East Midlands Shared Services Audit Plan 2022 / 2023
NotedCommittee2 papers
East Midlands Shared Services Joint Committee noted this item on Monday 21 March 2022. Below is the council's own wording, with the papers it was decided on.
Resolved 1) to note the update on progress against the Audit Plan for 2021/2022; 2) to approve the EMSS Audit Plan for 2022/2023. o Reason for the decision: Section 151 of the Local Government Act 1972 requires local authorities to make arrangements for the proper administration of their financial affairs and appoint a S151 Officer to have responsibility for those arrangements. In addition, the Accounts and Audit Regulations 2015 require local authorities to undertake an effective internal audit of their arrangements. The audits of the key areas recorded with the EMSS audit plan provides the section 151 officers within both partner organisations with some assurance in respect of the operation of the control environment. o Other options considered: None as this is a legal requirement, as explained above.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Report to East Midlands Shared Services Joint Committee
Reasons for recommendations
1.1To provide assurance to Joint Committee that EMSS has robust audit arrangements in place.
2 Background (including outcomes of consultation)
2.1EMSS managers are responsible for ensuring that proper standards of internal control operate within their organisation. NCC’s Internal Audit service reviews these controls and gives an opinion in respect of the systems and processes put in place.
2.2The Audit Plan is agreed annually and reported to LCC and NCC governance committees. 2.3 The Internal Audit service undertakes reviews of the internal control procedures in respect of the key systems and processes run by EMSS on behalf of itself and its clients; the Audit Plan will continue to focus in these areas.
2.4Reports in respect of all reviews are issued to the responsible colleagues within EMSS. These reports include agreed recommendations within attached action plans and a level of assurance that is drawn from the findings.
Update on 2021/22 plan
2.5Progress on this year’s plan has not been achieved as hoped. Particular challenges for NCC Internal Audit have been: Access to Fusion which has proven to be problematic Difficulty in identifying the required information, once access was granted The delay in Payroll going live Linked to the above, testing of Payroll requires ESC to provide much of the supporting documentation and it was agreed between NCC Internal Audit and ESC that due to workloads this would not be available until late February 2022. Other work commitments for NCC Internal Audit
2.6The current position with the planned audits is as follows:
System Status / Findings Planned Est Days Expected Days Used date of Draft Report Accounts Testing complete. 40 35 Late Payable Reviewing working March papers and draft report
No concerns identified with the testing completed so far Accounts Testing complete. 40 25 Late Receivable Reviewing working March papers and draft report
Minor changes to processes as noted from walk-throughs Minor issues regarding processes noted Payroll & HR Planning meeting, Audit 40 12 April/May Brief issued and sample selected System Status / Findings Planned Est Days Expected Days Used date of Draft Report A number of work around issues that are having to be completed. Concerns raised regarding Fusion history; it is understood that this can be overwritten OTL issues with schools/academies Exception reporting more time consuming as ESC are not always aware of reasons for changes to salaries We expect this review to continue into April. IT – System We are planning this review. 30 2 May Admin and If the full scope is not access controls achieved by May, an interim report will be issued Contingency Not used 20 0 - Total 170 74
2.7As indicated above, the work completed to date on AR and AP has not so far identified any significant control issues. Whilst there have been delays with the completion of this year’s plan, NCC Internal Audit is confident that the work will be completed and reports issued in time to provide a Head of Audit Opinion in May 2022.
Proposed Audit Plan for 2022/23
2.8The plan for 2022/23 is prepared on the same lines as the current year’s plan and is attached.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow East Midlands Shared Services Joint Committee at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.