Loxley House Work Place and Hub Phase 2: Outline Business Case and related Approvals

Approved Executive 3 papers

Executive Board approved this item on Tuesday 16 October 2018. Below is the council's own wording, with the papers it was decided on.

Item37

Resolved

RESOLVED to: (1) approve the Outline Business Case for the Loxley house Work Place and Hub Phase 2 programme of works as outlined at Appendix A to the report; (2) approve the financial model of the project as defined at Appendix B to the report; (3) delegate authority to the Corporate Director for Development and Growth, in consultation with the Leader/Portfolio Holder for Regeneration and Growth, to enter into work contracts, including the procurement of consultants, and to commit any expenditure required during the delivery of the programme, subject to costs being contained within the parameters of the financial model, noting that all requirements will be procured in conjunction with the Procurement Team and in accordance with the Council’s own Contract Procedure Rules and Public Procurement Regulations 2015; (4) approve the establishment of 1 Full-Time Equivalent (FTE) Grade I Change Manager post and 1 FTE Grade H Change Manager post and recruitment to these posts under scheme of delegation number 16, for a fixed term period of 12 months; (5) delegate authority to the Head of Legal Services to amend existing licence agreements to reflect changes and to enter into any service level agreements required to facilitate the programme and protect the interests of the Council; (6) delegate authority to the Corporate Director for Development and Growth, in consultation with the Leader/Portfolio Holder for Regeneration and Growth, to approve the Final Business Case, subject to the value being within the funding envelope set out within the Outline Business Case; (7) delegate authority to the Strategic Director of Finance to opt to tax Loxley House if required to protect the Council’s position; (8) increase the Capital programme by £1.823 million as detailed in the exempt finance comments. Reasons for decisions The proposals will release sites for development and will generate income and accrue savings for the Council. They provide an opportunity to implement more flexible working throughout Loxley House, and to consolidate public-facing services within a single location. They also provide the flexibility to recover VAT on any rental income from partners, subject to licences being in place, and this being the most favourable approach in the particular circumstances. Other options considered Do nothing: rejected as this could block at least 2 development opportunities and frustrate the most efficient use of resources. Relocate Revenues and Benefits and Housing Aid to other buildings: rejected as no appropriate buildings have been identified. Reconfigure Loxley House Ground Floor without introducing agile working: rejected, as existing back-office ground floor colleagues need relocating elsewhere within Loxley, requiring desk ratios to be improved. Appoint external consultants as change managers: rejected as is cost prohibitive. Use internal resources as change managers: rejected, as there is no in-house capacity to support this programme.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

EXECUTIVE BOARD – 16th October 2018

Subject: Loxley House Work Place and Hub Phase 2: Outline Business Case and Related Approvals Corporate Chris Henning, Corporate Director, Development and Growth Director(s)/Director(s): Portfolio Holder(s): Councillor Jon Collins, Leader/ Portfolio Holder for Regeneration and Growth Report author and Sarah White, Project Manager, Major Programmes. contact details: [email protected]. Tel: 0115 8763410

Subject to call-in: Yes No Key Decision: Yes No Criteria for Key Decision: (a) Expenditure Income Savings of £1,000,000 or more taking account of the overall impact of the decision and/or (b) Significant impact on communities living or working in two or more wards in the City Yes No Type of expenditure: Revenue Capital Total value of the decision: £1.823 million Wards affected: All Date of consultation with Portfolio Holder(s): 27.09.18 Relevant Council Plan Key Theme: Strategic Regeneration and Development Schools Planning and Housing Community Services Energy, Sustainability and Customer Jobs, Growth and Transport Adults, Health and Community Sector Children, Early Intervention and Early Years Leisure and Culture Resources and Neighbourhood Regeneration Summary of issues (including benefits to citizens/service users):

This report outlines proposals to maximise the potential of Loxley House and other assets, as outlined in the Council’s Corporate Asset Management Plan and the Strategic Regeneration Programme. This programme of works will include the movement of services from locations across the City to one central point, in Loxley House. The project will be funded through prudential borrowing, rental income, operational savings and capital receipts as set out in the financial model. The key outcome will be more efficient use of the Council’s estate and facilitating the development of key sites across the City.

Exempt information: State ‘None’ or complete the following Appendices C and D to this report are exempt from publication under paragraph 3 of Schedule 12A to the Local Government Act 1972 because they contain information relating to the financial affairs of the Council and its partners. It is not in the public interest to disclose this information because it may impact on the future ability of the Council to generate income to support public services. Recommendations: 1 To approve the Outline Business Case for the Loxley House Work Place and Hub Phase 2 programme of works as outlined in Appendix A.;

2. To approve the financial model of the project as outlined in the exempt Appendix C;

3 To delegate authority to the Corporate Director for Development and Growth, in consultation with the Leader/ Portfolio Holder for Regeneration and Growth, to enter into contracts for the works contracts, including the procurement of consultants, and to commit any other expenditure required during the delivery of the programme, subject to the costs being contained within the parameters of the financial model, noting that all requirements will be procured in conjunction with the Procurement Team and in accordance with the Councils own internal Contract Procedure Rules and Public Procurement Regulations 2015;

4 To approve the establishment of 1 FTE I grade change manager post and of 1 FTE H grade change manager post and the recruitment to that post under scheme of delegation number 16, for a fixed term of 12 months;

5 To delegate the authority to the Head of Legal Services to amend existing licence agreements to reflect changes and to enter into any service level agreements required to facilitate the programme and protect the interests of the Council;

6 To delegate the authority to the Corporate Director for Development and Growth, in consultation with Leader/ Portfolio Holder for Regeneration and Growth, to approve the Final Business Case, subject to the value being within the funding envelope set out within the Outline Business case.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Outline Business Case: Loxley House Work Place and Hub: Phase 2Appendix A 571 KB Download
PDF
EIA: Loxley House Work Place and Hub Phase 2Appendix B 180 KB Download
PDF
Loxley House Work Place and Hub Phase 2: Outline Business Case and related ApprovalsReport 340 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 14 attended
HC
Helen CarlinOfficer, expected
GC
Councillor Graham ChapmanVice Chair, apologies (work commitments)
JC
Councillor Jon CollinsChair, present
NK
Councillor Neghat KhanCommittee Member, present
DL
Councillor Dave LiversidgeCommittee Member, present
SL
Councillor Sally LongfordCommittee Member, present
NM
Noel McMenaminClerk, expected
DM
Councillor David MellenCommittee Member, present
TN
Councillor Toby NealCommittee Member, present
LP
Laura PattmanOfficer, expected
AR
Councillor Andrew RuleCommittee Member, in attendance
DT
Councillor Dave TrimbleCommittee Member, present

All 14 on the meeting page

On this subject at Nottingham

Search all
  1. Loxley House Work Place and Hub Phase 2: Outline Business Case and related ApprovalsThis decision
  2. Replacement of the existing city-wide fleet of Multi Functional Devices (MFDs) and the Loxley House Print Room machines - Key DecisionApproved

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open