Basford and Bestwood Area Committee approved this item on Wednesday 25 May 2016. Below is the council's own wording, with the papers it was decided on.
RESOLVED (1) to approve the following schemes for Bestwood: Location Scheme Cost Arnold Road shops (Landcroft Crescent) TRO study - parking issues around shops £8,525 Arnold Road shops (Leen Valley) TRO - construction of layby £22,000 (2) to note the end of year 2015/16 positions and available balances for 2016/17 as follows: Basford £ 2016/17 LTP allocation 64,900 LTP carried forward from 2015/16 0 2016/17 Public Realm allocation 38,900 Public Realm brought forward from 2015/16 13,312 Total available 2016/17 117,112 Bestwood £ 2016/17 LTP allocation 75,400 LTP carried forward from 2015/16 0 2016/17 Public Realm allocation 45,200 Public Realm brought forward from 2015/16 8,805 Total available 2016/17 129,405 Less LTP schemes 30,525 Total remaining available 2016/17 balance 98,880
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
1.1The Nottingham LTP 2011-2026 maintains a commitment to deliver local transport improvements across Nottingham’s Neighbourhoods and prioritises small scale transport improvements of importance to local communities. 1.2 As part of the budget process Nottingham City Council approved at the Executive Board meeting on 23 February 2016 an LTP capital allocation of £1.25 million citywide between 2016-17. At the same meeting a citywide allocation of General Fund Element (public realm) of £750,000 was agreed.
1.3To give opportunity for the Area Committee to make comment on suggested schemes and their progress
2 BACKGROUND (INCLUDING OUTCOMES OF CONSULTATION)
2.1The Area Capital Programme was established in 2006 to improve the environment of the neighbourhoods and to create a sense of place for residents in order to improve the quality of life of local people. The improvements that have been carried out to date using this programme, have included: footpaths, fences, visual enhancements to public realm, refurbishment of parks and improvements to public buildings.
2.2Resources are allocated from the Nottingham City Council general fund and the Local Transport Plan (LTP). To achieve a joint approach to environmental improvements in neighbourhoods, a greater degree of flexibility has been established to prioritise and deliver improvements so that there is a synergy in local solutions for local issues across neighbourhoods.
2.3The programme of works is a rolling programme. There have been instances where schemes are started, with strong community involvement and interest, only to be altered at a later stage due to changing circumstances such as economic conditions and changes in land values.
2.4The Area Committee, particularly community representatives, are invited to comment specifically on those schemes identified in the proposals column and also to consider whether certain schemes can be linked to other programmes of work in order to generate best value and create a greater impact on the local area.
3 OTHER OPTIONS CONSIDERED IN MAKING RECOMMENDATIONS
3.1None.
4 FINANCE COMMENTS (INCLUDING IMPLICATIONS AND VALUE FOR MONEY/VAT)
4.1Bringing together the various strands which form part of the Area Capital Programme enables the City Council to respond efficiently in delivering on public realm improvements as identified by local people.
5 LEGAL AND PROCUREMENT COMMENTS (INCLUDING RISK MANAGEMENT ISSUES, AND LEGAL, CRIME AND DISORDER ACT AND PROCUREMENT IMPLICATIONS)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Police and Community Protection updateRESOLVED to note the update and, further to minute 28, reiterate the thanks of the Committee and community to all tho...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.