Nottingham City Council
Commissioning and Procurement Executive Committee, Tuesday 14 April 2026 at 9.30am

Procurement of new railway gantry - key decision

Approved Executive 1 paper

AI summaryNottingham City Council approves open market competition to procure a design and build contractor for a new rail gantry on its district heating network, with contract values in an exempt appendix.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedDesign and build contractor via open competition, plus technical services via frameworks
MoneyMaximum values detailed in the exempt appendix
What happens nextProcurement to beginOpen competition for contractor, framework call-off for technical services
Who it affectsCastle ward and district heating customersc5,000 households and c200 electricity customers on the network

What was decided

The Council will procure, via open market competition, a design and build contractor to deliver a new rail gantry for council infrastructure. Report 1.3, 2.1

Additional technical services to support the project will be procured via appropriate frameworks. Report 2.2

Authority is delegated to the Corporate Director of Communities, Environment and Resident Services to enter into the contracts, within the parameters of the report. Report 2.3

Why

Procuring as a design and build scheme makes the contractor responsible for the design, reducing design-builder interface risk and giving earlier cost certainty from supply chain input. Report 2.1

An open market competition gives the Council flexibility to set scheme-specific contractual requirements, including Network Rail approval of the bidder and protections for other parties, which frameworks may not allow. Report P8

Continuing with the supplier that has taken technical services to RIBA Stage Three offers continuity and value for money. Report 2.2

What happens next

The Corporate Director will use delegated authority to enter into contracts for the gantry and associated services. Report 2.3

The contract will include the ability for the Council to break or pause at no cost on completion of the RIBA Stage Four design. Report 1.4

The Procurement Team will work with the client team to ensure appointments comply with Contract Procedure Rules and the Procurement Act 2023. Report 7.1

Options considered

  • Rejected: Not proceed with moving the gantry. Landlord would likely still require it moved; a temporary solution would be needed and later replaced at Council cost, causing abortive works and added network risk. Report P14
  • Rejected: Separately procure the architect and the constructor. Reasons set out in the exempt appendix. Report P15
  • Rejected: Use a framework for the design and build contractor. Frameworks may not provide the contractual flexibility needed, and not all suitable firms are likely to sit on the same framework. Report P16
  • Rejected: Thrust bore a tunnel under the railway instead of building a gantry. Engineering advice judged it not best practice to bury high pressure steam pipes. Report P16
  • Rejected: Use other overground routes instead of a gantry. Options explored had land complexities and did not offer value for money. Report P17

Implications

  • Risk: The market may not accept some of the Council's indemnity requirements; if so, each case would be decided on its merits, which could mean the Council accepting more risk. Report P19
  • Risk: If the new connection fails, steam supply to the heat station could be lost, but both sites have contingency plans to use while the issue is fixed. Report P20
  • Legal: The successful bidder will need Network Rail approval, and the contract must protect other parties such as other landowners. Report P8
  • Other: No data protection, equality impact or carbon impact assessment is required because the scheme replaces an existing asset; social value will be scored as part of the tender. Report 8.1

Who and where

  • Around 5,000 households supplied with heat and hot water from the district heating network Report 1.1
  • Around 200 domestic and commercial customers receiving electricity via the private wire Report 1.1
  • Residents and businesses in Castle ward Report P39
  • Other landowners whose interests need protection in the contract Report P8

Timeline

  • 24 February 2026: Lead Procurement Officer signed off the report, confirming no procurement concerns. Report P28
  • 2026-04-14: Decision taken by the Commissioning and Procurement Executive Committee to approve the procurement approach.

Plain English for the jargon

  • RIBA Stage Four: The Royal Institute of British Architects design stage covering detailed technical design before construction.
  • District heating network: A system that distributes heat and hot water from a central source to multiple buildings.
  • Private wire: A dedicated electricity supply line connecting a generator directly to customers.
  • Gantry: A bridge-like structure that carries pipes or cables over an obstacle such as a railway.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item77

Resolved

Resolved to approve that: (1) the Council procure, via an open market competition, and up to the maximum value as detailed in the exempt appendix, a design and build contractor to deliver a new rail gantry for Council infrastructure; (2) additional technical services required to support the project are procured via appropriate frameworks, and up to the maximum value as detailed in the exempt appendix; (3) authority is delegated to the Corporate Director of Communities, Environment and Resident Services to enter into contracts for the delivery of the rail gantry and associated services, subject to the parameters set out in the report. Reasons for recommendations a) Recommendation 1 The installation of a new rail gantry is a complex undertaking due to its interfaces with both an operational railway and district heating system. It is essential therefore that the RIBA Stage Four design is fully understood and has the confidence of the building contractor and their supply chain. By procuring the project as a design and build scheme the building contractor becomes responsible for the design thereby reducing the risk of issues occurring between the designer and builder. This approach also allows the supply chain to input into costings at an earlier stage of the process thereby helping the project gain greater cost certainty in advance as to would normally be the case. The procurement will be via an open market competition rather than a framework as this will enable to the Council to ensure that all of its contractual requirements with regards to the scheme can be met. These will range from the successful bidder being approved by Network Rail to its ability to give protection to other parties involved in the works, for example other landowners. On a framework there is not always the flexibility to do this. b) Recommendation 2 A number of technical services will be required to deliver the project; these include specialisms such as cost consultants and contract supervisor roles. The Council intends to procure these through existing frameworks as there has already been involvement from a supplier in providing some of these services up to RIBA Stage Three. Proceeding with this company will allow continuity and should provide value for money due to them already being familiarity with the scheme. c) Recommendation 3 The reasons for recommendation 3 are set out in an exempt appendix to the report. Other options considered The following options were considered, and rejected, for the reasons below. a) not to proceed with moving the gantry – the gantry would still need to be moved with the landlord likely to insist on a temporary solution being put in place. This temporary solution ... view the full minutes text for item 77.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Commissioning and Procurement Executive Committee

Background

1.1The Council operates a district heating network that supplies c5,000 households with heat and hot water as well as electricity via a private wire to c200 domestic and commercial customers.

1.2The network is fed from a high-pressure steam feed received from Eastcroft Incinerator which is transferred to the London Road Heat Station via a pipe connection. This connection crosses the canal (twice), goes under London Road and crosses the railway via a gantry to the east of Nottingham Station.

1.3The Council has been asked to relocate the rail gantry by the landowner. This will require the Council to procure a design and build contractor and associated specialist advisors, to develop a Royal Institute of British Architects (RIBA) Stage Four design and ultimately build the new gantry.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of new railway gantry: key decisionDecisions 118 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 13 attended
NM
Neil McArthurOfficer, expected
HI
Heather InghamCommittee Member, expected
RS
Richard SmithCouncil Staff, expected
AS
Ashley ShandCouncil Staff, expected
ML
Mark LeavesleyClerk, expected
CB
Councillor Cheryl BarnardCommittee Member, apologies (on leave)
JH
Councillor Jay HayesVice Chair, present
CJ
Councillor Corall JenkinsCommittee Member, present
ER
Councillor Ethan RadfordChair, apologies (personal reasons)
SF
Stuart FairOfficer, expected
HK
Councillor Helen KalsiCommittee Member, present
RA
Robert AitkenOfficer, expected

All 13 on the meeting page

More from Nottingham Commissioning and Procurement Executive Committee

All decisions
MeetingDecisionOutcome
14 Apr 2026 Public Health Funerals and The Nottingham Funeral - key decisionResolved to (1) approve: (a) continuation of the Nottingham Funeral Service in order to address funeral poverty in No... Approved Open
14 Apr 2026 Procurement of digital, AI, automation and telephony platforms - key decisionResolved to (1) approve spend of £1.9m to procure a 5-year contract (2 years, with an option to extend by a further 3... Approved Open
14 Apr 2026 Legal support for expiry of Private Finance Initiatives - key decisionResolved to approve (1) spend of a total £2million (£1.5million on general legal support and £0.5million specifically... Approved Open
10 Mar 2026 Agency Worker contract - key decisionResolved to (1) approve a tender process be undertaken to procure a corporate agency worker contract, with a maximum ... Approved Open