Resolved
RESOLVED THAT: The contents of the report and Appendices be noted.
Service Delivery Committee noted this item on Tuesday 11 September 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT: The contents of the report and Appendices be noted.
Service Delivery Tuesday, 11 Matter for Committee September 2018 Information
Report Title: Facilities Service Update (Q1 2018/19)
Report Author(s): Margaret Smith (Facilities & Administration Team Leader)
Purpose of Report: To update Members on work undertaken by the Facilities Section.
Report Summary: This report details work completed by the Facilities Section between 1 April and 30 June 2018.
Recommendation(s): That the contents of the report and appendices be noted.
Responsible Strategic Stephen Hinds (Director of Finance & Transformation) Director, Head of Service (0116) 257 22681 and Officer Contact(s): [email protected]
Adrian Thorpe (Head of Planning, Development and Regeneration) (0116) 257 2645 [email protected]
Margaret Smith (Facilities & Administration Team Leader) (0116) 257 2832 [email protected]
Corporate Priorities: Effective Service Provision (CP2) Green & Safe Places (CP4)
Vision and Values: Teamwork (V3) Innovation (V4) Customer Focus (V5)
Report Implications:-
Legal: There are no implications arising from this report.
Financial: Work is carried out within existing capital and revenue budgets.
Corporate Risk Management: Effective Utilisation of Assets/Buildings (CR5) Economy/Regeneration (CR9)
Equalities and Equalities There are no implications arising from this report. Assessment (EA): EA not applicable.
Human Rights: There are no implications arising from this report.
Health and Safety: The implications are as set out in the report.
Statutory Officers’ Comments:-
Head of Paid Service: The report is satisfactory.
Chief Finance Officer: The report is satisfactory. Monitoring Officer: The report is satisfactory.
Consultees: None.
Background Papers: None.
Appendices: 1. Horsewell Lane Pavilion Proposed Elevations 2. Horsewell Lane Pavilion Programme
1. Progress on Capital Projects During 1st Quarter 2018-19
1.1Florence Wragg Way Play Area, Oadby
Work started on site to remove the old equipment and install new equipment on 18 June 2018. The toddler swings have been retained and refurbished but all of the other equipment has been replaced with new and more challenging items in line with the results of the public consultation. The installation was completed on 13 July, at which point there was a post installation inspection carried out by an independent Registered Play Inspector before the area was accepted as complete by the Council. One item (trapeze handles on the monkey bar unit) failed to meet the required standards (BS EN 1176 Part 1) due to a finger trap hazard however, these have now been replaced by the manufacturer with compliant handles. The inspector also noted that the free (circulation) space between the nearest point of two items of equipment overlaps by 100mm but he has deemed this to be ‘very low risk’ and therefore no further action is required to be taken in this respect.
Feedback from users has been very positive although there have been a number of comments received that the junior slide is difficult for younger children to access as the only route to it is via the monkey bars or climbing wall which they find too difficult. Access to the slide forms part of the increased challenge requested via the consultation. However, the Facilities and Admin Team Leader has asked the installer to advise whether the equipment can be re-configured to make access easier without compromising the safe lower age limit for the slide. The play area was funded by Section 106 contributions and is now fully open for public use.
1.2Ervins Lock Footbridge, South Wigston
The planning application was submitted on 31 May 2018. The Canal and River Trust (CRT) has raised some queries on the application which have been responded to by our appointed project managers, William Saunders, on behalf of the Council.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Horsewell Lane Pavilion Proposed ElevationsAppendix 1 | 316 KB | Download |
PDF |
Horsewell Lane Pavilion ProgrammeAppendix 2 | 137 KB | Download |
PDF |
Facilities Services Update (Q1 2018/19)Report | 85 KB | DownloadRead as text |
Follow Service Delivery Committee at Oadby and Wigston and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Minutes of the Previous MeetingRESOLVED THAT: The minutes of the previous meeting held on 9 June 2026 be taken as read, confirmed and approved. | Approved | Open |
| 1 Sep 2026 | Action List Arising from the Previous MeetingRESOLVED THAT: The action list from the previous meeting held on 09 June 2026 be noted. | Noted | Open |
| 1 Sep 2026 | Corporate Performance Update (Q1 2026/27)RESOLVED THAT: The performance of the Council against its Corporate Objectives in delivering services be noted. Counc... | Noted | Open |
| 1 Sep 2026 | Housing Management Performance and Compliance (Q1 2026/27)RESOLVED THAT: The content of the report and appendices be noted. | Noted | Open |
| 9 Jun 2026 | Apologies for AbsenceRESOLVED THAT: Councillor K J Loydall be appointed as Vice-Chair for the duration of this meeting only. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.