Housing Benefit Subsidy Audit 2023/24

Noted Finance 2 papers

AI summaryOldham Audit Committee notes the 2023/24 Housing Benefit Subsidy audit, which found several small overstatement errors in the council's claim to the DWP.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedMembers noted the outcome of the external audit of the 2023/24 subsidy claim
MoneySix errors, £30 to £2,990Individual overstatement amounts given in the report; no overall total stated
What happens nextPrepare for 2024/25 auditIdentified issues have been reviewed ahead of the next audit cycle
Who it affectsHousing Benefit Subsidy claimAffects the council's annual claim to the Department for Work and Pensions

What was decided

The committee noted the outcome of the 2023/24 Housing Benefit Subsidy claim audit carried out by external auditors. Report P6

Why

The Department for Work and Pensions requires councils to undergo an annual external review of their Housing Benefit Subsidy claim under its Housing Benefits Assurance Process. Report P2

KPMG LLP carried out the 2023/24 review and prepared the report for members. Report P2

What happens next

The issues identified in the 2023/24 audit have been reviewed in preparation for the 2024/25 audit process. Report P3

The money

  • £2,990 Overstatement from five cases of miscalculated claimant earnings, a mix of overpayments and underpayments Report P5
  • £99 Overstatement from one case of incorrectly assessed tariff income from capital Report P5
  • £2,755 Overstatement caused by a system issue creating incorrect overpayments on temporary and supported accommodation claims during Universal Credit migration, now resolved Report P5
  • £1,101 Overstatement from two cases where prior year overpayments were misclassified as eligible rather than technical overpayments Report P5
  • £30 Overpayment from two cases where the effective date of change to tariff income in HRA claims was applied incorrectly Report P5
  • £1,419 Impact of eight cases of miscalculated childcare costs, a mix of overpayments and underpayments Report P5

Implications

  • Financial: Six identified overstatements reduce the subsidy the council can claim from the DWP for 2023/24, with individual amounts ranging from £30 to £2,990. Report P5
  • Risk: Errors, including a system issue linked to Universal Credit migration, must be resolved before the 2024/25 audit to avoid further qualification of the claim. Report P3, P5

Who and where

  • The council's Housing Benefit Subsidy claim for 2023/24, paid by the DWP Report P2, P5
  • Housing Benefit claimants whose earnings, tariff income, accommodation, or childcare costs were calculated incorrectly Report P5

Timeline

  • 2023/24: Financial year covered by the audited Housing Benefit Subsidy claim Report P1, P2

Plain English for the jargon

  • DWP: Department for Work and Pensions, the government department that reimburses councils for housing benefit paid
  • Housing Benefits Assurance Process: The DWP's annual process requiring councils to have their housing benefit subsidy claim independently reviewed
  • Housing Benefit Subsidy: Money the council reclaims from central government for housing benefit it has paid to claimants
  • Universal Credit migration: The transfer of claimants from Housing Benefit to Universal Credit, which contributed to a system issue in the period covered
  • Tariff income: An assumed income applied to claimants based on their capital, used in benefit calculations
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

That the submitted report detailing the outcome of the 2023/24 audit of the Housing Benefit Subsidy claim form, be noted.
Word for word from the decision Oldham published for this meeting. Source: committees.oldham.gov.uk

Follow this further

Built from Oldham's papers

What the report saysPro

Report to Audit Committee

Reason for decision

This report outlines for Members the outcome of the external audit of the Housing Benefit Subsidy claim for the financial year 2023/24..

Executive summary

In accordance with the DWP’s Housing Benefits Assurance Process, the Council is required to undergo an annual review of its Housing Benefit Subsidy claim. This review was conducted by external auditors, KPMG LLP. Appendix 1 includes a report prepared by the KPMG LLP officer who led the audit process..

Overall, the report is reasonably positive but highlights several issues that have been reviewed in preparation for the 2024/25 audit process

The findings are as follows:

 There were five cases where the claimant’s earnings had been miscalculated. This resulted in a mix of underpayments and overpayments, affecting the subsidy claim by an overstatement of £2,990  There were five cases where tariff income from capital was assessed incorrectly. Only one case resulted in an overpayment, affecting the subsidy claim by an overstatement of £99  A system issue caused some temporary and supported accommodation claims to have overpayments incorrectly created. This was due to the Universal Credit migration and has now been resolved. It affected the subsidy claim by an overstatement of £2,755.  Two cases involved prior year overpayments being misclassified as eligible rather than technical overpayments. This affected the subsidy claim by £1,101.  In two cases, the effective date of change to tariff income in HRA claims was applied incorrectly, resulting in an overpayment of £30..  Eight cases involved miscalculated childcare costs, resulting in both overpayments and underpayments, and affecting the subsidy claim by £1,419.  One observation noted a service charge being incorrectly included in a rent calculation. As no benefit was paid, there was no impact on the subsidy claim.

Recommendation

That Members of the Audit Committee note the outcome of the 2023/24 audit of the Housing Benefit Subsidy claim form.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
OMBC: Housing Benefit Subsidy Claim 2023-24Appendix 1 133 KB Download
PDF
Housing Benefit Subsidy Audit 2023/24Report 139 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 19 attended
SA
Sam Al-HamdaniCommittee Member, present
NA
Naseem AslamCommittee Member, apologies, sent representative
ZC
Zahid Chauhan OBECommittee Member, apologies, sent representative
NC
Naveed ChowhanCommittee Member, absent
AC
Angela CosgroveSubstitute, present as substitute
PD
Peter DavisSubstitute, present as substitute
VG
Victoria GallacherOfficer, expected
KG
Kamran GhafoorCommittee Member, present
FG
Fiona GreenwayOfficer, expected
JM
John MillerOfficer, expected
MK
Mark KenyonSubstitute, present as substitute
AM
Abdul MalikCommittee Member, absent

All 19 on the meeting page

On this subject at Oldham

Search all
  1. Housing Benefit Subsidy Audit 2023/24This decision
  2. Housing Benefit Subsidy Audit 2022/23Noted
  3. Audit of Housing Benefit SubsidyNoted
  4. Audit of Housing Benefit Subsidy 2020/21Noted
  5. Audit of Housing Benefit Subsidy 2019-20Noted
  6. Audit of Housing Benefit Subsidy 2018/19Noted

More from Oldham Audit Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 MinutesThat the of the meeting of the Audit Committee, held 26 th Manch 2026, be approved as a correct and the accompanying ... Approved Open
22 Jul 2026 Members' Allowances UpdateThat the Audit Committee notes ... view the full minutes text for item 6. Decided Open
22 Jul 2026 Audit Strategy MemorandumThat the report be noted. Noted Open
22 Jul 2026 Draft 2025/26 Annual Statement of AccountsThat the Council’s draft Statement of Accounts for 2025/26, be noted. Noted Open
22 Jul 2026 Treasury Management Review 2025/26That the Audit Committee notes and endorses the Treasury Management Outturn report and the Treasury Management activi... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies