Executive Board, Tuesday 19 September 2017 at 2.00pm

Expansion of Middleton Primary School, Wollaton - Key Decision

Approved Executive 4 papers

Executive Board approved this item on Tuesday 19 September 2017. Below is the council's own wording, with the papers it was decided on.

Item39

Resolved

RESOLVED to approve the expansion of Middleton Primary and Nursery School from a 420 place school to a 630 place school, from 1 September 2018. Reasons for decisions Although the city-wide picture for primary place provision is greatly improved, place pressures are still apparent in some areas, Wollaton being one of them. There has been an upward trend of pupil growth in this area and increasingly, there are more applications from within Middleton Primary’s immediate catchment area, than there are places available. In the 2015/16 Reception year, Middleton Primary admitted additional pupils over the Published Admission Number (PAN) of 60. In the 2017/18 Reception year, they will again be admitting additional pupils over the current PAN. A longer term solution is needed to address the sustained growth in pupil numbers. From September 2018, additional teaching, learning and hall space will be required. If Middleton Primary does not expand, there will be insufficient capacity to accommodate the growth in the number of applications from families in the catchment area. In order to meet the need and demand for school places in this area of Wollaton , it is proposed to expand Middleton Primary School from 420 to 630 places. There would be 90 pupils in each year group instead of 60 and the school would grow by one class per year (30 pupils) over a seven year period, until the school is full. One of the 5 key objectives of the Council Plan 2015-19, is to ensure that every child in Nottingham is taught in a school that is judged good or outstanding by Ofsted . The proposal to expand Middleton Primary School also supports the Council priorities of access to a good school close to home for every young person in Nottingham, and to meet parental preferences of places for every child at a local primary school. Parents/ carers quite rightly expect their children to be offered a local school place and the case for expanding a school which delivers a quality provision in an area where there are insufficient school places is a strong one. It is the duty and the desire of both the Council and the School to maximise opportunities to deliver a quality education to the communities we serve. Initial feasibility investigations (approved by Portfolio Holder Decision Ref: 2453) have confirmed that there is space on the site to expand, without compromising the quality of education and facilities. Any new buildings will be designed in collaboration with the school, to complement the existing build and be fit for the future of the growing school community. The school leadership team and the governing body are fully committed in their support for the proposal to expand the school. Extensive considerations have been undertaken by the School Governing Body and staff. Middleton achieves very good results and outcomes for the children who attend and has been rated as a “Good” school by Ofsted. Successful initial feasibility and early design investigations and a full and thorough consultation process with all stakeholders have been undertaken. The number of respondents in support of the proposal to expand the school exceeded the number against. One representation was made during the Statutory Notice stage, which is included at Appendix B, with a full response to the points raised. The full consultation results and summary of responses are included at Appendix A. The initial estimated date of completion for Key Stage One is September 2018 and for Key Stage Two, is December 2019, but this is subject to the completion of full feasibility and design works. The build would be funded by Basic Need funding allocated to the Council by Central Government, for expanding primary place provision. At this stage, it is currently estimated that the expansion of Middleton Primary School would cost £4.1m. The initial estimated date of completion for Key Stage One is September 2018 and for Key Stage Two, is December 2019, but this is subject to the completion of full feasibility and design works. The build would be funded by Basic Need funding allocated to the Council by Central Government, for expanding primary place provision. At this stage, it is currently estimated that the expansion of Middleton Primary School would cost £4.1million. Other options considered Add further temporary bulge years at Middleton Primary, in excess of the Pupil Admission Number. This is not a favourable or feasible option as it would not address the sustained pupil growth in the area and the school have no further capacity to accommodate additional children within the existing space. Other potential school build / expansion options were also considered (Bluecoat and Southwold), but Middleton is the preferred option due to the reasons stated in this report. Do nothing – this is not recommended as additional school places are required in the area. Sustained growth in pupil numbers required a permanent solution to meet the needs of the local community by providing a good school, close to home (as per the Council’s priorities).
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Appendix A – consultation report analysis

Proposal to expand Middleton Primary School from 420 to 630 places from September 2018

Consultation analysis

The stage one consultation on the proposal to expand Middleton Primary ran from Monday 24th April until Friday 19th May 2017, with parents, carers, staff, governors, trade unions, local residents and citizens. The tables below show the number of respondents in each category and the % analysis. This includes those who responded online or completed a paper copy of the consultation response form. Of the 102 people who responded to the consultation, 57% were in support of the proposal, 40% were against it and 3% registered no opinion.

Do you agree Parent / Staff Governor Other\resident Total with the proposal to carer expand Middleton Primary….

Yes 43 8 3 4 58 No 23 1 0 17 41 No opinion 2 0 0 1 3 Total 68 9 3 22 102

Do you agree with the proposal Analysis % to expand Middleton Primary... No Respondents Total Yes No opinion Base 102 57% 40% 3% I am a parent/carer of a 68 63% 34% 3% pupil I am a member of staff 9 89% 11% 0% I am a governor 3 100% 0% 0% Other\resident 22 19% 77% 4% Consultation activities

The table below shows the consultation timetable and the activities which were undertaken:

Date Event Time Venue

24 April Start of consultation (4 weeks) 26th April Meeting for staff & governors 3.45pm School 2nd May Meetings for parents and carers 6-7pm School 3rd May 9-10am 2nd May Community / local residents drop-in Between 3.30 School meeting and 5.30pm 16th May School gates consultation (NCC Between 3 and School gates School Organisation Officer) 4pm 17th May School gates consultation (NCC Between 8.15 School gates School Organisation Officer) and 9.15am Fri 19th May Close of consultation

An information and consultation meeting for staff and governors was held on 26 April. Two information and consultation meetings were held for parents/carers on 2 and 3 May. On the 2 May, we also hosted a Community drop in session for local residents living on Harrow Road, Harrow Gardens and Eaton Grove

Over the course of the meetings, information about the proposal was shared and attendees were invited to ask questions and comment on the proposal. Two ‘school gate consultations’ were also undertaken at the beginning and end of the school day, on the dates listed above.

We also wrote to 87 local residents to consult on the proposal, 22 of whom formally responded. 4 were in support of the proposal,17 opposed and 1 registered no opinion

We provided 500 letters to the school to distribute to parents, to include the Nursery and to account for families having more than one child. The letters contained details of the proposal, the rationale and the various methods and opportunities to engage in the consultation process. The following comments and questions were raised at the various consultation events. Responses have been provided and actions followed up if required:

Comments made / questions raised during the consultation meetings with staff & governors Wednesday 26th April 2017, 15:45 – 16:45

Leadership team and governing body are supportive of the proposed expansion, to meet the school place needs of the local community. Also referred to 1) safeguarding against proposed cuts to school budgets and 2) the leadership and governors are satisfied that the revised budget and design proposals will now meet the requirements of the school to maintain or enhance the standards and ethos.

Q1: Will expanded pupil cohort be admitted at the same time across year groups?

A: No, expansion will happen from the reception year upwards, by an additional class per academic year, over a 7 year period, commencing in September 18. By completion, the current preferred expansion design will create a new foundation unit, but initially anticipate completion of two new classrooms for Sept 18.

Q2: Will nursery numbers be affected by the expansion?

A: Numbers in nursery will remain the same.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
App A. Consultation reportAppendix 510 KB DownloadRead as text
PDF
App B: RepresentationAppendix 73 KB Withheld: personal details
PDF
App C: ResponseAppendix 290 KB Download
PDF
Expansion of Middleton Primary School, Wollaton: Key DecisionDecisions 339 KB Download

At this meeting

Whole meeting

Who was there

9 of 10 attended
GC
Councillor Graham ChapmanVice Chair, present
JC
Councillor Jon CollinsChair, present
SL
Councillor Sally LongfordCommittee Member, present
NM
Councillor Nick McDonaldCommittee Member, present
NM
Noel McMenaminClerk, in attendance
DM
Councillor David MellenCommittee Member, present
TN
Councillor Toby NealCommittee Member, present
DT
Councillor Dave TrimbleCommittee Member, present
JU
Councillor Jane UrquhartCommittee Member, present
SW
Councillor Sam WebsterCommittee Member, present

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies