Basford and Bestwood Area Committee, Wednesday 29 March 2017 at 4.30pm

AREA CAPITAL FUND - 2016/17 Programme

Approved Committee 1 paper

Basford and Bestwood Area Committee approved this item on Wednesday 29 March 2017. Below is the council's own wording, with the papers it was decided on.

Item49

Resolved

RESOLVED (1) to approve the following public realm schemes, prioritised since the last meeting: Basford Cost (£) Bagnall Road - excavate tree pits and repair footpath 1,630 River Leen footpath - lockable bollards / dropped kerb 1,972 Vernon Road - various tree works 7,000 Fenton Road - implementation of bus stop cages 7,250 Bestwood Leybourne Drive - various area improvements 18,361 (2) To note the remaining available balances of £396 (Basford) and £51,268 (Bestwood).
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Basford and Bestwood Area Committee

Reasons for recommendations

1.1The Nottingham LTP 2011-2026 maintains a commitment to deliver local transport improvements across Nottingham’s Neighbourhoods and prioritises small scale transport improvements of importance to local communities. 1.2 As part of the budget process Nottingham City Council approved at the Executive Board meeting on 23 February 2016 an LTP capital allocation of £1.25 million citywide between 2016-17. At the same meeting a citywide allocation of General Fund Element (public realm) of £750,000 was agreed.

1.3To give opportunity for the Area Committee to make comment on suggested schemes and their progress

2 BACKGROUND (INCLUDING OUTCOMES OF CONSULTATION)

2.1The Area Capital Programme was established in 2006 to improve the environment of the neighbourhoods and to create a sense of place for residents in order to improve the quality of life of local people. The improvements that have been carried out to date using this programme, have included: footpaths, fences, visual enhancements to public realm, refurbishment of parks and improvements to public buildings.

2.2Resources are allocated from the Nottingham City Council general fund and the Local Transport Plan (LTP). To achieve a joint approach to environmental improvements in neighbourhoods, a greater degree of flexibility has been established to prioritise and deliver improvements so that there is a synergy in local solutions for local issues across neighbourhoods.

2.3The programme of works is a rolling programme. There have been instances where schemes are started, with strong community involvement and interest, only to be altered at a later stage due to changing circumstances such as economic conditions and changes in land values.

2.4The Area Committee, particularly community representatives, are invited to comment specifically on those schemes identified in the proposals column and also to consider whether certain schemes can be linked to other programmes of work in order to generate best value and create a greater impact on the local area.

3 OTHER OPTIONS CONSIDERED IN MAKING RECOMMENDATIONS

3.1None.

4 FINANCE COMMENTS (INCLUDING IMPLICATIONS AND VALUE FOR MONEY/VAT)

4.1Bringing together the various strands which form part of the Area Capital Programme enables the City Council to respond efficiently in delivering on public realm improvements as identified by local people.

5 LEGAL AND PROCUREMENT COMMENTS (INCLUDING RISK MANAGEMENT ISSUES, AND LEGAL, CRIME AND DISORDER ACT AND PROCUREMENT IMPLICATIONS)

5.1A risk register has been produced which is regularly monitored.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AREA CAPITAL FUND: 2016/17 ProgrammeReport 367 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 10 attended
HM
Heidi MayCouncil Staff, expected
MG
Maria GawdiakCouncil Staff, expected
BG
Councillor Brian GrocockVice Chair, present
CA
Councillor Cat ArnoldCommittee Member, present
AN
Councillor Alex NorrisCommittee Member, present
DS
Councillor David SmithCommittee Member, present
MW
Councillor Michael WildgustChair, apologies (personal reasons)
LW
Councillor Linda WoodingsCommittee Member, present
WA
Wade AdamsOfficer, expected
ML
Mark LeavesleyClerk, in attendance

On this subject at Nottingham

Search all
  1. AREA CAPITAL FUND - 2016/17 ProgrammeThis decision
  2. Area Capital Fund Allocation for Highways and Transport - Key DecisionApproved
  3. Area Capital FundApproved
  4. Area Capital Fund ReportNoted
  5. Area Capital Fund 2020/21Approved
  6. Area Capital Fund ReportApproved

More from Nottingham Basford and Bestwood Area Committee

All decisions
MeetingDecisionOutcome
6 Mar 2019 Police and Community Protection updateRESOLVED to note the update and, further to minute 28, reiterate the thanks of the Committee and community to all tho... Noted Open
6 Mar 2019 Nottingham City HomesRESOLVED (1) to approve the following schemes: Cost Basford Fenton Road – replace front boundary fencing 63,358.58 Be... Approved Open
6 Mar 2019 Area Based GrantsRESOLVED to note the update and, due to forthcoming Area Committee re-alignments, record the thanks of the Committee ... Noted Open
6 Mar 2019 Area Capital FundRESOLVED (1) to approve the following schemes: Scheme Cost Basford - LTP Vernon Avenue – traffic calming 43,089 Basfo... Approved Open
6 Mar 2019 Ward Councillor Budgets / Delegated Authority spendRESOLVED to note the report. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies