D2N2 wide - Local Area Energy Planning

Agreed Executive 2 papers

Executive Board agreed this item on Tuesday 21 February 2023. Below is the council's own wording, with the papers it was decided on.

Item109

Resolved

Resolved to: 1) agree that Nottingham City Council leads on the procurement of a consultant to create a Local Area Energy Plan, on behalf of the Local Authorities across the Derby/ Derbyshire and Nottingham/ Nottinghamshire area (D2N2) 2) delegate authority to the Head of Midlands Net Zero Hub in consultation with the Director of Environment and Sustainability and the Director of Governance and Legal Services: a) to undertake a procurement exercise and enter into a contract to source a consultant to undertake the required work to deliver a Local Energy Plan for the Derby/ Derbyshire and Nottingham/ Nottinghamshire area. b) to recruit a Technical Advisor on a Fixed Term 2-year contract subject to acceptance from each of the partner authorities of funding of up to £75,000 (£7,000 to cover the Technical Advisor role and £68,000 to cover the Consultants) and noting commitments and commissioning through the proposed consultant contract would only be made once approval and funding has been secured by the relevant partner authority. 3) delegate authority to the Director of Environment and Sustainability in consultation with the Director of Governance and Legal Services to enter into an appropriate, agreements with the partner Local Authorities and other identified stakeholders for the creation of the Local Area Energy Plan. · Reasons for Decisions At Full Council on the 13th January 2020, the Council declared a Climate and Ecological Emergency. Then in June 2020 the CN 2028 Action Plan was published by the City Council to achieve sustainable carbon neutrality for Nottingham. Many of the partner Local Authorities have also declared Climate Emergencies, but recognise that they cannot deliver against their ambitions in isolation. Furthermore, some actions make more sense to deliver at a regional level. Local Area Energy Planning is seen as the foundation of the region’s ability to achieve Net Zero as it will develop a clear base line and identify the most cost effective and efficient path to achieve Net zero at a Local Authority, County and Regional level. The work may also support bidding for funding and investment into the region, as it demonstrates the scale of the opportunity. £2.7bn of Net Zero and Environment projects have already been identified across Derbyshire and Nottinghamshire, through the work of the Midlands Net Zero hub in partnership with the N2 Environmental Strategy Working Group and D2 Energy Group. Some projects identified may be best developed at a local level, others will have the potential to be packaged together and presented as a regional opportunity for investment and growth. Local Authorities are in a unique position to demonstrate strategic leadership and can utilise Local Area Energy Planning to make informed decisions that cut across multiple agendas including planning, transport, investment, health, skills, jobs and economic growth but with Net Zero as the golden thread. It is envisaged that Nottingham City Council, supported by Midlands Net Zero Hub, would lead the procurement of a consultant with input to the specification supported by the other Local Authorities. Other stakeholders will also be included for example National Grid and Cadent alongside others who will be identified as part of the process. The supporting LAs would look to seek approval through their own processes to deliver this work · Other Options Considered Not developing a Local Area Energy Plan -discounted as the disparate approach to Net Zero is inefficient and more costly, as demonstrated in the Socio-Economic report. Developing a LAEP enables a co-ordinated approach at Local and D2N2 level that will identify the most cost effective approach to achieve Net Zero. Not to proceed with the work, would be a missed opportunity to attract investment and to have a ready-made plan in place for addressing the Net Zero Transition at a Local Authority level and potentially at Combined Authority level, should Devolution proceed.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Executive Board – 21 February 2022

Subject: D2N2 wide – Local Area Energy Planning Corporate Frank Jordan, Corporate Director Communities, Environment and Director(s)/Director(s): Resident Services Wayne Bexton, Director of Environment and Sustainability

Portfolio Holder(s): Councillor Sally Longford, Portfolio Holder for Energy, Environment and Waste Services

Report author and Michael Gallagher – Head of Midlands Net Zero Hub contact details: [email protected]

Other colleagues who Wayne Bexton – Director Environment and Sustainability have provided input: Subject to call-in: Yes No Key Decision: Yes No Criteria for Key Decision: (a) Expenditure Income Savings of £750,000 or more taking account of the overall impact of the decision and/or (b) Significant impact on communities living or working in two or more wards in the City Yes No Type of expenditure: Revenue Capital If Capital, provide the date considered by Capital Board: consideration subject to the proposed bid being successful Total value of the decision: £1.2m Wards affected: All Date of consultation with Portfolio Holder(s): Cllr Longford – 11 Jan 23 Relevant Council Plan Key Outcome: Clean and Connected Communities Keeping Nottingham Working Carbon Neutral by 2028 Safer Nottingham Child-Friendly Nottingham Healthy and Inclusive Keeping Nottingham Moving Improve the City Centre Better Housing Financial Stability Serving People Well Summary of issues (including benefits to citizens/service users): The transition to Net Zero is complex and challenging. To do this successfully and economically is a significant strategic task which cannot be achieved in isolation. A clear plan on how to get there is needed. Local Area Energy Planning (LAEP) is a data driven and whole energy system, evidence-based approach that sets out to identify the most effective route for an area to contribute towards meeting the national net zero target, as well as meeting its local carbon reduction targets. LAEP is expected to be a significant component of a place-based approach to Net Zero that will be vital for government to meet its ambitions.

There is effective engagement on the net zero agenda across the Nottingham/ Nottinghamshire and Derby / Derbyshire area. This is facilitated through the Low Carbon Growth Board of the Local Enterprise Partnership, the Nottinghamshire Environmental Strategy Working Group and the (Derby / Derbyshire) Energy Group. Local Area Energy Planning has become a standardised item on the agendas of these groups over the last 6 months since the Energy Systems Catapult first presented the concept of Local Area Energy Planning to the groups.

Through these regular sub-regional discussions, the need for Local Area Energy Planning has been identified and its further exploration is supported in principle by the Chief Executives of Nottinghamshire, with positive engagement on-going with colleagues in Derbyshire.

Whilst this proposal is based on effective sub-regional working it is not dependent on the proposals relating to a combined authority and devolution deal that are currently being considered.

There are seven stages to Local Area Energy Planning. With the production of a Socio- Economic Report (appendix 1) and the drafting of a procurement specification for an expert consultant to support on the development of LAEP, we are currently at stage 1. However, elements of stage 2 are also being developed.

The stages are broken down as follows: Stage 1 – Preparation Stage 2 – Stakeholder Identification and Engagement Stage 3 – Understanding and Representing the Current Local Energy System Stage 4 – Modelling Options for the Future Stage 5 – Scenario Refinement and Selection Stage 6 – Actions, Priorities, and Decisions Stage 7 – Create the Plan

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
D2N2 wide: Local Area Energy PlanningReport 446 KB DownloadRead as text
PDF
Enc. 1 for D2N2 wide Local Area Energy PlanningReport 1.6 MB Download

At this meeting

Whole meeting

Who was there

12 of 18 attended
CB
Councillor Cheryl BarnardCommittee Member, present
MB
Mel BarrettOfficer, present
RB
Ross BrownOfficer, present
KC
Councillor Kevin ClarkeNon-voting, present
CH
Clive HeaphyOfficer, expected
FJ
Frank JordanOfficer, present
NK
Councillor Neghat KhanCommittee Member, apologies (on leave)
PK
Councillor Pavlos KotsonisCommittee Member, present
RL
Councillor Rebecca LangtonCommittee Member, apologies (unwell)
SL
Councillor Sally LongfordCommittee Member, present
DM
Councillor David MellenChair, present
TN
Councillor Toby NealCommittee Member, apologies (unwell)

All 18 on the meeting page

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies