Resolved to approve the application subject to the following conditions:- 1 Development begun within time limit 2 Develop in accordance with approved plans 3 Samples in Conservation Area ;Central , 4 Landscape hard surface design - tree roots 5 Landscape underground services - tree roots 6 Tree Protection Plan ( TPP ) 1 7 Arboricultural Method Statement ( AMS ) 1 8 Archaeology 9 Mechanical plant 10 Construction Travel Plan 11 Drainage details 12 Cycle parking details required 13 Gates - opening/closing hours 14 Details of gates 15 Cleaning regime The Committee imposed further conditions requiring additional cycle parking to be provided and a Construction Management Plan be submitted. It also suggested an informative be added that the applicant investigate increasing the energy efficiency of the building, for example by installing as many photovoltaic panels as possible.
Word for word from the decision Oxford published for this meeting.Source: mycouncil.oxford.gov.uk
Committee is recommended to support the proposal but defer the application in order to allow completion of a Unilateral Undertaking and to delegate to Officers the issuing of the notice of permission subject to conditions on its completion.
Reasons for approval:
1 Officers conclude that the proposal accord with all the relevant polices within the Oxford Core Strategy 2026, the Oxford Local Plan 2001-2016 and the West End Area Action Plan 2007-2016 and therefore recommends approval as the proposal is considered to positively enhance the role of the City centre as the principal retailing centre of Oxford. It will increases the prominence of the entrance in views from New Inn Hall Street, improve the shopping experience and improve the quality of the public realm. Changes in the roofscape will be seen in the context of the existing equipment on the roof of the Clarendon Centre and include use of solar PV panels which achieves 10% on-site renewables.
2 Officers have considered carefully all objections to these proposals. Officers have come to the view, for the detailed reasons set out in the officers report, that the objections do not amount, individually or cumulatively, to a reason for refusal and that all the issues that have been raised have been adequately addressed and the relevant bodies consulted.
63 3 The Council considers that the proposal accords with the policies of the development plan as summarised below. It has taken into consideration all other material matters, including matters raised in response to consultation and publicity. Any material harm that the development would otherwise give rise to can be offset by the conditions imposed.
4 The Council considers that the proposal, subject to the conditions imposed, would accord with the special character and appearance of the conservation area. It has taken into consideration all other material matters, including matters raised in response to consultation and publicity.
Conditions:
1 Development begun within time limit 2 Develop in accordance with approved plns 3 Samples in Conservation Area Central, 4 Landscape hard surface design - tree roots 5 Landscape underground services - tree roots 6 Tree Protection Plan (TPP) 1 7 Arboricultural Method Statement (AMS) 1 8 Archaeology 9 Mechanical plant 10 Construction Travel Plan 11 Drainage details 12 Cycle parking details required 13 Gates - opening/closing hours 14 Details of gates 15 Cleaning regime
Legal Agreement:
Financial contributions of £182,322 towards infrastructure works to serve the Oxford West End area are sought.
Main Local Plan Policies:
Oxford Local Plan 2001-2016
CP1 - Development Proposals CP6 - Efficient Use of Land & Density CP8 - Design Development to Relate to its Context CP9 - Creating Successful New Places CP10 - Siting Development to Meet Functional Needs CP13 - Accessibility CP21 - Noise NE16 - Protected Trees NE21 - Species Protection NE22 - Independent Assessment HE2 - Archaeology HE3 - Listed Buildings and Their Setting
64 HE7 - Conservation Areas HE9 - High Building Areas HE10 - View Cones of Oxford RC3 - Primary Shopping Frontage
Core Strategy
CS1_ - Hierarchy of centres CS5_ - West End CS9_ - Energy and natural resources CS12_ - Biodiversity CS18_ - Urb design, town character, historic env CS19_ - Community safety CS31_ - Retail
West End Area Action Plan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.