Resolved
Resolved to: 1) approve the virement of £62,000 from the MRP budget to operational equipment to fund the purchase of new fire hoods in response to the Grenfell enquiry outcomes (£37,000) and to correct an error in the medical equipment budget (£25,000); 2) approve the addition of two new projects to the Capital Programme: i) £30,000 capital project for ICT equipment to enable the service to react to Covid-19; and ii) £70,000 Command Support upgrade to be funded from Earmarked Reserves 3) approve the slippage of £2,557,000 to 2021/22 for the Worksop replacement fire station project.