CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Oldham Metropolitan Borough Council
Cabinet, Monday 23 March 2026 at 6.00pm

Princes Gate – Development Update (St Mary’s)

Decided Executive 1 paper

AI summaryCabinet defers confidential Princes Gate funding decisions to agenda item 35; 331-home town centre development update noted, with grant agreements to be considered separately.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDeferredConfidential Part B recommendations to be considered later
MoneyNot stated
What happens nextAgenda item 35 of this meetingCabinet to consider Part B recommendations
Who it affectsPrinces Gate housing scheme331 new homes at Oldham town centre

What was decided

Cabinet agreed to consider the confidential Part B recommendations on the Princes Gate development at agenda item 35, rather than deciding on the open report's recommendations immediately.

Why

Financial and legal details for the proposed grant funding agreements with Muse and Legal and General Affordable Homes are contained in the exempt Part B Report and are not disclosed in the open papers, so the Cabinet is considering those elements separately. Report 6.1, 7.1

What happens next

The Cabinet will return to the Princes Gate item at agenda item 35 of the same meeting to consider the Part B recommendations.

Subject to that consideration, delegated authority is proposed for the Deputy Chief Executive (Place), in consultation with named cabinet members and officers, to enter into grant funding agreements with Muse and with Legal and General Affordable Homes. Report P2

The Place, Economic Growth and Environment Scrutiny Board considered the report on 19 March 2026, and the report is exempt from call-in under Rule 14 of the Overview and Scrutiny Procedure Rules. Report P2

Options considered

  • Chosen: Enter into the grant funding agreements with Muse and Legal and General Affordable Homes as set out in the report. Preferred option: enables Muse to deliver 331 new homes at Princes Gate as the first phase of town centre residential development under the Creating a Better Place Regeneration Programme Report 3.2, P22
  • Rejected: Do not enter into the grant funding agreements. The scheme would remain unviable, Muse would not be able to deliver it, the Council would face reputational damage, and the already secured GMCA grant would likely be reallocated outside the borough Report 3.1, P19

Implications

  • Financial: Financial implications, including the proposed Council match funding contribution and the affordable housing contribution to Legal and General Affordable Homes, are contained in the Part B Report and not disclosed in the open papers. Report 6.1, P2
  • Legal: Legal implications are contained within the Part B Report and are not disclosed in the open papers; delegated authority is proposed for the Director of Legal Services to sign and seal required documentation. Report 7.1, P2
  • Risk: If the grant funding agreements are not entered into, the already secured GMCA grant funding could be reallocated outside the borough, causing reputational damage to the Council. Report 3.1
  • Equalities: The report states there is no equality impact, including implications for children and young people. Report 9.1
  • Other: No immediate procurement implications identified; the procurement team will continue to provide support to the development programme when required. Report 8.1, P28

Who and where

  • Muse, the Council's long-term Strategic Delivery Partner for the town centre Report 1.3, 1.5
  • Legal and General Affordable Homes, the proposed residential delivery partner for Phase 1 Report P2, 2.5
  • Future residents of the 331 new homes at Princes Gate, including 75 homes in Phase 1 to be let at social rent Report P1, 2.3, 2.4
  • Households on Oldham's housing waiting list who may be offered the social rent homes Report 2.3, 2.4
  • A local contractor appointed for the enabling works package, set to commence shortly Report 2.5

Timeline

  • September 2023: Master Development Agreement between the Council and Muse entered into Report 1.3
  • January 2025: Cabinet approved formal inclusion of the Princes Gate site into the MDA with Muse as a Core site Report 1.5
  • 24 March 2025: Cabinet approved acceptance of the MHCLG Community Regeneration Partnership grant funding offer Report 1.1
  • 2 July 2025: Planning approval granted for the Development Framework and detailed consent for 331 new homes at Princes Gate Report 1.3, 1.4
  • March 2026: Deed of Variation to the MDA completed to formally include Princes Gate as a Core site Report 1.5
  • 19 March 2026: Place, Economic Growth and Environment Scrutiny Board considered the report Report P2
  • October 2026: Application for viability gap grant submitted to the GM Good Growth Fund Report 2.1
  • December 2026: Provisional GMCA grant funding award approved, plus offer of GMCA patient capital equity Report 2.1

Plain English for the jargon

  • MDA: Master Development Agreement, the long-term Strategic Delivery Partnership between the Council and Muse for town centre development
  • CRP: Community Regeneration Partnership, the MHCLG grant programme covering seven areas of activity including Town Centre Housing Delivery
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26

Resolved

That the Cabinet will consider the confidential recommendations, detailed in the report, at agenda item 35.
Word for word from the decision Oldham published for this meeting. Source: committees.oldham.gov.uk

Follow this further

Built from Oldham's papers

What the report saysPro

Report to Cabinet

Reason for decision

To provide an update on overall scheme progress and to obtain approval for the Council to enter into the necessary Grant Funding Agreements and to complete all other necessary agreements/documentation to allow the development of 331 new homes at Princes Gate to commence on site.

Recommendations

 To grant delegated authority to the Deputy Chief Executive (Place) in consultation with the Cabinet Member for Building a Better Place Oldham, the Director of Finance and the Borough Solicitor and Monitoring officer to agree final terms and to enter into a Grant Funding agreement with Muse in respect of the Community Regeneration Partnership grant funding as outlined in the Part B report  To grant delegated authority to the Deputy Chief Executive (Place) in consultation with the Cabinet Member for Building a Better Place Oldham, the Director of Finance and the Borough Solicitor and Monitoring officer to agree final terms and to enter into a Grant Funding agreement with Muse in respect of the proposed Council match funding contribution as set out in the Part B report  To grant delegated authority to the Deputy Chief Executive (Place) in consultation with the Cabinet Member for Building a Better Oldham, the Director of Finance and the Borough Solicitor and Monitoring officer to agree final terms and to enter into a Grant Funding agreement with Legal and General Affordable Homes in respect of the Council affordable housing contribution (if required) and as set out in the Part B report, which will ensure that the new homes are let at a social rent level.  To grant delegated authority to the Deputy Chief Executive (Place) in consultation with the Cabinet Member for Building a Better Oldham, the Director of Finance and the Director of Legal Services and Monitoring officer to enter into any associated documentation or agreements that may be required in connection with the above matters and to enable a phased drawdown of the site, which will result in a start on site at the earliest opportunity.  To grant delegated authority to the Director of Legal Services or his/her nominees to formalise any necessary legal requirements including signing and/or sealing any documentation required to give effect to the recommendations and/or delegations in this report.  To note that following consideration by the Place, Economic Growth and Environment Scrutiny Board on 19th March 2026 the report is exempt from call-in, under Rule 14 of the Overview and Scrutiny Procedure Rules in the Constitution.

2 Cabinet March 2026

Princes Gate Development Update

Background

1.1By virtue of a previous Cabinet Report considered on the 24th March 2025, Council approval was obtained to accept a Community Regeneration Partnership Grant funding offer from MHCLG.

1.2Delegated authority was granted to the Deputy Chief Executive (Place) in consultation with the Cabinet Member for Building a Better Oldham, the Director of Finance and the Borough Solicitor and Monitoring officer to oversee and approve: the expenditure of grant funding for the selected projects, the onward award of grant and any associated partnership or programme activity. The policy intervention list for Grant Award Projects, identified by MHCLG for Oldham, covered seven areas of activity, which included Town Centre Housing Delivery. This consisted of a specific capital contribution to accelerate development and to support delivery of the four key Town Centre housing sites, including the Civic Centre, former Magistrates Court site, former Leisure Centre site, and Princes Gate.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Princes Gate: Development Update (St Mary’s)Report 275 KB DownloadRead as text

At this meeting

Whole meeting
5MinutesApproved 6Adult Social Care CQC Assessment OutcomeNoted 7Extension to the Adult Social Care Service Level Agreement with Miocare Group CIC 2026Approved 8Proposal to update Smokefree policyDecided 9Extension of the Current Commissioning Arrangements for Care at HomeApproved 10Approval to Tender the Domestic Property Disability Adaptions FrameworkApproved 11Procurement of a Crisis Payment ProviderAgreed 12Crisis and Resilience Fund – Utilisation of Grant AllocationAgreed 13Arts Council - Development Extension GrantApproved 14Bikeability Core and Bikeability Plus delivery 2026 - 2029Approved 15Grant Acceptance: City Region Sustainable Transport Settlement (CRSTS) - Revenue FundingApproved 16Staying Close Leaving Care OfferApproved 17Greater Manchester’s Integrated Settlement for Education, Work and SkillsAgreed 18Special Education Needs (SEN) Travel Assistance Service – Contract ExtensionDecided 19High Needs Provision in Mainstream Settings Capital WorkApproved 20Capital Works (Kingsland)Approved 21Proposal to Undertake Statutory Consultation on the Establishment of an Oldham Mayoral Development CorporationApproved 22Housing Allocations Scheme 2026Approved 23Infrastructure Funding Statement 2024/25Approved 24Oldham's Monitoring Report 2024/25Approved 25Biodiversity Duty ReportApproved
26Princes Gate – Development Update (St Mary’s)This decision
27Sale of Land at Rosary Road, Fitton Hill (Medlock Vale)Decided 28Economic Development and Regeneration Flexible Grant AcceptanceDecided 29Revenue Monitor and Capital Investment Programme 2025/26 - Month 10Approved 30Local Taxation Discretionary Policies 2026/27Approved 31Greater Manchester Empty Homes and Leasing Programme - Acceptance of FundingApproved 32Local Authority Housing Fund (LAHF) - Acceptance of FundingApproved 33Acceptance of 2026/27 GMCA Community Safety Partnership, Voluntary and Community Sector, Hate Crime, GM Violence Reduction and Cohesion GrantsApproved 34Exclusion of the Press and PublicOn the agenda 35Princes Gate – Development Update (St Mary’s) PART BPrivate 36Sale of Land at Rosary Road, Fitton Hill (Medlock Vale)Private 37Economic Development and Regeneration Flexible Grant AcceptancePrivate 38Upgrade of E3 to E5 Licences for remaining user basePrivate 39CAF CompliancePrivate 40Telephony Contract RenewalPrivate 41Cyber - Server ProtectionPrivate 42Oldham Council MFD Print SolutionPrivate 43Security Operations CentrePrivate 44ZTNA – Zero Trust Network AccessPrivate

Who was there

7 of 30 attended
MA
Mohon AliCommittee Member, present
JB
Jack BaileyOfficer, expected
MB
Mike BarkerOfficer, expected
MB
Mike BarkerOfficer, expected
EB
Emma BartonOfficer, expected
AB
Alex BougatefOfficer, expected
BB
Barbara BrownridgeCommittee Member, present
MB
Matthew BulmerOfficer, expected
NC
Neil ConsterdineOfficer, expected
ND
Nasir DadOfficer, expected
JD
Julie DanielsOfficer, expected
PD
Peter DeanCommittee Member, apologies

All 30 on the meeting page

On this subject at Oldham

Search all
  1. Princes Gate – Development Update (St Mary’s)This decision
  2. Princes Gate – Development Update (St Mary’s)Approved
  3. Inclusion of Oldham Mumps, Princes Gate into the Town Centre Development PartnershipDecided
  4. Acceptance of Brownfield Infrastructure and Land Funding Grant for Oldham Mumps, Princes GateAgreed

More from Oldham Cabinet

All decisions
MeetingDecisionOutcome
23 Mar 2026 MinutesThat the minutes of the meeting of the Cabinet held on 23 rd February 2026, be approved as a correct record. Approved Open
23 Mar 2026 Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe... Noted Open
23 Mar 2026 Extension to the Adult Social Care Service Level Agreement with Miocare Group CIC 2026That the Cabinet: 1. Approves the Service Level Agreement with Miocare Group CIC. 2. Approves the refreshed Service L... Approved Open
23 Mar 2026 Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ... Decided Open
23 Mar 2026 Extension of the Current Commissioning Arrangements for Care at HomeThat the Cabinet approves a three-month extension of the current contracts for Care at Home, Extra Care and Night Pro... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies