CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Oldham Metropolitan Borough Council

Princes Gate – Development Update (St Mary’s)

Approved Scrutiny 1 paper

AI summaryOldham Place Scrutiny Board backs Princes Gate deal, endorsing grant agreements to allow 331 new town centre homes to be built, with 75 at social rent in Phase 1.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedBoard endorses scheme and funding agreements
MoneyNot stated in Part AFigures contained in exempt Part B report
What happens nextSign grant funding agreementsStart on site at earliest opportunity
Who it affectsFuture residents and town centre331 new homes including 75 social rent

What was decided

The Board endorsed the Princes Gate development update and approved the Council entering the Grant Funding Agreements and other necessary agreements to allow the development of 331 new homes to commence on site. Report P1

Delegated authority was granted to the Deputy Chief Executive (Place), in consultation with named cabinet members and directors, to agree final terms and enter into the three grant funding agreements. Report P2

The report was noted as exempt from call-in under Rule 14 of the Overview and Scrutiny Procedure Rules. Report P2

Why

Princes Gate was selected as the preferred site to commence new homes delivery in the town centre, with detailed planning consent already in place. Report 2.1, 2.4

Provisional GMCA grant funding and an offer of GMCA patient capital equity, alongside MHCLG grant already secured, mean the scheme can now proceed. Report 2.1

Using Right to Buy capital receipts to support the affordable housing contribution will allow the 75 Phase 1 homes to be let at Social Rent rather than Affordable Rent. Report 2.3

What happens next

Enter into a Grant Funding agreement with Muse for the Community Regeneration Partnership grant and a further agreement for the Council match funding contribution. Report P2, 2.2

Enter into a Grant Funding agreement with Legal and General Affordable Homes for the Council affordable housing contribution, so the new homes are let at social rent. Report P2, 2.2

Complete a Deed of Variation to the Master Development Agreement (done in March 2026) and progress to phased drawdown and start on site. Report 1.5, P2

Options considered

  • Chosen: Enter into the Grant Funding Agreements (preferred option). Allows Muse to deliver 331 new homes as the first phase of town centre residential development under the Creating a Better Place Regeneration Programme. Report 3.2, P22
  • Rejected: Do not enter into the Grant Funding Agreements. Scheme would remain unviable, Muse could not deliver, and secured GMCA grant could be reallocated outside the borough, causing reputational damage. Report 3.1
  • Rejected: Do not contribute towards the socially rented homes. The 75 new homes in Phase 1 would be let only at Affordable Rent levels rather than Social Rent. Report P19

Implications

  • Financial: Financial implications are contained in the exempt Part B report and not set out in this paper. Report 6.1
  • Legal: Legal implications are contained in the exempt Part B report; the Director of Legal Services is authorised to sign, seal or formalise required documentation. Report 7.1, P2
  • Risk: Not drawing down the secured GMCA grant could damage the Council's reputation and see funding reallocated outside the borough. Report 3.1
  • Other: Right to Buy capital receipts, which must be spent on further affordable housing or are taken by the Treasury, are proposed to fund the additional affordable housing contribution. Report 2.3

Who and where

  • Future residents of the 331 new homes at Princes Gate, including 75 households to be let at Social Rent in Phase 1 Report 2.4, 2.3
  • The town centre of Oldham, through mixed-use ground floor spaces intended to support surrounding activity Report 2.4
  • Muse, as the Council's strategic delivery partner, and Legal and General Affordable Homes as residential delivery partner Report 1.3, 2.5

Timeline

  • September 2023: Master Development Agreement entered into between the Council and Muse Report 1.3
  • November 2024: Town Centre Development Framework endorsed by Cabinet Report 1.3
  • January 2025: Cabinet approval to formally include Princes Gate in the MDA as a Core site Report 1.5
  • 24 March 2025: Cabinet approval to accept Community Regeneration Partnership Grant funding from MHCLG Report 1.1
  • 2 July 2025: Planning approval granted for the Town Centre Development Framework including Princes Gate Report 1.3
  • March 2026: Deed of Variation to the MDA completed to include Princes Gate Report 1.5
  • 19 March 2026: Place, Economic Growth and Environment Scrutiny Board considered the report Report P2
  • October 2026: Viability gap grant funding application submitted to the GM Good Growth Fund Report 2.1
  • December 2026: Provisional award of GMCA grant funding and offer of GMCA patient capital equity received Report 2.1

Plain English for the jargon

  • MHCLG: The government department that awarded the Community Regeneration Partnership grant to Oldham.
  • GMCA: Greater Manchester Combined Authority, source of the provisional grant and patient capital equity offer.
  • MDA: Master Development Agreement between the Council and Muse, with Princes Gate added by a Deed of Variation in March 2026.
  • Social Rent: A lower rental level than Affordable Rent, proposed for the 75 Phase 1 homes using Right to Buy receipts.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

RESOLVED that the Place, Economic Growth and Environment Scrutiny Board endorses the Princes Gate development update and approval of the Council entering the Grant Funding Agreements and completions of other necessary agreements to allow the development of 331 new homes at Princes Gate to commence on site.
Word for word from the decision Oldham published for this meeting. Source: committees.oldham.gov.uk

Follow this further

Built from Oldham's papers

What the report saysPro

Report to Place, Economic Growth and Environment Scrutiny Board

Reason for decision

To provide an update on overall scheme progress and to obtain approval for the Council to enter into the necessary Grant Funding Agreements and to complete all other necessary agreements/documentation to allow the development of 331 new homes at Princes Gate to commence on site.

Recommendations

 To grant delegated authority to the Deputy Chief Executive (Place) in consultation with the Cabinet Member for Building a Better Place Oldham, the Director of Finance and the Borough Solicitor and Monitoring officer to agree final terms and to enter into a Grant Funding agreement with Muse in respect of the Community Regeneration Partnership grant funding as outlined in the Part B report  To grant delegated authority to the Deputy Chief Executive (Place) in consultation with the Cabinet Member for Building a Better Place Oldham, the Director of Finance and the Borough Solicitor and Monitoring officer to agree final terms and to enter into a Grant Funding agreement with Muse in respect of the proposed Council match funding contribution as set out in the Part B report  To grant delegated authority to the Deputy Chief Executive (Place) in consultation with the Cabinet Member for Building a Better Oldham, the Director of Finance and the Borough Solicitor and Monitoring officer to agree final terms and to enter into a Grant Funding agreement with Legal and General Affordable Homes in respect of the Council affordable housing contribution (if required) and as set out in the Part B report, which will ensure that the new homes are let at a social rent level.  To grant delegated authority to the Deputy Chief Executive (Place) in consultation with the Cabinet Member for Building a Better Oldham, the Director of Finance and the Director of Legal Services and Monitoring officer to enter into any associated documentation or agreements that may be required in connection with the above matters and to enable a phased drawdown of the site, which will result in a start on site at the earliest opportunity.  To grant delegated authority to the Director of Legal Services or his/her nominees to formalise any necessary legal requirements including signing and/or sealing any documentation required to give effect to the recommendations and/or delegations in this report.  To note that following consideration by the Place, Economic Growth and Environment Scrutiny Board on 19th March 2026 the report is exempt from call-in, under Rule 14 of the Overview and Scrutiny Procedure Rules in the Constitution.

2 Cabinet March 2026

Princes Gate Development Update

Background

1.1By virtue of a previous Cabinet Report considered on the 24th March 2025, Council approval was obtained to accept a Community Regeneration Partnership Grant funding offer from MHCLG.

1.2Delegated authority was granted to the Deputy Chief Executive (Place) in consultation with the Cabinet Member for Building a Better Oldham, the Director of Finance and the Borough Solicitor and Monitoring officer to oversee and approve: the expenditure of grant funding for the selected projects, the onward award of grant and any associated partnership or programme activity. The policy intervention list for Grant Award Projects, identified by MHCLG for Oldham, covered seven areas of activity, which included Town Centre Housing Delivery. This consisted of a specific capital contribution to accelerate development and to support delivery of the four key Town Centre housing sites, including the Civic Centre, former Magistrates Court site, former Leisure Centre site, and Princes Gate.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Princes Gate: Development Update (St Mary’s)Report 275 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 23 attended
NA
Naseem AslamCommittee Member, apologies
EB
Emma BartonOfficer, expected
AB
Alex BougatefOfficer, in attendance
GB
Georgina BrownridgeOfficer, in attendance
MB
Matthew BulmerOfficer, in attendance
BC
Bryn CookeOfficer, in attendance
ND
Nasir DadOfficer, expected
JG
Jenny GeeSecretary, expected
KG
Kamran GhafoorCommittee Member, absent
MG
Matthew GrattonOfficer, expected
GH
Garth HarknessCommittee Member, present
JH
Junaid HussainChair, present

All 23 on the meeting page

On this subject at Oldham

Search all
  1. Princes Gate – Development Update (St Mary’s)This decision
  2. Princes Gate – Development Update (St Mary’s)Decided
  3. Inclusion of Oldham Mumps, Princes Gate into the Town Centre Development PartnershipDecided
  4. Acceptance of Brownfield Infrastructure and Land Funding Grant for Oldham Mumps, Princes GateAgreed

More from Oldham Place, Economic Growth and Environment Scrutiny Board

All decisions
MeetingDecisionOutcome
19 Mar 2026 Biodiversity Duty ReportRESOLVED that the Place, Economic Growth and Environment Scrutiny Board endorses the Biodiversity Duty Report publica... Decided Open
19 Mar 2026 Proposal to Undertake Statutory Consultation on the Establishment of an Oldham Mayoral Development CorporationRESOLVED that the Place, Economic Growth and Environment Scrutiny Board endorses the Proposal to undertake Statutory ... Decided Open
19 Mar 2026 Work ProgrammeRESOLVED that the Place, Economic Growth and Environment Scrutiny Board’s for 2025/26 be noted. Noted Open
19 Mar 2026 Key Decision DocumentRESOLVED that the report be noted. Noted Open
19 Mar 2026 Rule 13 and 14RESOLVED that the Rule 14 decisions be noted Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies