Resolved 1) to grant planning permission subject to: (a) the Environment Agency withdrawing their objection upon provision of a satisfactory Flood Risk Assessment (FRA) and Surface Water Drainage Strategy to secure implementation of mitigation to ensure the development is safe for its lifetime from flooding and would not result in flooding elsewhere; and with the Director of Planning and Regeneration having delegated authority to determine the final details of the appropriate conditions; (b) prior completion of a Section 106 Planning Obligation to secure: (i) a commuted sum of £296,601 in lieu of on-site affordable housing provision; (ii) a financial contribution of £174,166 towards the enhancement of public open space/public realm in the surrounding area, in lieu of onsite provision (ii) a student management plan and restrictions on keeping private vehicles; (iii) local employment and training benefits including opportunities in the construction and operational phases of development, together with payment of a financial contribution of £24,504 towards their delivery; (c) the indicative conditions substantially in the form of those listed in the draft decision notice at the end of the report; 2) that the Committee is satisfied that Regulation 122(2) Community Infrastructure Levy Regulations 2010 is complied with, in that the planning obligations sought are (a) necessary to make the development acceptable in planning terms, (b) directly related to the development and (c) fairly and reasonably related in scale and kind to the development; 3) for the power to determine the final details of the conditions of planning permission to be delegated to the Director of Planning and Regeneration.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Application No: 22/00001/PFUL3 for planning permission
Application by: DPP Planning on behalf of Cassidy (Triumph Road) Ltd.
Proposal: Demolition of the existing structures and the construction of new purpose-built student accommodation, associated ground floor indoor/external amenity areas, access, landscaping, car parking and associated infrastructure.
The application is brought to Committee at the request of a Ward Councillor who has raised valid planning considerations.
To meet the Council's Performance Targets this application should have been determined by 6 May 2022. An extension of time has been agreed with the applicant until 30th May 2022.
Recommendations
2.1GRANT PLANNING PERMISSION subject to:
(a) The Environment Agency withdrawing their objection upon provision of satisfactory a Flood Risk Assessment (FRA) and Surface Water Drainage Strategy to secure implementation of mitigation to ensure the development is safe for its lifetime from flooding and would not result in flooding elsewhere; and with the Director of Planning and Regeneration having delegated authority to determine the final details of the appropriate conditions
(b) Prior completion of a Section 106 Planning Obligation to secure:
(i) A commuted sum of £296,601 in lieu of on-site affordable housing provision
(ii) A financial contribution of £174,166 towards the enhancement of public open space/public realm in the surrounding area, in lieu of on- site provision
(iii) A student management plan and restrictions on keeping private vehicles
(iv) Local employment and training benefits including opportunities in the construction and operational phases of development, together with payment of a financial contribution of £24,504 towards their delivery (c) The indicative conditions substantially in the form of those listed in the draft decision notice at the end of this report.
2.2Committee being satisfied that Regulation 122(2) Community Infrastructure Levy Regulations 2010 is complied with, in that the planning obligations sought are (a) necessary to make the development acceptable in planning terms, (b) directly related to the development and (c) fairly and reasonably related in scale and kind to the development.
2.3Power to determine the final details of the conditions of planning permission to be delegated to the Director of Planning and Regeneration.
3 Site and Background
3.1The site currently contains a large single storey building sub-divided in two units which front onto Triumph Road. One is occupied by a yoga studio/cafe and the other is a car dealership. The building is industrial in character and constructed of brick with a series of pitched roofs finished in metal cladding. The area at the front of the units is used for parking. There is also a single storey industrial outbuilding at the rear of the site, currently used by a taxi rental company. The rest of the site is a hardstanding parking/storage/service area. There are no trees or soft landscaping on the site.
3.2The site is bounded by Triumph Road to the west and the River Leen to the east. Adjacent the site to the north is the Co-op Funeral care building. This comprises a 2-storey office element which fronts onto Triumph Road, behind which it becomes a more industrial single storey building with a series of pitched roofs. To the south of the site at the corner of Triumph Road and Derby Road is a car dealership.
3.3The River Leen runs along the eastern boundary of the site and on the other side of this is a large student accommodation scheme by Unite is currently under construction. This is largely 5-6 storeys in scale and is to accommodate 690 beds.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Station Street, Nottingham, NG2 3NGResolved (1) To grant planning permission for the reasons set out in the report, subject to: (a) The indicative condi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.