Resolved
RESOLVED THAT: i) The content of the report and appendices be noted; and ii) The additional capital expenditure as set out at paragraph 3 of the report be approved
Policy, Finance & Development Committee noted this item on Tuesday 15 September 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT: i) The content of the report and appendices be noted; and ii) The additional capital expenditure as set out at paragraph 3 of the report be approved
Policy, Finance and Matter for Tuesday, 15 Development Information and September 2020 Committee Decision
Report Title: Financial Outturn Report (Q1 2020/21)
Report Author(s): Comie Campbell (Interim Financial Services Manager)
Purpose of Report: This report gives a summary of the overall Council position for the financial year 2020/21 at the end of the first quarter for both Revenue and Capital Expenditure.
Report Summary: The Council has completed quarter one of the financial year 2020/21. There is a significant variation in the General Fund due to COVID-19 related additional expenditure and income losses. A full capital pro- gramme is at Appendix 1 which includes new schemes for 2020/21 and schemes from the 2019/20 programme which are still to complete.
Recommendation(s): A. That the contents of the report and appendix be noted; B. That the additional capital expenditure (as set out at paragraph 3 of the report) be approved.
Senior Leadership, Stephen Hinds (Deputy Chief Executive) Head of Service, (0116) 257 2736 Manager, Officer and [email protected] Other Contact(s): Comie Campbell (Interim Financial Services Manager) (0116) 257 2713 [email protected]
Corporate Objectives: Providing Excellent Services (CO3)
Vision and Values: “A Stronger Borough Together” (Vision) Accountability (V1)
Report Implications:-
Legal: There are no implications arising from this report.
Financial: The implications are as set out at paragraphs 1 to 4 of this report.
Corporate Risk Decreasing Financial Resources / Increasing Financial Pressures (CR1) Management: Reputation Damage (CR4) Economy / Regeneration (CR9)
Equalities and Equalities There are no implications arising from this report. Assessment (EA): EA not applicable.
Human Rights: There are no implications arising from this report.
Health and Safety: There are no implications arising from this report.
Statutory Officers’ Comments:-
Head of Paid Service: The report is satisfactory. Chief Finance Officer: The report is satisfactory.
Monitoring Officer: The report is satisfactory.
Consultees: Senior Leadership Team and Heads of Service
Background Papers: Report entitled ‘2020/21 Budget & Medium-Term Financial Strategy (2021/22 – 2024/25)’ to Full Council 20 February 2020
Appendices: 1. Capital Programme (2020/21)
1. Introduction
1.1In February 2020, the Council approved a General Fund Budget for 2020/21 of £6.119m. This budget has been revised to £6.019m.
2. General Fund Position
2.1On a departmental basis, the Council is currently forecasting an overspend variance of £514k which is 9% of the overall budget. This forecast overspend is mainly due to an estimated £1.2million COVID-19 related costs and income loss. Currently the COVID-19 forecast comprises of £267k expenditure relating to Salary, Agency staff costs and various supplies and services costs. The forecast COVID-19 related income loss of £955k relates primarily to realigned Selective Licensing Income to 2021/22, the reported loss of income through the leisure closures and contractual agreements. Minor losses of income relate to the loss of car parking income and income from the closure of our community buildings.
2.2With respect to variances that are outside of the direct consequences and impacts of COVID-19 (although indirect impacts have been included in the following), there have been few significant variances. These variances include £35k additional costs for interim Finance Staffing, forecast additional homelessness costs of circa £40k, additional costs in ICT, HR and Procurement that were not included in the original budget of £85k (including Learning and Development, Procurement costs and additional hardware).The majority of these costs have been offset by savings in vacant posts and minor underspends across the council.
2.3A summary of the overall General Fund Budget and Forecast Outturn is outlined in the Table 1 at a service level. Table 2 outlines a summary of the General Fund Budget and COVID-19 monitoring.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Programme (2020/21)Appendix 1 | 150 KB | Download |
PDF |
Financial Outturn Report (Q1 2020/21)Report | 684 KB | DownloadRead as text |
Follow Policy, Finance & Development Committee at Oadby and Wigston and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Minutes of the Previous MeetingRESOLVED THAT: The minutes of the previous meeting held on 16 June 2026 be taken as read, confirmed and approved. | Approved | Open |
| 8 Sep 2026 | Budget Setting Approach 2027/28 and Medium Term Financial Plan UpdateRESOLVED THAT: The Budget Approach for 2027/28 be agreed and recommended to Council. | Agreed | Open |
| 8 Sep 2026 | Treasury Management Annual Report (2025/26)RESOLVED THAT: The content of the report and appendices be noted. | Noted | Open |
| 8 Sep 2026 | Budget Monitoring (Q1 2026/27)RESOLVED THAT: i) The contents of the Quarter 1 report and the Appendices be noted; ii) The carry forward of slippage... | Noted | Open |
| 8 Sep 2026 | Sundry Debtor & Revenues Write Offs (Q1 2026/27)RESOLVED THAT: The content of the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.