Bulwell Local Regeneration Fund Community Grant Scheme

Approved Executive 2 papers

AI summaryNottingham City Council Executive Board has approved reallocating £1.5m of Local Regeneration Funding to three new community and business grant schemes for Bulwell and Bulwell Forest wards.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFor Bulwell and Bulwell Forest wards
Money£1.5mReallocated from £19.8m LRF
What happens nextApplications open May 2026Business grants from May 2026
Who it affectsBulwell and Bulwell Forest wardsCommunity groups, businesses, venues

What was decided

Reallocate £1.5m of Local Regeneration Funding to establish three Community and Business Grant Schemes covering Bulwell and Bulwell Forest wards. Report 1.5, 1.6

Delegate authority to the Corporate Director for Growth and City Development, in consultation with the Executive Member for Strategic Regeneration, Property and Communications, to manage the budget, move funds between schemes, award grants, and ensure procurement compliance. Report 1.22

Why

Consultation showed strong community desire for the funding to be focused where it gives the most local benefit. Report 2.1, 1.4

The grant award scheme is a tried and tested way of allocating funding in a fair and transparent manner. Report 2.2

The scheme offers a route to ensure the full £19.8m LRF allocation is expended for local benefit. Report 2.3, 1.17

What happens next

Business Grants will open on a rolling basis from May 2026 and Community Event and Activity Grant applications will be received from May to July 2026. Report 1.9, 1.11

Funding may be moved between the three schemes based on demand, and a second application window may be opened if extra resource becomes available. Report 1.16, 1.18

The Corporate Director and Executive Member will be briefed on scoring outcomes before final grant award decisions are made. Report 1.22

The money

  • £1.5m Reallocation of Local Regeneration Funding to the three grant schemes Report 1.5, 5.1
  • £19.8m Total Local Regeneration Funding awarded to the Bulwell Town Centre Regeneration scheme Report 1.1, 1.2
  • £15,000 and £200,000 Range for Community Venues and Spaces Grant Report 1.7
  • between £5,000 and £14,999 Range for Community Event and Activity Grant Report 1.9
  • between £1,000 and £5,000 Range for Business Growth and Shop Front Improvement grants Report 1.11
  • between £500 and £5,000 Range for Business Decarbonisation grants Report 1.11

Options considered

  • Rejected: Do nothing. Would leave grant unspent and fail to deliver outputs and outcomes from the three schemes Report 3.1
  • Rejected: Identify additional work to deliver under the public realm improvements contract. Would not meet community-led aspirations or the outcomes expected from the three grant schemes Report 3.2

Implications

  • Financial: The £1.5m is ring-fenced from the public realm works contract, which has its own risk allowances and contingencies, so there is no risk of the grant fund being used to support the public realm scheme. Report P35, 5.2
  • Financial: LRF funding is eligible only as capital expenditure and cannot fund revenue activity or create a revenue burden on the council. Report 1.19, P36
  • Financial: Staff time to manage the grants will be funded through a Capacity and Capability revenue grant from MHCLG accepted in an Operational decision on 30th May 2025, with no expected Medium Term Financial Plan implications. Report 1.20
  • Legal: Grant agreements must specify eligible expenditure, monitoring requirements and clawback provisions to ensure compliance with MHCLG funding conditions. Report P43, P44
  • Legal: Where grants are awarded to businesses, officers must ensure compliance with the Subsidy Control Act 2022 and keep appropriate records. Report P46
  • Legal: Where the council procures works, goods or services these must follow the council's Contract Procedure Rules, and the grant process must keep a clear audit trail of assessment and moderation. Report P45
  • Risk: Risk of overspend on the public realm scheme is mitigated by the contract's risk allowances and contingencies, protecting the £1.5m grant allocation. Report P29
  • Risk: Risk of insufficient or low quality applications will be addressed through pre-application engagement, clear guidance, targeted outreach, and early promotion of Dynamic Grant Process registration. Report P29
  • Risk: Risk of capacity and delivery challenges, particularly for smaller voluntary and community sector organisations, will be addressed through robust delivery plans, phased milestone payments, early inception meetings and proportionate monitoring. Report P29
  • Risk: Risk of conflicts of interest or perceived bias in assessment will be addressed through formal declarations, a two-assessor plus moderator model, ranked scoring, and a full audit trail of decisions. Report P30
  • Other: Projects are expected to deliver community benefits such as low or zero carbon energy infrastructure, greener spaces, volunteering opportunities, jobs, and improved retail areas. Report 1.8, 1.10, 1.12

Who and where

  • Community groups, venues and organisations in Bulwell and Bulwell Forest wards Report 1.7, 1.9, P68
  • Businesses based in Bulwell and Bulwell Forest wards Report 1.11, P68
  • Ward councillors and the local MP Report 1.4, 1.21
  • Nottingham City Council's Economic Development team, which will administer the schemes Report 1.5, 1.13

Timeline

  • November 2023: Council awarded £19.8m Levelling Up Funding for Bulwell Town Centre Regeneration Report 1.1
  • July 2024: Following change of Government, programme responsibility moved to MHCLG and became the Local Regeneration Fund Report 1.2
  • 30th May 2025: Operational decision accepted Capacity and Capability revenue grant for staff time Report 1.20
  • September 2025: MHCLG confirmed simplification of fund management, captured in a revised MoU Report 1.3
  • 27th February 2026: Revised Memorandum of Understanding between MHCLG and the council signed Report 1.3
  • 4th March 2026: Capital finance advice provided by Victoria Gelderd, Team Leader (Capital) Report P38
  • 5 March 2026: Legal advice provided by Pamela Nsofor, Solicitor Contracts and Commercial Report P48
  • 18th March 2026: Commercial Business Partner advice provided by Paul Rogers Report P38
  • 21st April 2026: Executive Board decision to reallocate £1.5m and approve the three grant schemes
  • May 2026: Bulwell Business Grants Programme opens on a rolling basis Report 1.11
  • May to July 2026: Application window for the Community Event and Activity Grant Report 1.9
  • August 2026 to July 2027: Delivery period for Community Event and Activity Grant projects Report 1.9
  • End of 2026: Public realm works under the wider Bulwell scheme anticipated to complete Report 1.1
  • October 2026 to September 2027: Delivery period for Community Venues and Spaces Grant projects Report 1.7
  • March 2028: All Business Grants projects to be completed Report 1.11, P29

Plain English for the jargon

  • Local Regeneration Fund (LRF): The £19.8m formerly known as Levelling Up Funding, now managed by MHCLG for the Bulwell Town Centre Regeneration scheme.
  • Dynamic Grant Process (DGP): A pre-approved Nottingham City Council framework that allows quick and compliant commissioning of external suppliers for externally funded projects, structured into thematic lots.
  • Lot 2 of the DGP: The lot covering community and cultural development, including community cohesion, cultural participation, social mobility, and engagement of marginalised groups.
  • MHCLG: Ministry of Housing, Communities and Local Government, the UK Government department now responsible for the funding.
  • MTFP: Medium Term Financial Plan, the council's multi-year revenue budget planning document.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item108

Resolved

Resolved to: (1) approve the re-allocation of £1.5m of Local Regeneration Funding (LRF) to establish three Community and Business Grant Schemes for Bulwell and Bulwell Forest wards; (2) delegate authority to the Corporate Director for Growth and City Development, in consultation with the Executive Member for Strategic Regeneration, Property and Communications, to: (i) implement and manage the £1.5m budget for the three Community and Business Grant Schemes; (ii) allocate any additional LRF3 funding into the schemes should unspent contingency remain following completion of contracted public realm works; (iii) approve the movement of funding between the three proposed grant schemes in response to actual levels of demand; (iv) award, sign and enter into all associated grant agreements required for delivery of successful applicants’ projects; (v) ensure that all works, services or supplies relating to all projects are procured in accordance with Contract Procedure Rules. Reason for decisions: it has been clear from consultation that there is a strong desire within the local communities to ensure that the LRF funding is focussed where it gives the most local benefit; the grant award scheme is a tried and tested way of ensuring funding is allocated in a fair and transparent manner; the grant award scheme offers a route to ensure that the full allocation of £19.8m funding is expended to the benefit of local communities. Other options considered: do nothing. This option was rejected as it would result in unspent grant award and would fail to deliver on outputs and outcomes anticipated through the three proposed grant schemes; identify additional work to deliver under the public realm improvements contract. This option has been rejected as it would not meet community-led aspirations and would not deliver the outcomes anticipated through the three proposed grant schemes.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Background

1.1In November 2023 Nottingham City Council was awarded £19.8m of Levelling up Funding (LUF) by the then Department for Levelling Up, Housing and Communities (‘DLUHC’) to deliver a Bulwell Town Centre Regeneration scheme. These works are well progressed and anticipated to completed by the end of 2026.

1.2Following the change of Government in July 2024, programme responsibility moved to the Ministry of Housing, Communities and Local Government (MHCLG) and the funding would now be managed as the Local Regeneration Fund (LRF).

1.3MHCLG confirmed in September 2025 a simplification to how this fund is managed, allowing a much greater degree of flexibility to adapt schemes to meet local needs. These changes to the funding arrangements are captured in a revised Memorandum of Understanding (MoU) between MHCLG and NCC, dated 27th February 2026. MHCLG has also confirmed that local authorities no longer require approval for changes, provided conditions in the revised MoU are satisfied.

1.4Engagement with community groups, ward members and the MP demonstrates strong support for directing uncommitted funds to local priorities beyond the original project scope

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Bulwell LRF Report UpdatedReport 142 KB DownloadRead as text
PDF
Bulwell Local Regeneration Fund Community Grant SchemeReport 172 KB Download

At this meeting

Whole meeting

Who was there

8 of 21 attended
CB
Councillor Cheryl BarnardCommittee Member, apologies
BB
Beth BrownOfficer, apologies, sent representative
MC
Michael CareyClerk, in attendance
SF
Stuart FairOfficer, apologies, sent representative
JH
Councillor Jay HayesCommittee Member, present
LH
Lucy HubberOfficer, in attendance
CJ
Councillor Corall JenkinsCommittee Member, present
NJ
Nicki JenkinsOfficer, in attendance
HK
Councillor Helen KalsiCommittee Member, present
NK
Councillor Neghat KhanChair, present
LL
Lucy LeeOfficer, expected
SL
Councillor Sam LuxCommittee Member, apologies

All 21 on the meeting page

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open