RESOLVED to: (1) note the monies available: Dales - £68101 Mapperley - £64900 St Ann’s - £107084 (2) note and approve the following schemes as added to at the meeting: Dales LTP Location Type Estimate Details Sneinton Hermitage Footpath £15,713 Excavate footpath and replace kerbs with a lower face to allow drainage cross fall – lead service: Highway Maintenance Greenwood Academy Road Safety £2,200 Further contribution to previously agreed scheme – lead service: Traffic & Safety Dales Ward bins Litter Bins £5,500 Installation of eleven litter bins at identified sites in the Dales Ward – lead service: Streetscene Dales Public Realm Location Type Estimate Details North Sneinton Dale Area Improvement £5,000 Additional contribution to area improvement in North Sneinton Dale area – lead service: Neigbourhood Management Colwick Country Park Area Improvement £2,900 Provision of a kick-about area on Colwick Country Park Mapperley LTP Location Type Estimate Details Mapperley Ward Footpaths £40,624 Contribution to large scale footpath patching works on Richmond Drive, Old Hall Drive and Zulla Road (LTP contribution) – lead service: Highway Maintenance Mapperley Public Realm Location Type Estimate Details Mapperley Ward Footpaths £1,736 Contribution to large scale footpath patching works on Richmond Drive, Old Hall Drive and Zulla Road (PR contribution) – lead service: Highway Maintenance Querneby Road area Study £5,500 Study to address issues around parking and moving traffic in the Querneby Road area – lead service: Traffic and Safety St Ann’s Public Realm Location Type Estimate Details King Edward’s Park Park Improvements £20,000 Further contribution to previously approved scheme – lead service: Parks and Open Spaces Massey Gardens Area Improvement £25,593 Contribution to NCH area improvement scheme on Massey Gardens – lead Service: NCH
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Report to Area Committee East (A.C.E) Dales, St Ann's & Mapperley
AREA COMMITTEE EAST (ACE) (Dales, Mapperley, St Ann’s) – 13th September 2016
Title of paper: AREA CAPITAL FUND - 2016/17 Programme Director(s)/ Andy Vaughan Wards affected: Corporate Director(s): Corporate Director of Commercial and Dales, Mapperley & Operations St Ann’s Contact Officer(s) and contact Greg Foister details: Neighbourhood Development Officer – Dales Ward 0115 8839807 [email protected] Fi Cusick Neighbourhood Development Officer – Mapperley Ward 0115 8839728 [email protected] Michelle Graley Neighbourhood Development Officer – St Ann’s Ward 0115 8839808 [email protected]
Other officers who have Nancy Hudson, Projects Officer, Highway Services provided input: Tel: 0115 8765633 Nancy. [email protected]
Relevant Council Plan Strategic Priority: Cutting unemployment by a quarter Cut crime and anti-social behaviour Ensure more school leavers get a job, training or further education than any other City Your neighbourhood as clean as the City Centre Help keep your energy bills down Good access to local transport Nottingham has a good mix of housing Nottingham is a good place to do business, invest and create jobs Nottingham offers a wide range of leisure activities, parks and sporting events Support early intervention activities Deliver effective, value for money services to our citizens
Summary of issues (including benefits to customers/service users): This report provides Councillors with :- Latest spend proposals under the Area Capital Fund including highways and footways
Recommendation(s): 1 a) Note the monies available to Dales, Mapperley and St Ann’s Wards for 2016/2017 as outlined in Appendix 1. 2 REASONS FOR RECOMMENDATIONS The Nottingham LTP strategy 2011-2026 maintains a commitment to deliver local transport Improvements across Nottingham’s Neighbourhoods and prioritises small scale transport improvements of importance to local communities.
2.1As part of the budget process Nottingham City Council approved in March 2015 an LTP capital allocation of £1.25 million citywide between 2015-2016.
3 BACKGROUND (INCLUDING OUTCOMES OF CONSULTATION)
3.1The Area Capital Programme was established to improve the environment of the neighbourhoods and to create a sense of place for residents in order to improve the quality of life of local people. Since it was established in 2006 to meet the then corporate priority of “Transforming Neighbourhoods” the Area Capital Fund has included a total programme expenditure portfolio of £40 million. The improvements that have been carried out to date using this programme have included footpath, fences, visual enhancements to public realm, refurbishment of parks and improvements to public buildings.
3.2Resources are allocated from the Nottingham City Council general fund, the Local Transport Plan (LTP) and from the Housing revenue Account. To achieve a joint approach to environmental improvements in neighbourhoods, a greater degree of flexibility has been established to prioritise and deliver improvements so that there is a synergy in local solutions for local issues across neighbourhoods.
3.3The programme of works is a rolling programme. There have been instances where schemes are started, with strong community involvement and interest, only to be altered at a later stage due to changing circumstances such as economic conditions and changes in land values.
3.4The Area Committee, particularly community representatives, are invited to comment specifically on those schemes identified in the proposals column and also to consider whether certain schemes can be linked to other programmes of work in order to generate best value and create a greater impact on the local area.
4 OTHER OPTIONS CONSIDERED IN MAKING RECOMMENDATIONS
4.1None
5 FINANCIAL IMPLICATIONS (INCLUDING VALUE FOR MONEY/VAT)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Area Committee East (A.C.E) Dales, St Ann's & Mapperley at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
Area Capital Fund 2018/19 ProgrammeRESOLVED to: (1) Approve the new schemes prioritised by Ward Councillors since the last area committee as detailed be...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.