Basford, Berridge and Sherwood Area Committee approved this item on Wednesday 24 February 2021. Below is the council's own wording, with the papers it was decided on.
Resolved (1) to approve the following schemes, as detailed in the appendix to the report: Location Scheme Cost Basford - LTP Church St / Ladbrooke Cres Footpath improvements 63,855 Basford – public realm Vernon Park Improvements 9,950 Heathfield / Whitemoor Park Improvements 9,018 Church St / Ladbrooke Cres Footpath improvements 9,950 Various locations Litter bin installation 5,000 Berridge - LTP ‘Active Travel’ road safety Various 4,671 Berridge – public realm Various locations Environmental improvement 1,600 Sherwood - LTP ‘Active Travel’ road safety Various 9,595 Sherwood – public realm Various locations Grit bin installation 2,424 Various locations Litter bin installation 884 (2) to note, that in light of the above approvals, all wards have a zero remaining balance for both LTP and Public Realm.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Report to Basford, Berridge and Sherwood Area Committee
Recommendation
1 That the Committee approves the schemes detailed in appendix 1.
Reasons for recommendations
1.1The Nottingham LTP strategy 2011-2026 maintains a commitment to deliver local transport improvements across Nottingham’s neighbourhoods and prioritises small- scale transport improvements of importance to local communities.
1.2As part of the budget process Nottingham City Council approved at the Executive Board meeting on 18 February 2020 an LTP capital allocation of £1.25 million citywide between 2019 -20 was approved. At the same meeting a citywide allocation of General Fund Element (public realm) of £750,000 was agreed. At the subsequent Executive Board meeting on 21 July 2020, as part of the budget update, a top-slice of 20% was made to the General Fund Element (public realm) reducing it to £600,000.
2.1The Area Capital Programme was established to improve the environment of the neighbourhoods and to create a sense of place for residents in order to improve the quality of life of local people. Since its establishment in 2006 to meet the then corporate priority of ‘Transforming Neighbourhoods’, the Area Capital Fund has included a total programme expenditure portfolio of £40 million. The improvements that have been carried out to date using the programme have included footpath construction and repairs, fences, visual enhancements to public realm, refurbishment of parks and improvements to public buildings.
2.2Resources are allocated from the Nottingham City council general fund, the Local Transport Plan (LTP) and from the Housing Revenue Account. To achieve a joint approach to environmental improvements in neighbourhoods, a greater degree of flexibility has been established to prioritise and deliver improvements so that there is a synergy in local solutions for local issues across neighbourhoods.
2.3The programme of works is a rolling programme. There have been instances where schemes are started, with strong community involvement and interest, only to be altered at a later stage due to changing circumstances such as economic conditions and changes in land values.
2.4The Area Committee, particularly community representatives, are invited to comment specifically on those schemes identified in the proposals column and to consider whether certain schemes can be linked to other programmes of work in order to generate best value and create a greater impact on the local area.
3 Other options considered in making recommendations
3.1None.
4 Finance comments (including implications and value for money/VAT)
4.1Bringing together the various strands, which form part of the Area Capital Programme, enables the City Council to respond efficiently in delivering on public realm improvements as identified by local people.
4.2This report has been sent to the Chief Executive and Section 151 Officer for information in line with the amendment to delegations for making decisions for new capital expenditure, which came into force on 11 November 2020.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Basford, Berridge and Sherwood Area Committee at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
Police and Community Protection updatesResolved to note the updates and thank the Police and Community Protection representatives for their work in the loca...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.