Resolved
RESOLVED THAT: (i) The contents of the report and appendix be noted; and (ii) The additional Capital Expenditure for 2021/22 be approved.
Policy, Finance & Development Committee noted this item on Tuesday 16 March 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT: (i) The contents of the report and appendix be noted; and (ii) The additional Capital Expenditure for 2021/22 be approved.
Policy, Finance and Matter for Tuesday, 16 March Development Information and 2021 Committee Decision
Report Title: Financial Outturn Report (Q3 2020/21)
Report Author(s): Comie Campbell (Head of Finance / Deputy Section 151 Officer)
Purpose of Report: This report gives a summary of the overall Council position for the financial year 2020/21 at the end of the third quarter for both Revenue and Capital Expenditure.
Report Summary: The Council has completed quarter three of the financial year 2020/21. There is a significant variation in the General Fund due to COVID-19 related additional expenditure and income losses.
A full 2020/21 Capital Programme is set out at in Appendix 1.
Recommendation(s): A. That the contents of the report and appendix be noted; B. That the additional Capital Expenditure for 2021/22 (as set out at paragraph 3 of the report) be approved.
Senior Leadership, Stephen Hinds (Deputy Chief Executive / Section 151 Officer) Head of Service, (0116) 257 2681 Manager, Officer and [email protected] Other Contact(s): Comie Campbell (Head of Finance / Deputy Section 151 Officer) (0116) 257 2713 [email protected]
Corporate Objectives: Providing Excellent Services (CO3)
Vision and Values: “A Stronger Borough Together” (Vision) Accountability (V1)
Report Implications:-
Legal: There are no implications arising from this report.
Financial: The implications are as set out at paragraphs 1 to 4 of this report.
Corporate Risk Decreasing Financial Resources / Increasing Financial Pressures (CR1) Management: Reputation Damage (CR4) Economy / Regeneration (CR9)
Equalities and Equalities There are no implications arising from this report. Assessment (EA): EA not applicable.
Human Rights: There are no implications arising from this report.
Health and Safety: There are no implications arising from this report.
Statutory Officers’ Comments:-
Head of Paid Service: The report is satisfactory. Chief Finance Officer: The report is satisfactory.
Monitoring Officer: The report is satisfactory.
Consultees: Senior Leadership Team and Heads of Service
Background Papers: Report entitled ‘2020/21 Budget & Medium-Term Financial Strategy (2021/22 - 2024/25)’ to Full Council 20 February 2020
Appendices: 1. Capital Programme (2020/21)
1. Introduction
1.1In February 2020, the Council approved a General Fund Budget for 2020/21 of £6.119m. This budget has been revised to £6.019m.
2. General Fund Position
2.1On a departmental basis, the Council is currently forecasting an overspend variance of £292k which is 4.8% of the overall budget. This forecast overspend is mainly due to an estimated £1.8m of COVID-19 related costs and income loss. Currently the COVID-19 forecast comprises of £510k expenditure relating to Salary, Agency staff costs and various supplies and services costs. The forecast COVID-19 related income loss of £1.2m relates primarily to realigned Selective Licensing Income to 2021/22, the reported loss of income through the leisure closures and contractual agreements. Minor losses of income relate to the loss of car parking income and income from the closure of our community buildings.
2.2With respect to variances that are outside of the direct consequences and impacts of COVID-19 (although indirect impacts have been included in the following), there have been few significant variances. These variances include £69k additional cost for interim finance staff, £91k investment income not achievable, additional £120k ICT &Telephony contract procurement costs that were not included in the original budget. These costs have been offset against savings in vacant posts and minor underspends across the council
2.3A summary of the overall General Fund Budget and Forecast Outturn is outlined in the Table 1 at a service level. Table 2 outlines a summary of the General Fund Budget and COVID-19 monitoring.
(Continued overleaf) Table 1 – General Fund Budget Monitoring
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Programme (Q3 2020/21)Appendix 1 | 43 KB | Download |
PDF |
Financial Outturn Report (Q3 2020/21)Report | 338 KB | DownloadRead as text |
Follow Policy, Finance & Development Committee at Oadby and Wigston and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Minutes of the Previous MeetingRESOLVED THAT: The minutes of the previous meeting held on 16 June 2026 be taken as read, confirmed and approved. | Approved | Open |
| 8 Sep 2026 | Budget Setting Approach 2027/28 and Medium Term Financial Plan UpdateRESOLVED THAT: The Budget Approach for 2027/28 be agreed and recommended to Council. | Agreed | Open |
| 8 Sep 2026 | Treasury Management Annual Report (2025/26)RESOLVED THAT: The content of the report and appendices be noted. | Noted | Open |
| 8 Sep 2026 | Budget Monitoring (Q1 2026/27)RESOLVED THAT: i) The contents of the Quarter 1 report and the Appendices be noted; ii) The carry forward of slippage... | Noted | Open |
| 8 Sep 2026 | Sundry Debtor & Revenues Write Offs (Q1 2026/27)RESOLVED THAT: The content of the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.