Building Services, Mechanical And Electrical Team Procurement Requirements – 2020-24
ApprovedExecutive1 paper
Commissioning and Procurement Executive Committee approved this item on Tuesday 14 January 2020. Below is the council's own wording, with the papers it was decided on.
RESOLVED to (1) approve the procurement of Framework Agreements in line with Public Procurement Regulations 2015; (2) delegate authority to the Head of Service for Building Services to approve the outcome of the procurement processes and award Framework Agreements in line with criteria as set out within the tender documentation; (3) delegate authority to the appropriate person within Building Services in line with the Financial Regulations, to call off from the Framework Agreements. Reasons for decision · NCC adopts a mixed approach to the delivery of M&E work that utilises the Council’s own skilled workforce and fully supports the City Council’s ambitious commercialisation agenda. · Procuring the Frameworks will result in the following advantages: o a value for money delivery model with no fixed financial commitment to use the framework; o opportunities for local Small to Medium Enterprise (SME) companies to tender for the work; o the potential for a local workforce either through direct employment or through regional SME sub-contractors. · The delivery model has a number of additional benefits including: o strong links to the Council’s corporate value and objectives; o a highly flexible and responsive structure to accommodate short term changes to design programmes; o local knowledge available in the planning and assessment of proposed works. Other options considered · Do nothing – no authorised procurement is in place for the provision of specialist services and as such would not be compliant with Nottingham City Council’s Financial Regulations and Public Procurement Regulation 2015. · Insource all of the activity covered by the contract areas under consideration for renewal – this option has been rejected due to the following; capacity, complexity, risk and value for money.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Report to Commissioning and Procurement Executive Committee
COMMISSIONING AND PROCUREMENT SUB-COMMITTEE – 14/01/2020
Subject: Building Services, Mechanical And Electrical Team Procurement Requirements – 2020-24 Corporate Andy Vaughan, Corporate Director for Commercial & Operations Director(s)/ Dave Halstead, Director of Neighbourhood Services Director(s): Portfolio Holder(s): Councillor Sally Longford, Portfolio Holder Energy, Environment and Democratic Services Report author and Mark Bradbury, Infrastructure Delivery Manager contact details: Tel: 0115 876 1353 Email: [email protected] David King, Head of Building Services Tel: [phone removed] Email: [email protected] Key Decision Yes No Subject to call-in Yes No Reasons: Expenditure Income Savings of £1,000,000 or Revenue Capital more taking account of the overall impact of the decision Significant impact on communities living or working in two or more Yes No wards in the City Total value of the decision: £14.85 m Wards affected: All Date of consultation with Portfolio Holder(s): 7th Jan 2020 Relevant Council Plan Key Theme: Nottingham People Living in Nottingham Growing Nottingham Respect for Nottingham Serving Nottingham Better Summary of issues (including benefits to citizens/service users): This report sets out the requirements for Nottingham City Council (NCC), Building Services Mechanical and Electrical (M&E) team to procure multiple Frameworks to enhance the expanding service requirements. The 6 specific frameworks that will be procured are as detailed below. The benefit of this approach is being able to enhance the specialist M&E team maximising the delivery of internally led works and supporting the team in periods of peak workload
Building Services at NCC has a core M&E team. The delivery of works by this team is key to NCC’s commercialism strategy, in-sourcing works where it is economically advantageous to do so. To support the existing team it is essential to have access to a supply chain that is encompassed within a framework to deliver value for money, whilst improving the local spend, therefore enhancing local employment opportunities.
The frameworks will allow the M&E team to support the existing workforce. The Frameworks will benefit the team by allowing specialist services to complement a professional delivery team both on site and within office operations.
1. Electrical Support Framework (£1m over 4 years): This framework will consist of but not limited to the following disciplines; Electrician
2. Mechanical Support Framework (£2.5m over 4 years): Plumber Domestic Gas Engineer Commercial Gas Engineer Mechanical Fitter
With these services/disciplines it will allow the team to expand the current workforce as required where work commitments exceeds that of the internal team.
3. Electrical Contracting Supply and Install Framework (£5m over 4 years): This framework will consist of, but not limited to the following; Electrical Supply and Install Electrical Testing
4. Mechanical Contracting Supply and Install Framework (£4.8m over 4 years): This framework will consist of, but not limited to the following; Mechanical Supply and Install Out of Hours Call Out
These Frameworks will enable the team to manage more commercially execute demanding m&e projects, with the benefit of going to the local market to support the workforce. Where the DLO is at capacity with existing requirements, the team will have the ability to outsource and manage accordingly.
5. Flue Fabrication and Install Framework (£0.3m over 4 years): This framework will consist of, but not limited to the following; Fabrication and install of specialist flue systems
This framework will allow the team to maximise the delivery of mechanical install by enabling installation works requiring this specialist element to be delivery by the current in-house team.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Commissioning and Procurement Executive Committee at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
Agency Worker contract - key decisionResolved to (1) approve a tender process be undertaken to procure a corporate agency worker contract, with a maximum ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.