Preparing a New Local Plan for Nottingham

Approved Executive 3 papers

AI summaryNottingham City Council Executive Board approves preparation of a new Local Plan and Joint Minerals Local Plan, with £108,474.57 government funding, publishing a Notice of Intention by 30 June 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedAlso approved Joint Minerals Local Plan with Nottinghamshire County Council
Money£108,474.57 government fundingAwarded for new Local Plan preparation costs
What happens nextPublish Notice of Intention by 30 June 2026Gateway 1 self-assessment scheduled for October 2026
Who it affectsAll wards in Nottingham CityPlan covers entire city administrative area

What was decided

The Executive Board approved preparation of a new Local Plan and publication of the formal Notice of Intention to Commence under the Town and Country Planning (Local Planning) (England) Regulations 2026. Report 1.1

Authority was delegated to the Strategic Director of Planning and Transport, in consultation with the Executive Member for Housing and Planning, to undertake scoping work, evidence gathering, and agree timetable updates.

Preparation of a Joint Minerals Local Plan for Nottingham and Nottinghamshire was approved, with delegated authority to approve and publish its Notice of Intention and timetable. Report 1.11

Why

National planning policy requires all authorities to maintain an up-to-date Local Plan, with consequences for failure including increased government intervention and appeal risk. Report 2.1

The existing Land and Planning Policies Document Part 2 Local Plan (2020) is over five years old and considered out-of-date, weakening the Council's ability to shape development. Report 1.4, 2.1

Minerals planning policies are out-of-date and minerals resources span across authority boundaries, making a joint approach with the County Council the best option. Report 1.11, 2.1

What happens next

Officers will undertake scoping and preparatory tasks during Summer 2026, including stakeholder engagement, baseline evidence review, and preparation for Gateway 1. Report 1.8

A Project Initiation Document will be prepared before Gateway 1, and recruitment will take place including one new post and backfilling two existing vacancies. Report P25

A Local Plan Working Group will be established for councillors and officers, with updates reported to the Homes, Economy and Infrastructure Scrutiny Committee. Report 1.10

The money

  • £108,474.57 Government new local plan funding awarded to the City Council Report 1.3, P31

Options considered

  • Rejected: Defer commencement of a new Local Plan until greater clarity on local government reorganisation. National policy makes clear LGR is not a valid reason to delay; deferral would prolong reliance on an out-of-date framework and increase appeal and intervention risk. Report P19
  • Rejected: Rely on existing Local Plan policies supplemented by national policy and ad-hoc decision making. An out-of-date plan weakens ability to shape growth in line with local priorities and increases exposure to speculative development. Report P20
  • Rejected: Defer commencement of a new Minerals Plan until greater clarity on local government reorganisation. National policy makes clear LGR is not a valid reason to delay; joint preparation ensures full coverage of minerals policy across the reorganisation area. Report P21

Implications

  • Legal: Statutory duty to maintain an up-to-date Local Plan; failure to follow procedural requirements could invalidate later stages and expose the Council to legal challenge. Report 6.1, P35
  • Financial: Total Local Plan costs will exceed the government grant and be met from the approved Local Plan budget, increased via prior Star Chamber/Leadership decisions. Report P31
  • Financial: Joint Minerals Plan costs will be shared with Nottinghamshire County Council; the City's contribution will be limited and met from existing budget. Report 1.12, P31
  • Risk: Risk of misalignment if administrative boundaries change; mitigation includes joint evidence commissioning with Greater Nottingham Planning Partnership. Report 4.1, P25
  • Staffing: Recruitment needed: one new post plus backfilling two existing vacant posts in the Planning Policy Team. Report P25
  • Other: An Equalities Impact Assessment, Carbon Impact Assessment, and Strategic Environmental Assessment will be prepared and consulted on at the draft plan stage. Report 8.1

Who and where

  • All wards across Nottingham City Report P50
  • Statutory consultees and infrastructure providers involved in early stakeholder engagement Report 1.8
  • Neighbouring authorities in the Greater Nottingham Planning Partnership (Broxtowe, Rushcliffe) Report 4.1
  • Nottinghamshire County Council (joint minerals planning partner) Report 1.11

Timeline

  • June 2026: Notice of Intention to commence Local Plan preparation published Report P10, 1.5
  • October 2026: Gateway 1 self-assessment stage Report P10
  • September 2027: Gateway 2 assessment following first consultation on draft plan Report P11
  • September 2028: Gateway 3 assessment following consultation on proposed submission plan Report P12
  • Summer 2026: Scoping and preparatory tasks undertaken by officers Report 1.8

Plain English for the jargon

  • Local Plan: A statutory planning document setting out site allocations and policies used to determine planning applications.
  • Gateway 1, 2, 3: Statutory assessment stages under the Levelling-up and Regeneration Act 2023 plan-making framework, assessed by planning inspectors at key milestones.
  • EMCCA Spatial Development Strategy: A regional spatial strategy being prepared for the East Midlands Combined County Authority area.
  • Joint Minerals Local Plan: A plan covering minerals planning policies and site allocations across both Nottingham City and Nottinghamshire County administrative areas.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item28

Resolved

Resolved to: (1) approve the preparation of a New Local Plan for Nottingham, and the publication of the City Council’s formal ‘Notice of Intention to Commence’ the new Nottingham Local Plan (contained in Appendix 1), in accordance with the Town and Country Planning (Local Planning) (England) Regulations 2026; (2) approve and publish the Nottingham Local Plan timetable (contained in Appendix 2), and to delegate authority to the Strategic Director of Planning and Transport in consultation with the Executive Member for Housing and Planning, to agree any subsequent updates to the Local Plan timetable when necessary; (3) delegate authority to the Strategic Director of Planning and Transport in consultation with the Executive Member for Housing and Planning to undertake necessary scoping work and evidence gathering to support the new Local Plan, prior to the Gateway 1 Assessment stage; (4) approve the preparation of a Joint Minerals Local Plan for Nottingham and Nottinghamshire, and to delegate authority to the Strategic Director of Planning and Transport in consultation with the Executive Member for Housing and Planning, to approve and publish the ‘Notice of Intention’ to commence the Joint Minerals Plan and associated timetable. Reason for decisions: national planning policy and proposed reforms reinforce the requirement for all local planning authorities to maintain an up-to-date Local Plan, with explicit consequences for failure, including increased Government intervention in plan-making and decision-taking; an out-of-date plan weakens the Council’s ability to shape development, exposes planning decisions to appeal risk, and reduces leverage to secure infrastructure and affordable housing; Government has been clear that local government reorganisation does not justify delay in plan preparation; early commencement of a new Local Plan is essential both to retain local planning control and to provide the statutory spatial framework needed to enable delivery of the Nottingham Vision. It will also ensure the City’s priorities are fully aligned with, and positively contribute to, the preparation of the EMCCA Spatial Development Strategy, safeguarding Nottingham’s role within the wider regional growth agenda; Similarly, the City Council’s current minerals planning policies are out-of-date and the preparation of a Joint Minerals Local Plan for Nottingham and Nottinghamshire is considered to be the best approach for planning for minerals, which typically span across authority boundaries. Other options considered: defer commence of a new Local Plan until there is greater clarify on local government reorganisation . This option was rejected as national policy and proposed reforms make clear that LGR is not a valid reason to delay, and would prolong reliance on an out-of-date planning policy framework; rely on existing Local Plan policies supplemented by national policy and ad-hoc decision making . This open was rejected because an out-of-date Local Plan significant weakens the Council’s ability to shape growth in line with local priorities; defer commencement of a new Minerals Plan until there is greater clarify on local government reorganisation . This option was rejected as national policy and proposed reforms make clear that LGR is not a valid reason to delay, and would prolong reliance on an out-of-date planning policy framework.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Background

1.1The Levelling-up and Regeneration Act 2023 introduced a new Local Plan-making framework, replacing the former system with a streamlined 30-month plan preparation process.

1.2Under this new system, local planning authorities must give notice of their intention to commence plan-making before starting the 30-month process. This is a statutory requirement intended to ensure transparency, early engagement and readiness prior to Gateway 1. Gateway 1 then comprises a self-assessment to ensure that the authority is ready to start the 30-month process of producing the plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Notice of Intention to Commence a New Local PlanAppendix 1 127 KB Download
PDF
New Local Plan TimetableAppendix 2 85 KB Download
PDF
Preparing a New Local Plan for NottinghamReport 128 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 20 attended
BB
Beth BrownOfficer, apologies, sent representative
MC
Michael CareyClerk, in attendance
SF
Stuart FairOfficer, in attendance
JH
Councillor Jay HayesCommittee Member, present
PU
Councillor Patience Uloma IfedioraCommittee Member, apologies due to council business
NJ
Nicki JenkinsOfficer, apologies, sent representative
HK
Councillor Helen KalsiCommittee Member, present
NK
Councillor Neghat KhanChair, present
LL
Lucy LeeOfficer, expected
SL
Councillor Sam LuxCommittee Member, present
SM
Councillor Sulcan MahmoodCommittee Member, present
NM
Neil McArthurOfficer, in attendance

All 20 on the meeting page

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies