham City Homes fees - £0.071 million; and (f) the acquisition of Hazel Hill land - £0.300 million; (2) delegate authority to the Deputy Chief Executive/Corporate Director for Development and Growth, in consultation with the Portfolio Holder for Planning and Housing, to award the new build tenders for the four sites (Hazel Hill, Hazel Hill Crescent, Oakford Close and Conway Close), and sign the contracts, subject to tenders being returned within the total funding envelope of £7.171 million; (3) approve the use of £0.051 million of Homes and Community Agency Affordable Homes Programme 2015-18 grant to part fund the Hazel Hill Crescent scheme; (4) approve the use of £0.867 million of retained Right to Buy 1-4-1 receipts to support the development of Hazel Hill, Oakford Close and Conway Close; (5) approve the transfer of £0.300 million from the HRA Capital Programme to the Property Trading Account as payment for the Hazel Hill site and the demolition of the existing property. Reasons for decisions To enable the Council to realise its ambition to provide high quality housing and actively regenerate neighbourhoods. The awarding of the contracts will allow new homes to be delivered within the existing housing programme. Other options considered Not redeveloping the sites was rejected because of the Council’s ambition to provide high quality housing and regenerate neighbourhoods. Selling the sites for market housing development was rejected as the provision of council homes in these locations will ensure the Council can regenerate communities, and one of the sites has been returned by a developer after only 50% of the site was developed. Disposing of all the sites to a Registered Provider partner, for a reduced receipt in order for them to provide new affordable housing, was rejected because the sites are not marketable, and Hazel Hill has been given up by a Registered Provider.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Equality Impact Assessment Form (Page 1 of 2)

Title of EIA/ DDM: Approval to proceed with the new build tender awards for sites in the Building a Better Nottingham: Council Housing Programme Name of Author: Robert Caswell Department: Development Director: David Bishop Service Area: Major Programmes Strategic Budget EIA Y/N (please underline) Author (assigned to Covalent): Not Applicable

Brief description of proposal / policy / service being assessed: The Building a Better Nottingham: Council Housing Programme will improve housing for older people and will promote integration and regeneration within the Aspley, Bestwood and St Ann’s wards.

Information used to analyse the effects on equality: This project will affect the Aspley, Bestwood and St Ann’s wards. The Building a Better Nottingham: Council Housing Programme aims to remove council houses which are in the worst condition and the least popular in the City.

Could May Details of actions to reduce How different groups particularly adversely negative or increase could be affected benefit impact positive impact (Summary of impacts) X X (or why action isn’t possible) People from different ethnic This project will affect the housing The new housing development will groups. provision in the Aspley, Bestwood improve integration within the area Men and St Ann’s wards and will promote and will regenerate the integration and regeneration. These neighbourhood. Women wards are ranked 1st, 5th and 2nd Trans most deprived wards in the City. The sites are currently vacant and Disabled people or carers. present opportunities for anti-social The four schemes proposed are all behaviour. The development of Pregnancy/ Maternity older people’s bungalow schemes these sites will assist to reduce crime People of different faiths/ beliefs and will have a shared community and disorder in the areas. and those with none. room. The homes will be a mix of Lesbian, gay or bisexual people. one and two bedroom bungalows, The provision of specific older which will support people looking to peoples housing will assist to free up Older downsize which in turn will free up family housing that may be currently Younger larger family properties for occupied by this group and will allow reallocation. more families to move into the areas Other (e.g. marriage/ civil partnership, looked after children, to promote integration. cohesion/ good relations, At present there are over 3,000 vulnerable children/ adults). tenants aged 60 and above living in The proposal supports the Council’s NCH houses across the City, pledge to improve housing by Please underline the group(s) therefore full occupation of the replacing council housing that is in /issue more adversely affected bungalows is anticipated. poor condition and the least popular or which benefits. in the City. The new homes provided will be high quality bungalows for older people, which will address the Council’s commitments for these sites. The housing will be energy efficient and will have a lower carbon foot print and will result in reduced energy bills for the tenants.

Outcome(s) of equality impact assessment: •No major change needed •Adjust the policy/proposal •Adverse impact but continue •Stop and remove the policy/proposal

Arrangem ents for future monitoring of equality im pact of this proposal / policy / service: Consultation with the local community will be progressed to assist with the development / proposal.

Approved by (m anager signature): Date sent to equality team for publishing: Robert Caswell 22/09/2015 Programme Manager 0115 8763408 [email protected]

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EIAReport 116 KB DownloadRead as text
PDF
New Build Tender Awards for sites in the Building a Better Nottingham Council House Programme: Key DecisionDecisions 214 KB Download

At this meeting

Whole meeting

Who was there

7 of 11 attended
GC
Councillor Graham ChapmanVice Chair, present
AC
Councillor Alan ClarkCommittee Member, apologies (council business)
JC
Councillor Jon CollinsChair, present
NH
Councillor Nicola HeatonCommittee Member, present
NM
Councillor Nick McDonaldCommittee Member, apologies (council business)
DM
Councillor David MellenCommittee Member, present
AN
Councillor Alex NorrisCommittee Member, apologies (council business)
DT
Councillor Dave TrimbleCommittee Member, present
JU
Councillor Jane UrquhartCommittee Member, present
SW
Councillor Sam WebsterCommittee Member, present
LW
Laura Wilson - Constitutional ServicesClerk, in attendance

On this subject at Nottingham

Search all
  1. New Build Tender Awards for sites in the Building a Better Nottingham Council House Programme - Key DecisionThis decision
  2. Amendment to Capital Programme - United Reformed Church New Build SchemeApproved
  3. Amendment to Capital Programme - Laura Chambers Lodge New Build SchemeApproved
  4. Lease Renewal - Part of Building No. 3, and Building No. 7, Woolsthorpe Depot, Bilborough NottinghamApproved
  5. Lease renewal - alexander fleming building, nottingham science parkApproved
  6. New Build Tender Awards for Meadows and Cranwell Road - Key DecisionApproved

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies