City Executive Board (became Cabinet, Monday 13 May 2019 at 5.00pm

Electrical Materials - Award of Contract

Decided Executive 1 paper

City Executive Board (became Cabinet decided this item on Monday 13 May 2019. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

Resolved to appoint a supplier for the provision of electrical materials and to award a contract for the supply of such materials for the period 1 August 2012 – 31 December 2015 to Eyre and Elliston Ltd.
Word for word from the decision Oxford published for this meeting. Source: mycouncil.oxford.gov.uk

Follow this further

Built from Oxford's papers

What the report saysPro

Report to City Executive Board (became Cabinet

Summary

1.1This report sets out the procurement route that has been taken to put in place a new contract to provide the Council with improved value for money from purchasing electrical materials. The proposed contract award complies with the EU Procurement Regulations 2006.

Background

135 2.1 The Council currently has a contract for the supply of electrical materials with Wilts Electrical Ltd. Wilts Electrical Ltd supply materials from their local depot and, where appropriate, hold stock to assist with the reduction in any time lag in repairs being carried out due to their stockholding arrangement.

2.2The current contract with Wilts Electrical Ltd will cease at the end of July 2012.

2.3The Council spends approximately £365,000 a year on electrical materials.

3. Tender Process

3.1A number of different tender routes are available to the Council to replace the current contract. Wilts Electrical Ltd was appointed as a result of the Council carrying out its own tender in 2008.

3.2The Council is a member of a consortium called Procurement for Housing (PfH). PfH is able to offer access to an EU compliant framework contract which negates the need for a full EU tender being carried out by the Council. The framework is also able to offer preferential pricing through the leverage obtained through purchasing via a larger contract.

3.3The Council used a similar PfH framework to appoint the supplier of building material supplies in 2011.The resulting contract has provided new savings and was more cost efficient in staff resources needed to put the contract in place.

3.4The tender evaluation criteria used to appoint Eyre and Elliston via the framework is in accordance with the Council’s Procurement Strategy of 40 % quality and 60 % price.

3.5The tender evaluation panel consisted of the electrical materials category buyer for PfH, Direct Services, and a member of the Procurement Team.

3.6As a result of completing the evaluation the panel concluded that Eyre and Elliston provided the Council with the best commercial offer based on our requirements.

4. Savings

4.1Overall, the contract will represent an average increase of 6% against the Wilts Electrical Ltd pricing in June 2011. The Electrical materials market has in the last year seen price changes from -76.77% to +54.95%.

136 4.1 Direct Services had budgeted for a likely increase of around 6%. This price increase expectation was based on soft market testing and benchmarking. In addition the Department for Business Innovation and Skills’ latest report advise that the electrical material price index have risen by an average of 7.8% in the last year – based on a basket of commonly bought goods.

4.2Based on this analysis, this contract will deliver a price increase lower than expected

4.3The electrical materials market is volatile and the fixed pricing offered in this contract will provide the Council with the stability of known pricing, enabling work for the next year to be planned based in the knowledge of having fixed pricing.

4.5The contract will offer fixed prices on all materials, apart from cable for 12 months. Cabling will be reviewed on a four monthly basis as it is not possible to fix this pricing for longer periods.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Electrical Materials: Award of ContractReport 99 KB DownloadRead as text

More from Oxford City Executive Board (became Cabinet

All decisions
MeetingDecisionOutcome
13 May 2019 Public QuestionsResolved to note the questions and answers provided. Noted Open
13 May 2019 Scrutiny Committee ReportsResolved to thank the Scrutiny Committees and the Scrutiny Panel for their useful input and to accept the recommendat... Agreed Open
13 May 2019 Scrutiny Committee ReportsIt was agreed that the Action Plan could be presented to the Housing Scrutiny Panel for review and monitoring. (4) Pr... Agreed Open
13 May 2019 Scrutiny Committee ReportsResolved to thank the Committee for its input and accept the recommendations in the report. Decided Open