Future High Streets Fund - Reallocation of Funding

Agreed Executive 1 paper

Executive Board agreed this item on Tuesday 21 May 2024. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Resolved to (1) agree to discontinue the Angel Row element of the FHSF project on the grounds that it is undeliverable; (2) approve the reallocation of FHSF grant funding from the Angel Row project to support the delivery of the Community Diagnostics Centre (CDC); (3) delegate authority to the Corporate Director for Growth and City Development to sign the MOU once/if revisions are agreed with DLUHC; (4) delegate authority to the Corporate Director of Growth and City Development to agree any subsequent grant agreement and MOU with NUHT. Reasons for decisions: · The decisions will allow the FHSF Grant to be retained by the city rather than being returned to DLUHC and utilised within the funding conditions. · The additional funding will enable an optimised and enhanced CDC development to be delivered which will bring increased health, social and environmental benefits to the city. Other options considered: · Alternative Schemes: Alternative schemes within the capital programme have been considered for the utilisation of this funding, however the recommended project needed to meet the FHSF funding criteria and conditions. The alternative projects that have been investigated have ultimately been discounted due not fully meeting the funding criteria, timescales and budgetary requirements. It has therefore been determined that the NHS Community Diagnostics Centre (CDC), proposed for Lister Gate, is the most appropriate opportunity to deliver the outcomes required by the FHSF and would enable the grant to be utilised within the city and within the funding constraints. · Detailed Grant Agreement to specify works: The advantage of this type of agreement is that it would give the Council greater certainty that NUHT will deliver specific outputs as the Council expects and within the expected timescale and budget. However, a potential disadvantage is that if the Council uses the agreement to impose substantial detailed obligations on NUHT, there is a risk that this could bring the agreement within the scope of a public works contract and so be subject to public procurement legislation. This is not possible within the timeframes and an open procurement exercise is not appropriate for this scheme delivery which is being led by the NUHT. · Forfeit FHSF Grant: Without support for the CDC project, Officers would recommend forfeiting the FHSF grant associated with the Angel Row Creative Cooperative to DLUHC.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Executive Board – 21 May 2024

Subject: Future High Streets Fund – Reallocation of funding Corporate Sajeeda Rose, Corporate Director of Growth & City development Director(s)/Director(s): Portfolio Holder(s): The Portfolio Holder with responsibility for Strategic Regeneration

Report author and Laura Marsden/Mark Lowe, Head of Housing & Regeneration contact details: Telephone: 0115 8763532 Email: [email protected] Other colleagues who Anthony Heath, Team Leader, Legal Services have provided input: Mick Suggett, Team Leader, Legal Services Sue Oliver, Category Manager, Procurement Jonathan Whitmarsh, Corporate Procurement Officer Beverley Gouveia, Head of Property Thomas Straw, Senior Accountant Geetha Blood, Interim Finance Business Partner Subject to call-in: Yes No Key Decision: Yes No Criteria for Key Decision: (a) Expenditure Income Savings of £750,000 or more taking account of the overall impact of the decision and/or (b) Significant impact on communities living or working in two or more wards in the City Yes No Type of expenditure: Revenue Capital If Capital, provide the date considered by Capital Board Date: 7th May 2024 Total value of the decision: £3.865m Section 151 Officer expenditure approval Has the spend been approved by the Section 151 Officer? Yes No N/a Spend Control Board approval reference number: Commissioner Consideration Has this report been shared with the Commissioners’ Office? Yes No Any comments the Commissioners wish to provide are listed below. Wards affected: Castle Date of consultation with Portfolio Holder(s): Relevant Council Plan Key Outcome: Clean, Green and Connected Communities Keeping Nottingham Working Carbon Neutral by 2028 Safer Nottingham Child-Friendly Nottingham Living Well in Our Communities Keeping Nottingham Moving Improve the City Centre Better Housing Serving People Well Summary of issues (including benefits to citizens/service users): In December 2020, the council was successful in securing £12,520,000 from Department for Levelling Up, Housing and Communities (DLUHC) ‘Future High Street Fund’ (FHSF), as part of the governments’ Levelling Up’ programme. This funding was granted to deliver two schemes that were intended to ‘renew and reshape the Nottingham high street in a way that improves experience, drives growth, and ensures future sustainability’. The projects were:1) Maid Marian Way Highway Infrastructure - £8.6 million, and 2) Angel Row Creative Cooperative - £3.9 million. Whilst the Highway Infrastructure project continues to make significant progress and is expected to be completed by Spring 2025, unfortunately the Angel Row scheme is undeliverable. The Angel Row project was dependent on the successful sale of Nottingham Central Library on Angel Row to a developer. However, due to the current ongoing economic conditions, the developer identified for the site did not complete on the purchase and this has resulted in the Angel Row project being undeliverable.

In this context, we have been in dialogue with DLUHC to request an extension to the current funding deadline of March 2024 to March 2025 and seek authorisation to reallocate the Angel Row Future Highstreets Fund (FHSF) grant to an alternative project at Broad Marsh, specifically the Community Diagnostics Centre (CDC) on Lister Gate in partnership with the Nottingham Universities Hospitals Trust (NUHT). DLUHC have approved this request and have requested that the Council sign a new memorandum of understanding (MOU) that includes the extended funding timescale and reallocation of funding to the CDC project. It is therefore proposed that the FHSF funding be transferred to the NUHT via a grant agreement under section 76 of the National Health Service Act 2006 to support delivery of the CDC. This will be on the condition of agreeing revised outputs with DLUHC.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Future High Streets Fund: Reallocation of FundingReport 455 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 21 attended
NK
Councillor Neghat KhanChair, present
ER
Councillor Ethan RadfordVice Chair, present
CB
Councillor Cheryl BarnardCommittee Member, present
KC
Councillor Kevin ClarkeNon-voting, absent
JH
Councillor Jay HayesCommittee Member, present
CJ
Councillor Corall JenkinsCommittee Member, present
PK
Councillor Pavlos KotsonisCommittee Member, present
SL
Councillor Sam LuxCommittee Member, present
LW
Councillor Linda WoodingsCommittee Member, present
MB
Mel BarrettOfficer, apologies
BB
Beth BrownOfficer, in attendance
RB
Ross BrownOfficer, in attendance

All 21 on the meeting page

On this subject at Nottingham

Search all
  1. Future High Streets Fund - Reallocation of FundingThis decision
  2. Future High Streets Fund and Towns FundDecided

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies