Northern Part Of Former British Gas Works Site Radford Road Nottingham

Decided Planning 1 paper

Planning Committee decided this item on Wednesday 18 May 2022. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Resolved 1) to grant planning permission subject to:- (a) further testing and investigative work being undertaken concluding with a Remediation Method Statement being submitted to the satisfaction of the Environmental Health Officer prior to any consent being issued and with the Director of Planning and Regeneration having delegated authority to determine the final details of any appropriate linked conditions; (b) the Environment Agency withdrawing their objection upon provision of satisfactory a Flood Risk Assessment (FRA) and Surface Water Drainage Strategy to secure implementation of mitigation to ensure the development is safe for its lifetime from flooding and would not result in flooding elsewhere; and with the Director of Planning and Regeneration having delegated authority to determine the final details of the appropriate conditions; (c) prior completion of a Section 106 planning obligation to secure: (i) a financial contribution of £495,000 in lieu of on-site provision of affordable housing; (ii) a financial contribution of £168,699 in lieu of on-site provision of public open space; (d) the indicative conditions substantially in the form of those listed in the draft decision notice at the end of the report (as amended and added to within the Update Sheet); 2) for the power to determine the final details of the planning obligation and conditions of planning permission to be delegated to the Director of Planning and Regeneration; 3) that the Committee is satisfied that Regulation 122(2) Community Infrastructure Levy Regulations 2010 is complied with, in that the planning obligations sought is (a) necessary to make the development acceptable in planning terms, (b) directly related to the development and (c) fairly and reasonably related in scale and kind to the development.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Planning Committee

Summary

Application No: 21/01786/PFUL3 for planning permission

Application by: Marrons Planning on behalf of Strata Homes, Patrick Anthony Ryan & Margaret Anne Ryan

Proposal: Full planning application for the residential development of 114 build-to-rent dwellings alongside associated site infrastructure, open space, and landscaping.

The application is brought to Committee because it is a major application on a prominent site where there are important land use and design considerations. In addition it is proposed that the planning obligations typically required by adopted planning policies be reduced in this case.

To meet the Council's Performance Targets this application should have been determined by 09th November 2021. An extension of time has been agreed with the applicant until 30th May 2022.

Recommendations

2.1To GRANT PLANNING PERMISSION subject to:- (a)The Environment Agency withdrawing their objection upon provision of satisfactory a Flood Risk Assessment (FRA) and Surface Water Drainage Strategy to secure implementation of mitigation to ensure the development is safe for its lifetime from flooding and would not result in flooding elsewhere; and with the Director of Planning and Regeneration having delegated authority to determine the final details of the appropriate conditions

(b) prior completion of a Section 106 planning obligation to secure:

(i) a financial contribution of £495,000 in lieu of on-site provision of affordable housing (ii) A financial contribution of £168,699 in lieu of on-site provision of public open space

(c) the indicative conditions substantially in the form of those listed in the draft decision notice at the end of this report. 2.2 Power to determine the final details of the planning obligation and conditions of planning permission to be delegated to the Director of Planning and Regeneration.

2.3That Committee are satisfied that Regulation 122(2) Community Infrastructure Levy Regulations 2010 is complied with, in that the planning obligations sought is (a) necessary to make the development acceptable in planning terms, (b) directly related to the development and (c) fairly and reasonably related in scale and kind to the development.

3 SITE AND SURROUNDINGS

3.1The application site measures 2.4 hectares and forms the northern part of the former British Gas Works site on the western side of Radford Road. The site is undeveloped, disused and overgrown and has been vacant for many years.

3.2The site is bounded to the north by Basford Depot - a gas pipeline and infrastructure site. Directly to the east is Radford Road and beyond this comprises the residential area of New Basford. To the south is Selco Builders Warehouse alongside a police custody suite which is currently under construction. The site is also bound to the west by a tram line, railway line and the River Leen.

3.3There is a substantial brick wall bounding the site on Radford Road.

4 PLANNING HISTORY

4.1The site was granted Outline Planning Permission in 2006 (05/02476/POUT) for mixed use purposes, ‘including B1 and/or B2 and or B8, retail (A1), residential (C3), community facilities (D1), car showroom, A3/A4/A5, including new access/egress to Radford Road, service road and landscaping. Reserved matters, following the outline permission was approved in 2008. However, development never commenced.

4.2Planning Permission was granted in June 2013 for the ‘erection of mixed-use development including employment/retail/residential and leisure within classes A1, A2, A3, B1, B2, B8, C3 and D2. This permission has since expired.

4.3Planning permission reference 19/01480/PFUL3 for a development adjacent to the south west of the site for the development of a custody suite building was approved on 20th November 2019 and is currently under construction.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Northern Part Of Former British Gas Works Site Radford Road NottinghamReport 656 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 21 attended
LA
Councillor Leslie AyoolaCommittee Member, apologies (council business)
GC
Councillor Graham ChapmanVice Chair, present
AC
Councillor Azad ChoudhryCommittee Member, absent
KC
Councillor Kevin ClarkeCommittee Member, present
ME
Councillor Michael EdwardsChair, present
LG
Lisa GuestOfficer, present
JH
Councillor Jay HayesCommittee Member, apologies (unwell)
CJ
Councillor Corall JenkinsCommittee Member, present
AK
Councillor Angela KandolaCommittee Member, present
GN
Councillor Gul Nawaz KhanCommittee Member, present
DL
Councillor Dave LiversidgeCommittee Member, apologies
SL
Councillor Sally LongfordCommittee Member, present

All 21 on the meeting page

More from Nottingham Planning Committee

All decisions
MeetingDecisionOutcome
19 Aug 2026 Land West Of Arkwright Street. South Of Crocus Street Nottingham NG2 2HHResolved (1) That the Committee approve in principle the variation of the Section 106 Planning Obligation dated 12 Ja... Approved Open
19 Aug 2026 Amendments to the Constitution arising from the Planning and Infrastructure Act 2025Resolved (1) To note the requirements of the National Scheme of Delegation for planning functions in accordance with ... Noted Open
22 Jul 2026 Site of Toll Bridge Inn, Victoria Embankment, NG2 2JYResolved (1) To grant planning permission for the reasons set out in this report, subject to: i) Prior completion of ... Decided Open
22 Jul 2026 Station Street, Nottingham, NG2 3NGResolved (1) To grant planning permission for the reasons set out in the report, subject to: (a) The indicative condi... Decided Open
22 Jul 2026 Car park at rear of Riverleen House, Centurion Way, NG2 1RUResolved (1) To grant planning permission subject to: a. conditions substantially in the form of those listed in the ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies