AI summaryNottingham Fire and Rescue Authority's Finance and Resources Committee approved the 2025/26 outturn, including £570k moved to capital financing, £223k to reserves, £1.510m slippage, and a £4.420m capital programme increase.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedRevenue underspend, capital slippage and reserve changes
Money£4.420m added to capital programmePlus £570k DRF, £223k reserves, £1.510m slippage
What happens nextApply approved reallocationsReprofiled capital programme runs to 2029/30
Who it affectsFire Authority reserves and capitalRevenue budget, earmarked reserves and capital programme
What was decided
Move £570k of revenue underspend into Capital Financing Costs via Direct Revenue Financing, and transfer £223k of underspends to Earmarked Reserves. Report 10.2, P14
Approve the reallocation of earmarked reserves. Report 10.3
Approve £1.510m of capital slippage and £50k net overspend in the 2025/26 Capital Programme, and a net £4.420m increase to the Capital Programme from 2026/27 to 2029/30, including the slippage. Report 10.4, 10.5, 10.6
Why
Members scrutinised the report to gain assurance over the Authority's financial position. Report P12
Regular financial reporting is itself a control on financial risk, with finance staff working with budget holders during the year. Report P10
The report explains variances to the approved budget which reflects existing policies, so no new policy, function or service arises. Report P5
What happens next
Apply the approved slippage and reallocations to the reprofiled Capital Programme for 2026/27 to 2029/30. Report 10.5, 10.6, P29
The money
£570k Direct Revenue Financing increase to Capital Financing Costs Report 10.2, P14
£223k Transfer of underspends to Earmarked Reserves Report 10.2, P14
£1.510m Capital slippage from 2025/26 into later years Report 10.4, 10.5
£50k Net overspend in 2025/26 capital programme Report 10.4
£4.420m Net increase to Capital Programme 2026/27 to 2029/30 Report 10.5
Implications
Financial: Report sets out revenue and capital variances and approves reallocations across reserves and the capital programme. Report P1, 10.2, 10.5
Risk: No new risk management implications identified; regular financial reporting is itself a control on financial risk. Report P10
Legal: No legal implications arising directly from the report. Report P8
Equalities: No equality impact assessment undertaken because the report is not linked to a policy, function or service. Report P5
Climate: No environmental and sustainability implications arising directly from the report. Report P7
Staffing: No human resources or learning and development implications arising directly from the report. Report P3
Other: No collaboration implications arising directly from the report. Report P11
Who and where
Nottingham Fire and Rescue Authority Report P12, P21
Timeline
2025/26: Revenue and capital outturn period reported Report P22, P28
31 March 2026: Reserve position closing date Report P22
19 June 2026: Committee meeting date
2026/27 to 2029/30: Reprofiled Capital Programme period Report 10.5, P29
Plain English for the jargon
Direct Revenue Financing (DRF): Using revenue budget to fund capital spending instead of borrowing.
Earmarked Reserves: Reserves set aside for a specific planned purpose.
Slippage: Capital or revenue budget not spent in the planned year and carried forward.
S151 Officer: Statutory Chief Finance Officer designated under section 151 of the Local Government Act.
ESMCP: Emergency Services Mobile Communications Programme.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4
Resolved
Resolved to 1. Scrutinise and gain assurance on the contents of this report. 2. Approve the use of underspend as set out in the report: (a) increase the Authority’s Capital Financing Costs by way of Direct Revenue Financing (DRF) to the value of £570k (Table 1); (b) the transfer of £223k of underspends to Earmarked Reserves (Table 4). 3. Approve the reallocation of earmarked reserves (Table 3). 4. Approve the slippage of £1.510m and net overspend of £50k in the 2025/26 Capital Programme (Table 6 and Appendix B). 5. Approve the net increase to the Capital Programme 2026/27 to 2029/30 of £4.420m, including £1.510m slippage from 2025/26 (Table 7). 6. Approve the reprofiled Capital Programme (Table 8 and Appendix C).
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Report to Nottingham Fire and Rescue Authority - Finance and Resources
Nottinghamshire and City of Nottingham Fire and Rescue Authority Finance and Resources Committee
2025/26 REVENUE AND CAPITAL OUTTURN Report of the Head of Finance and Treasurer to the Fire Authority (S151 Officer) Date: 19 June 2026
Purpose of Report: To report to Members on the provisional financial performance of the Service for 2025/26, analysing significant variances against the approved revenue and capital budgets. The outturn position gives Members an overview of the financial position for 2025/26.
Recommendations: It is recommended that Members:
• Scrutinise and gain assurance on the contents of this report.
• Approve the use of underspend as set out in the report:
o Increase the Authority’s Capital Financing Costs by way of Direct Revenue Financing (DRF) to the value of £570k (Table 1). o Approve the transfer of £223k of underspends to Earmarked Reserves (Table 4).
• Approve the reallocation of earmarked reserves (Table 3)
• Approve the slippage of £1.510m and net overspend of £50k in the 2025/26 capital programme (Table 6 and Appendix B).
• Approve the net increase to the Capital Programme 2026/27 to 2029/30 of £4.420m, including £1.510m slippage from 2025/26 (Table 7)
• Approve the reprofiled Capital Programme (Table 8 and Appendix C). CONTACT OFFICER Maria Fox Name: Head of Finance and Treasurer to the Fire Authority (S151 Officer) Tel: 0115 8388100
Media Enquiries Corporate Communications Team Contact: 0115 8388100 [email protected] 1. BACKGROUND
1.1The purpose of this report is to give Members information regarding the Authority’s financial performance for 2025/26. The outturn position may be subject to change if any issues are identified by the finance team prior to the audit of the accounts, or if any issues are identified by the auditors during the audit which require amendments to the revenue or capital position. Any changes will be reported to the Finance and Resources Committee at a future date.
1.2The 2025/26 Statement of Accounts are due to be audited by KPMG, with work commencing in July 2026 and with a deadline for the audit to be completed by the 31 January 2027.
2. REPORT
2.1The 2025/26 revenue budget of £57.736m was approved by the Fire Authority in February 2025. During the year additional use of other specific earmarked reserves were approved, amending the budget to £57.399m. At the October meeting of the Finance and Resources Committee, Members approved the principle that the in-year revenue underspend will be used to fund the capital programme. Throughout the 2025/26 financial year financial reports approved by the Finance and Resources Committee have reallocated a projected £1.506m underspend to capital which has been allocated as follows:
• £1.183m as Voluntary Revenue Provision approved to repay historic internal borrowing. • £323k as Direct Revenue Financing (DRF) approved to reduce the Authorities borrowing requirement from the 2025/26 Capital Programme.
2.2As part of year end it is recommended that a further £570k is charged as DRF meaning total expenditure for 2025/26 will be £57.116m representing an underspend of £283k (0.49%) on the overall 2025/26 budget.
2.3The original and revised 2025/26 budget included £261k use of the General Fund Reserve which is not required, this means that the remaining £21k underspend is to be moved to the General Fund Reserve.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Nottingham Fire and Rescue Authority - Finance and Resources at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
Internal Audit Annual Report 2025/26Resolved to (1) Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.