RESOLVED THAT: (i) The contents of the report be noted by Members; (ii) Subject to the approval of the capital bid of £83,300 submitted for 2018/19 by Full Council at its meeting on 22 February, that the building of the Ervins Lock Footbridge over the canal proceed; and (iii) William Saunders be retained to carry the project forward at Ervins Lock Footbridge as project managers.
Word for word from the decision Oadby and Wigston published for this meeting.Source: moderngov.oadby-wigston.gov.uk
Matter for Service Delivery Tuesday, 23 January Information and Committee 2018 Decision
Title: Facilities Services Update
Author(s): Margaret Smith (Facilities & Administration Team Leader)
1. Introduction
This report covers the progress and developments within the Facilities Section and sets out achievements and work in progress since 10 October 2017 when progress was last reported.
2. Recommendation(s)
2.1That Members note the information contained in the report.
2.2On the basis of the work carried out to date it is recommended that the Council proceeds with building Ervins Lock Footbridge over the canal, subject to the approval of a capital bid of £83,300 which has been submitted for 2018-19 and which will require approval of February Full Council. It is also recommended that William Saunders is retained to carry the project forward as project managers.
3. Capital Projects 2017-18
Ervin’s Lock Footbridge, South Wigston
3.1William Saunders was appointed to carry out feasibility works for this project and to offer advice on likely overall costs. This work, which included carrying out topographical surveys, obtaining utility records for the area and carrying out CCTV surveys of the canal bywash pipe, has now been completed. Draft details of a bridge design have been submitted to Canal and River Trust and the Principal Historic Buildings Officer at Leicestershire County Council for their comments. Feedback has been received from both which has resulted in minor amendments being made to the design which is now ready to be submitted for planning approval.
3.2Of the original budget of £51,700 (from S106 funds) a total of £4,306 has so far been spent on the feasibility works, generation of the draft design and meetings with Canal and River Trust leaving a balance of £47,394. William Saunders estimate that a further £83,300 will be required to complete the works. This includes costs associated with submitting the planning application, the foundations, manufacture and installation of the bridge, waterway stoppage/restriction licence, transport and cranage, air right fees to Canal and River Trust and project management.
3.3Once funding is approved, the next stages to be progressed (which can be done in parallel) are to:
• obtain the formal agreement and negotiate the maintenance obligation with Canal and River Trust, • prepare the design and access statement, heritage impact assessment and arboricultural survey required to be submitted with the formal planning application. Play Area Refurbishment
3.4A climbing unit is on order for Grittar Close play area using Section 106 funds. The balance beam and mushrooms which are rarely used will be removed to make way for this. Installation is expected to take place in early March.
3.5Following meetings with ward Councillors for Oadby Grange Ward, a consultation exercise was carried out for the play area at Florence Wragg Way. The consultation was advertised via the Council’s website, on social media, notices in the play area and on noticeboards, and letters were sent to local residents. The consultation closed on 19 January 2018. Once the results have been assessed a specification will be drawn up in order to obtain quotes. Installation of new equipment is anticipated to be in late Spring 2018 (avoiding school holidays).
3.6Borough Entry Signs (Greening the Borough Project)
The signs at Crow Mill, Aylestone Lane (Blue Bridge) and Kilby Bridge have been refurbished and returned to site. A strap line has been placed under each sign acknowledging the Borough’s successes in East Midlands in Bloom and Britain in Bloom.
3.7Horsewell Lane Pavilion Development
Prior to Christmas, Officers undertook a consultation exercise with current and potential users of the new pavilion, including the Wigston Club for Young People. Following the consultation the views of customers and the internal facilities management team have been taken into consideration and a development brief is now being prepared to go out to tender for a design and build contractor.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.