Children’s Social Care Service Redesign

Noted Executive 1 paper

Executive Board noted this item on Tuesday 22 February 2022. Below is the council's own wording, with the papers it was decided on.

Item106

Resolved

Resolved to: (1) note the proposed investment and transformation programme set out in the report, and that the savings to be derived from the programme have been incorporated into the Medium Term Financial Plan and Budget Report. (2) approve the investment of up to £6,500,000 to procure a delivery partner to support the delivery of this programme pending a procurement process, as set out in section 2.3 of the report. (3) approve the investment of up to £2,400,000 for additional internal specialist resources to support delivery of this programme, as set out in section 2.3 of the report. (4) delegate authority to the Corporate Director for People to complete the procurement of a delivery partner and to allocate the budget set out in the report to deliver the service redesign programme. · Reasons for the decision To support the implementation of a substantial programme of transformation, service redesign and improvement, within a critical area of statutory service. The MTFP being presented as an agenda item at this meeting of the 22 February 2022 includes the financial benefits and if investment is not approved this will destabilise the budget position and change the assumptions in that report. · Other options considered Option 1: to do nothing. This option is rejected as there is significant risk to outcomes of residents and financial and reputational risk to the Authority if these opportunities to improve are not delivered. Option 2: to undertake a transformation programme aimed at a smaller subset of services. This option is rejected because Nottingham City Councils requires a transformation programme of sufficient size and scale to deliver improved and lower cost services. Undertaking only limited sections of the full identified opportunities within the October - November 2021 assessment would not achieve the necessary scale. There are also significant interdependencies between workstreams that would make the overall programme more difficult to deliver if not all done at once. For example, critical capacity from staff may be freed up through the Children in Need/Child Protection work that will support more timely and effective interventions with young people and their families. Option 3: to undertake the transformation programme with only internal resources. This option is rejected because an experienced transformation partner will bring with them the wider expertise of an organisation that has conducted public sector, and Children’s Services transformational changes across the country. In addition an experienced transformation partner would negate the requirement for Nottingham City Council to add significant additional transformation management capacity and capability resource. This would require hiring, onboarding, experiential learning and training before a transformation programme of this magnitude could begin. This would add a critical time delay to any programme and is likely to significantly reduce the magnitude of improvement achieved.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Executive Board 22 February 2022

Subject: Children’s Social Care Service Redesign

Corporate Catherine Underwood, Corporate Director for People Director(s)/Director(s):

Portfolio Holder(s): Councillor Cheryl Barnard, Portfolio Holder for Children and Young People

Report author and Catherine Underwood, Corporate Director for People contact details: [email protected]

Other colleagues who Ceri Walters, Head of Commercial Finance have provided input: Richard Grice, Interim Director of Transformation

Subject to call-in: Yes No

Key Decision: Yes No Criteria for Key Decision: (a) Expenditure Income Savings of £750,000 or more taking account of the overall impact of the decision and/or (b) Significant impact on communities living or working in two or more wards in the City Yes No

Type of expenditure: Revenue Capital

Total value of the decision: Up to £6,500,000 for a delivery partner over a 2-year period, and Up to £2,400,000 for internal specialist resources over a 4-year period

Wards affected: All

Date of consultation with Portfolio Holder(s): Throughout the budget process

Relevant Council Plan Key Outcome: Clean and Connected Communities Keeping Nottingham Working Carbon Neutral by 2028 Safer Nottingham Child-Friendly Nottingham Healthy and Inclusive Keeping Nottingham Moving Improve the City Centre Better Housing Financial Stability Serving People Well Summary of issues This report presents a case for a multi-year investment and transformation programme to redesign Nottingham City Council’s (NCC) provision of social care services for children and young people, as part of the council’s overall improvement journey. The redesign would:  improve the outcomes, safety and experience of the children supported by NCC while significantly reducing the cost of the service for Nottingham residents and  Support the opportunities to improve service quality and OFSTED performance.

Due to the size, scale and pace of the transformation programme required, the council would need to procure an external delivery partner to provide the experience, expertise and capacity for a 2 year period and additional internal service capacity for a 4 year period.

Full implementation will take 8 years with 83% of the programme being delivered in the Medium Term Financial Plan (MTFP) time frame.

The value of savings delivered as a result of the investment over an:  8 year period is: o £63.376m gross and £50.776m net. o The Return on Investment (RoI), over the life of the programme, is 7.1 : 1.

 4 year MTFP time frame is: o £20.759m gross and £16.549m net. o The RoI is 2.3 : 1

The 3 : 1 ratio is achieved between year 4 and 5 due to the significant upfront investment required.

The savings anticipated through this investment and transformation programme have been accounted for in the MTFP and Budget Report at agenda item 6 at this Executive Board meeting; if this investment is not approved this will destabilise the proposed budget.

The savings in the MTFP do not reflect the ‘stretch’ target associated with this programme which could deliver up to a further £13m over the life of the programme. The rationale for exclusion at this stage is set out in section 5.1. Delivery of this would increase the RoI.

This report requests approval for the investment required to deliver this critical redesign of children’s social care services and funding recommendations.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Children’s Social Care Service RedesignReport 208 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 18 attended
DM
Councillor David MellenChair, present
SL
Councillor Sally LongfordVice Chair, apologies (personal reasons)
CB
Councillor Cheryl BarnardCommittee Member, present
EC
Councillor Eunice Campbell-ClarkCommittee Member, apologies (personal reasons)
RH
Councillor Rosemary HealyCommittee Member, present
NK
Councillor Neghat KhanCommittee Member, present
RL
Councillor Rebecca LangtonCommittee Member, present
AW
Councillor Adele WilliamsCommittee Member, present
SW
Councillor Sam WebsterCommittee Member, present
LW
Councillor Linda WoodingsCommittee Member, present
KC
Councillor Kevin ClarkeNon-voting, present
AR
Councillor Andrew RuleNon-voting, present

All 18 on the meeting page

On this subject at Nottingham

Search all
  1. Children’s Social Care Service RedesignThis decision
  2. Children in Care Social Care complaintsNoted
  3. Children in Care - social care complaintsDecided
  4. Children in Care Social Care ComplaintsNoted
  5. Re-designation of Director of Adult Social Services responsibilities from the Corporate Director of Children and Adults to the Director of Adult Social CareApproved
  6. Children in Care Social Care ComplaintsDecided

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies