Procurement of digital, AI, automation and telephony platforms - key decision

Approved Executive 1 paper

AI summaryNottingham City Council's Commissioning and Procurement Executive Committee approved £1.9m to replace fragmented digital, AI, automation and telephony systems with one supplier, under a two-year contract extendable by three one-year extensions.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSpend and delegated authority to Chief Technology Officer
Money£1.9mTwo-year contract, with three one-year extensions
What happens nextAward via frameworkCrown Commercial Services Back Office Software 2
Who it affectsAll wardsCouncil-wide digital and customer contact services

What was decided

Approved spend of £1.9m to procure a single-supplier contract for replacement digital, AI, robotic process automation and telephony solutions, initially for two years with an option to extend by three further one-year periods.

Delegated authority to the Chief Technology Officer, in consultation with the appropriate Executive Member, to award and enter into the contract up to £1.9m using approved procurement methods.

Why

Existing digital, AI, telephony and automation services are spread across multiple suppliers, increasing complexity, cost and technical risk and making joined-up customer journeys difficult. Report 1.1, 1.2, 1.6

Several current contracts are nearing the end of their term, creating a timely opportunity to tender replacements rather than extend arrangements that no longer provide flexibility or value for money. Report 1.3, P20

Using an approved procurement framework allows faster, lower-risk award to pre-qualified suppliers with pre-agreed terms, while remaining compliant with procurement regulations. Report 1.16, 1.17, P22

What happens next

Run a compliant call-off through the Crown Commercial Services Back Office Software 2 framework, with a Data Protection Impact Assessment completed and any issues built into the specification and contract. Report 6.1, 6.2, 8.1, P22

Time the new contract to start as current contracts end, to avoid a break in service, and manage implementation alongside other planned IT work. Report P52, P58

Contract manager to complete a balance scorecard and tiering tool, with regular post-project reviews to confirm benefits and value for money. Report P54, P59

The money

  • £1.9m Total value of the decision, covering the initial two-year contract and any extensions Report 5.1

Options considered

  • Rejected: Do nothing or extend existing contracts. Would keep the fragmented technology landscape, increase integration risk and costs, and prevent better value for money Report P26, P27
  • Rejected: Procure separate point solutions for digital, AI, telephony and automation. Would continue the siloed model, needing multiple suppliers and complex integrations and limiting joined-up services Report P28, P29
  • Rejected: Avoid frameworks and run only full open tenders. Frameworks are faster, lower risk and fully compliant, with pre-qualified suppliers and pre-agreed terms Report P30, P31

Implications

  • Legal: Call-off must follow framework rules and the Council's Contract Procedure Rules; a Data Protection Impact Assessment is required and must be reflected in the specification and contract. Report 6.1, 6.2, 8.1, P63, P65
  • Risk: Risks of fragmented customer experience, increased technical risk, poor value for money, weak data protection and short-term extensions are to be mitigated by the consolidated procurement, rationalised estate and stronger contractual requirements. Report P33, P34, P35, P36, P37
  • Equalities: An Equality Impact Assessment has been carried out and due regard will be given to any issues raised. Report 8.2
  • Climate: A Carbon Impact Assessment has been carried out and due regard will be given to any issues raised. Report 8.3
  • Financial: Soft market testing suggests the new cost may be lower than existing contracts through economies of scale, but final cost and any savings are not yet confirmed. Report 5.2
  • Staffing: A single-supplier approach should reduce the burden of managing multiple supplier relationships and free internal capacity for service delivery. Report 1.12, P72
  • Other: An initial two-year term with three one-year extensions allows the Council to consider potential Local Government Reorganisation opportunities, with an appropriate break clause included. Report 1.18

Who and where

  • Residents and service users across all wards who contact the Council by digital, AI-assisted and telephone channels Report P81, 1.2, P71
  • Customer Services and contact centre staff who manage enquiries across channels Report 1.2, 1.12
  • The Council's IT and procurement teams who will run the tender and manage the new contract Report 1.13, P54

Timeline

  • Two-year initial contract term, with option of three further one-year extensions: Length of the approved contract for digital, AI, automation and telephony services Report 1.18
  • Existing contracts nearing the end of their term: Window in which the new contract is intended to be awarded and implemented without a gap in service Report 1.3, P52, P58
  • 23/03/2026: Solicitor and Lead Procurement Officer comments on the report Report P48, P55
  • 23/03/2026: Chief Technology Officer comments confirming IT has no concerns Report P60
  • 26/03/26: Strategic Finance Business Partner sign-off on the proposal Report P42

Plain English for the jargon

  • Robotic Process Automation: Software that automates routine, rules-based digital tasks normally done by a person.
  • Crown Commercial Service Back Office Software 2 framework: A pre-procured government framework that lets public bodies buy back-office software, including cloud, on-premise or hybrid options, under set terms.
  • Data Protection Impact Assessment (DPIA): A process required under UK GDPR Article 35 to assess and reduce the privacy risks of a project that is likely to involve high-risk data processing.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item75

Resolved

Resolved to (1) approve spend of £1.9m to procure a 5-year contract (2 years, with an option to extend by a further 3 x 1 year extensions) for replacement Digital, AI, Robotic Process Automation and Telephony solutions through one supplier; (2) delegate authority to the Chief Technology Officer, in consultation with the appropriate Executive Member, to award a contract, via a compliant Procurement Framework, and to enter into the contract up to the value of £1.9m, using approved procurement methods. Reasons for recommendations a) Recommendation 1 This recommendation has been proposed to enable the Council to replace its current fragmented set of digital, AI, telephony and automation solutions with modern, sustainable arrangements that better meet current and future service needs. Existing solutions are delivered through multiple suppliers, increasing complexity, cost and technical risk, while limiting the Council’s ability to deliver seamless end?to?end customer journeys. Several existing contracts are approaching the end of their term, creating a timely opportunity to tender replacement solutions rather than extending arrangements that no longer provide sufficient flexibility, capability or value for money. Approving spend for a defined contract period provides the certainty required to procure solutions that support digital transformation, service resilience and improved customer experience, while remaining affordable and scalable. b) Recommendation 2 This recommendation has been proposed to give the Council flexibility to use approved procurement frameworks where appropriate, enabling contracts to be awarded more quickly while remaining fully compliant with procurement regulations. Frameworks have already been competitively procured and legally established, reducing procurement risk and administrative burden. Using compliant frameworks provides access to pre ... view the full minutes text for item 75.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Commissioning and Procurement Executive Committee

Background

1.1The Council’s current digital, AI, telephony and automation services are delivered through multiple suppliers and contracts, which increases complexity, support effort and cost, and makes it harder to manage services in a consistent and strategic way.

1.2Using separate systems across digital, telephone and automation channels creates a fragmented customer journey as each piece of technology has to be configured to work with another. It is therefore difficult to provide a seamless experience for users of our systems, particularly where customers move between online and AI assisted services through to our established contact centres. A replacement solution can be designed to effectively support end‑to‑end customer journeys, ensuring that enquiries are handled efficiently from first contact through to resolution across different channels seamlessly, providing a much improved experience and a simplified technological environment.

1.3Several existing contracts are nearing the end of their term, creating a natural and timely opportunity to improve our services.

1.4Tendering replacement solutions provides an opportunity to test the market and ensure the Council continues to achieve best value for money in a rapidly evolving technology landscape and allows us to consider our technology provision against future changes to the local government landscape.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of digital, AI, automation and telephony platforms: key decisionDecisions 141 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 13 attended
NM
Neil McArthurOfficer, expected
HI
Heather InghamCommittee Member, expected
RS
Richard SmithCouncil Staff, expected
AS
Ashley ShandCouncil Staff, expected
ML
Mark LeavesleyClerk, expected
CB
Councillor Cheryl BarnardCommittee Member, apologies (on leave)
JH
Councillor Jay HayesVice Chair, present
CJ
Councillor Corall JenkinsCommittee Member, present
ER
Councillor Ethan RadfordChair, apologies (personal reasons)
SF
Stuart FairOfficer, expected
HK
Councillor Helen KalsiCommittee Member, present
RA
Robert AitkenOfficer, expected

All 13 on the meeting page

More from Nottingham Commissioning and Procurement Executive Committee

All decisions
MeetingDecisionOutcome
14 Apr 2026 Public Health Funerals and The Nottingham Funeral - key decisionResolved to (1) approve: (a) continuation of the Nottingham Funeral Service in order to address funeral poverty in No... Approved Open
14 Apr 2026 Legal support for expiry of Private Finance Initiatives - key decisionResolved to approve (1) spend of a total £2million (£1.5million on general legal support and £0.5million specifically... Approved Open
14 Apr 2026 Procurement of new railway gantry - key decisionResolved to approve that: (1) the Council procure, via an open market competition, and up to the maximum value as det... Approved Open
10 Mar 2026 Agency Worker contract - key decisionResolved to (1) approve a tender process be undertaken to procure a corporate agency worker contract, with a maximum ... Approved Open