Resolved
RESOLVED to: (1) note the update on the implementation of the Tri-Service Control system; (2) ask that a further update comes to next Policy and Strategy meeting.
Nottingham Fire and Rescue Authority - Policy and Strategy noted this item on Friday 29 January 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to: (1) note the update on the implementation of the Tri-Service Control system; (2) ask that a further update comes to next Policy and Strategy meeting.
To update Members on the progress of implementation of the Tri-Service Control project in conjunction with Leicestershire and Derbyshire Fire and Rescue Services.
CONTACT OFFICER
John Buckley Name : Chief Fire Officer Tel : 0115 967 0880
Email : [email protected]
Media Enquiries Therese Easom Contact : (0115) 967 0880 [email protected] 1. BACKGROUND
1.1At the Fire Authority meeting on 14 December 2012, Members considered a report from the Chief Fire Officer confirming that the collaborative partnership bid from Nottinghamshire, Derbyshire and Leicestershire Fire and Rescue Authorities had secured £5.4 million grant from Government to progress the procurement of a replacement command and control system.
1.2This successful bid led to the creation of the Tri-Service Control Project and subsequent tender for a supplier to replace the three legacy systems within the tri-service area. A further £247k was committed from each authority to bring the total project value to £6.1 million.
1.3A report was presented to the Policy and Strategy Committee on 13 November 2015 providing an update on progress with the implementation of the new system and this report continues that information stream and considers the next phase of the project.
2. REPORT
2.1The overarching concept of the Tri-Service Control programme is that a single common mobilising system would be used in all three control facilities and interlinked by means of a network. The philosophy of this being that any of the control rooms can take calls and mobilise appliances and resources for each other. This provides significant resilience and removes the need to operate a secondary or fall-back control facility for each of the services, thereby generating an immediate efficiency.
2.2As previously reported the project has faced slippage, however the main mobilising system has been in operation across the three services since September 2015. In the period since going live there have been a number of issues with the system where it has failed to operate as required. As with any new and complex system, these type of events were anticipated and planned contingency measures were put in place. Work by the supplier and Tri-Service staff in the intervening period has improved the stability of the system to a satisfactory level.
2.3Whilst go-live has been achieved there are a number of improvements and developments to be delivered before the system fully meets the requirements of the specification agreed with the supplier. Some of these are minor in nature, whilst others are significantly larger and include:
A dynamic cover tool to relocate resources to meet demand during busy periods; An electronic incident management system to enhance information collection and sharing an operational incidents; A replacement for the Incident Reporting System (IRS); An update of the gazetteer to reflect changes by Ordnance Survey; Enhancing the ability to make adjustments to individual operator positions to meet the needs of staff.
2.4These larger items form an aspect within the project known as ‘Phase 2’ for which the precise detail is currently being worked up in conjunction with the supplier. This means that the project will continue into 2016/17 financial year to deliver the required improvements and developments before it can be formally closed.
2.5The delay to go-live of the mobilising system has almost exhausted the financial provisions that were put in place, especially in respect of staffing costs. A consequence of the delay is that resource, including dedicated staffing, will need to be committed into 2016/17 to continue to work with the supplier to oversee and implement the outstanding improvements.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
TRI-SERVICE CONTROL PROJECT UPDATEReport | 149 KB | DownloadRead as text |
Follow Nottingham Fire and Rescue Authority - Policy and Strategy at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 May 2026 | Exclusion of the PublicResolved to exclude the public from the meeting during consideration of the remaining items in accordance with Sectio... | Decided | Open |
| 15 Nov 2024 | Service Improvement - Futures 25 Closure ReportResolved to note the contents of the report. | Noted | Open |
| 15 Nov 2024 | Exclusion of the publicResolved to exclude the public from the meeting during consideration of the remaining items in accordance with Sectio... | Decided | Open |
| 26 Apr 2024 | Governance ArrangementsResolved to note (1) The arrangements with regard to the direct employment of the Clerk and Monitoring Officer. (2) T... | Noted | Open |
| 26 Apr 2024 | 10-Year Workforce Diversity PlanningResolved to (1) Endorse a long-term commitment to workforce diversity via a 10-year Diversity Plan. (2) Note the cont... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.