Nottingham City Council
Executive Board, Tuesday 17 March 2026 at 2.00pm

Reallocation of Basic Need Grant Funding to High Needs Project

Approved Executive 1 paper

AI summaryNottingham City Council's Executive Board has approved reallocating £5,240,000 of Basic Need Grant to fund 54 mainstream places within new SEND units at five schools, shifting the cost from the High Needs Capital Grant.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFrom High Needs to Basic Need Grant for 54 mainstream places
Money£5,240,000Total Basic Need Grant to be reallocated across five sites
What happens nextNo new spend requiredAmends existing project approvals and funding split
Who it affectsAll wards across the cityFive schools and academies citywide

What was decided

Approve spending £5,240,000 of Basic Needs Grant Funding to fund 54 mainstream places within newly constructed SEND units listed in Table 1 of the report. Report P8

Amend four existing governance approvals from 2023 and 2024 so they reflect the use of Basic Needs Grant instead of High Needs Capital Grant for the 54 mainstream places. Report 1.1, 1.4

Why

Basic Need allocations under Section 31 of the Local Government Act 2003 are not ringfenced or time-bound, so the council can use the grant to support SEND provision in mainstream schools while still meeting its duty to provide enough mainstream places. Report 2.1, 2.2, 2.3, 6.1, 6.2

Of the 92 total places being created across the five sites, 54 are mainstream specialist places that can properly be funded from the Basic Need Capital Grant rather than the High Needs Capital Grant. Report 1.3, 1.4, 5.3

What happens next

No change to the overall project budget is required; the funding split will be amended in working files ahead of year-end capital financing. Report P19

Education Services must work with Legal Services colleagues on licences and long lease amendments for academy trust owned sites. Report 6.6

The money

  • £5,240,000 Total Basic Need Grant to be reallocated across the five sites Report P8, 5.1
  • £8,380,000 Total combined cost of the five SEND unit projects Report P8
  • £400,000 Djanogly Strelley Academy: £200,000 from Basic Need Grant Report P7
  • £700,000 Milford Primary Academy: £350,000 from Basic Need Grant Report P7
  • £2,050,000 Glade Hill Primary School: £1,025,000 from Basic Need Grant Report P7
  • £3,150,000 Fernwood School Academy: £2,625,000 from Basic Need Grant Report P7
  • £2,080,000 Nottingham Girls Academy: £1,040,000 from Basic Need Grant Report P7
  • £6,491m Current available Basic Needs funding balance in reserve Report 5.4
  • £34.5m Basic Needs Grant allocated to the council for 2026-2028 Report P15

Options considered

  • Rejected: Continue funding the 54 newly created places from the High Needs Capital Grant. Limited funding available to deliver the SEND Sufficiency Strategy Report 3.1, P12

Implications

  • Financial: Switching the 54 places from High Needs to Basic Need Grant frees up High Needs funding for the SEND Sufficiency Strategy; Basic Needs reserve of £6,491m and ongoing monthly receipts of £775k are judged ample. Report 5.4, P15
  • Legal: Projects must comply with the Basic Need Grant Determination (2025) No.31/7865, the Basic Needs Capital Allocations guidance, and procurement rules; failure could risk Department for Education clawback. Report 6.1, 6.3, 6.4
  • Legal: Licences and amended long leases will be needed for academy trust owned sites such as Djanogly Strelley Academy. Report 6.6
  • Equalities: Equality impact assessments were refreshed for this report after being carried out at the original 2024 approvals. Report 8.1
  • Risk: Risk of insufficient Basic Needs funding to meet the statutory duty to provide mainstream places is mitigated by the £34.5m 2026-2028 allocation. Report P15

Who and where

  • Djanogly Strelley Academy: 16 total places, 8 new from Basic Need Grant Report P7
  • Milford Primary Academy: 16 total places, 8 new from Basic Need Grant Report P7
  • Glade Hill Primary School: 16 total places, 8 new from Basic Need Grant Report P7
  • Fernwood School Academy: 24 total places, 20 new from Basic Need Grant Report P7
  • Nottingham Girls Academy: 20 total places, 10 new from Basic Need Grant Report P7
  • Pupils aged 5 to 16 across the city needing mainstream school places Report 2.1, 6.1

Timeline

  • 06/01/2026: Finance sign-off by the Strategic Capital Accountant Report P22
  • 26.01.2026: Legal sign-off by the Senior Solicitor Report P30
  • By September 2027: All five SEND unit projects to be delivered, whether complete, on site, or progressing to construction contract Report 1.2
  • 2026-27 and 2027-28 financial years: Basic Need Grant Determination (2025) No.31/7865 provides £21,160,777 and £13,421,978 respectively to create new school places by September 2028 Report 6.1

Plain English for the jargon

  • Basic Need Grant: Capital funding from the Department for Education under Section 31 of the Local Government Act 2003 to help councils provide enough school places for pupils aged 5 to 16; not ringfenced or time-bound.
  • High Needs Capital Grant: Capital funding specifically for special educational needs and disabilities provision for children and young people with higher needs.
  • SEND: Special Educational Needs and Disabilities.
  • SEND Sufficiency Strategy: Nottingham City Council's plan, originally running 2023-2028 and refreshed in February 2026, to ensure there are enough appropriate SEND places in the city.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item100

Resolved

Resolved to: (1) approve the spend of £5,240,000 of Basic Needs Grant Gunding, to fund mainstream places within newly constructed SEND units listed at Table 1 of the report; (2) approve the amendment of the existing governance approvals which are: · Executive Board 22 nd October 2024 – To create a Special Educational Needs Provision at Gladehill Primary School and Fernwood Secondary School; · Executive Board 17 th December 2024 – To create a Special Educational Needs Provision at Rise Park Primary School and the Milford Academy Primary School; · Leader’s Key Decision (5089) 21 st February 2024 – To create a Special Educational Needs Provision at Nottingham Girls Academy; · Executive Board 20 th June 2023 – SEND Capital Programme Scheme (Djanogly Strelley); to reflect the utilisation of Basic Needs Granting Funding to replace previously approved use of High Needs Capital Provision Grant Funding for the projects listed at Table 1 of the report. Reason for decisions: Basic Need allocations are provided under Section 31 of the Local Government Act 2003. The funding is not ringfenced, nor is it time bound, meaning local authorities are free to use this funding to best meet their local priorities. It is intended to support the creation of mainstream places for pupils aged 5 to 16. Local authorities can use this funding to create places in whole new schools, or through the expansion or remodelling of existing schools, and the Department for Education (DfE) expect that local authorities will work with any school in their local area in doing so, including academies and free schools; local authorities can also use Basic Need Funding to support alternative capital priorities, including SEND provisions in mainstream schools, on the condition that the local authority can still deliver its statutory duty to provide sufficient mainstream places across the city, within the Basic Need Grant Funding allocated; it is therefore considered acceptable to fund the fifty-four newly created local authority commissioned places in mainstream schools from the Basic Need Capital Grant and not the High Needs Capital Grant as originally approved. Other options considered: to continue to fund the fifty-four newly created places from the High Needs Capital Grant . This option was rejected due to the limited funding available to deliver the SEND Sufficiency Strategy.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Background

1.1Four approvals were obtained in 2024 for the use of High Needs Grant Funding to create SEND units in schools and academies at the five sites listed in this report. This report is to amend those resolutions passed or the decisions contained in individual decision records

1.2These projects are now either complete, on site, or progressing to construction contract, with all of them being delivered by September 2027.

1.3They will provide ninety-two (92) places across the five (5) sites. Fifty-four (54) of the ninety-two (92) places are to create additional mainstream specialist places, and can be funded from the Basic Need Capital Grant.

1.4The original approvals for these five (5) projects identified the use of High Needs Capital Grant to fund all ninety-two (92) places. However, since this time it is deemed this does not make best use of this grant and that the fifty-four (54) places will be better funded from the Basic Need Capital Grant.

1.5The table below shows the places created and provides a breakdown of pupils already on roll and new places created.

Table 1 Name Total Already Local Currently Re- Capacity on roll. Authority Approved charge Being To be Commissioned from to Basic Created funded places (new High Need from admissions). Needs Grant High To be funded Grant. Needs from Basic Grant. Need Grant.

Djanogly 16 8 8 £400,000 £200,000 Strelley Academy * Milford 16 8 8 £700,000 £350,000 Primary Academy Glade Hill 16 8 8 £2,050,000 £1,025,000 Primary School Maintained Fernwood 24 4 20 £3,150,000 £2,625,000 School Academy Nottingham 20 10 10 £2,080,000 £1,040,000 Girls Academy

Total 92 38 54 £8,380,000 £5,240,000

Reasons for recommendations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Reallocation of Basic Need Grant Funding to High Needs ProjectReport 113 KB DownloadRead as text

At this meeting

Whole meeting
99MinutesOn the agenda
100Reallocation of Basic Need Grant Funding to High Needs ProjectThis decision
101Local Youth TransformationApproved

Who was there

8 of 19 attended
CB
Councillor Cheryl BarnardCommittee Member, present
BB
Beth BrownOfficer, in attendance
MC
Michael CareyClerk, in attendance
SF
Stuart FairOfficer, in attendance
JH
Councillor Jay HayesCommittee Member, present
CJ
Councillor Corall JenkinsCommittee Member, present
NJ
Nicki JenkinsOfficer, apologies
HK
Councillor Helen KalsiCommittee Member, present
NK
Councillor Neghat KhanChair, present
LL
Lucy LeeOfficer, expected
SL
Councillor Sam LuxCommittee Member, present
NM
Neil McArthurOfficer, expected

All 19 on the meeting page

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open