Agenda Item 8
To: Audit and Governance Committee City Executive Board
Date: 29th June 2012 4th July 2012
Report of: Head of Finance
Title of Report: RISK MANAGEMENT QUARTERLY REPORTING: QUARTER 4 2011/2012
Summary and Recommendations
Purpose of report: To update members on both corporate and service risks as at the end of quarter 4, 31st March 2012.
Key decision No
Executive lead member:
Policy Framework: Improving value for money and service performance
Recommendation(s):
Members are requested to note the contents of the report
Appendix A Corporate Risk Register Appendix B Service Risk Register – Red Risks
Risk Management Strategy 1) The Risk Management Strategy was approved at the City Executive Board on 23rd April 2012 with the stated aims of:
• fully embedding Risk Management into the culture, processes and procedures of the Council, so that threats and opportunities are proactively managed thereby strengthening the Council’s ability to deliver its objectives and strategic priorities. • providing a clear and consistent approach to the management of risk across the organisation and through organisational boundaries.
109 2) A copy of the updated Strategy can be found on the intranet:
http://occweb/intranet/riskmanagementstrategy.cfm
Risk Identification 3) Corporate Risks – The Corporate Risk Register (CRR) is reviewed by the Corporate Management Team (CMT) on a quarterly basis, any new risks are incorporated into a revised version of the CRR. Risk owners for corporate risks are generally held at Director level.
4) Service Risks – Service area risks are reviewed periodically by Heads of Service and Service Managers. The Risk Manager will have oversight of all risks and on a quarterly basis will review service risks to determine the need for inclusion in the Corporate Risk Register.
5) Project and Programme Risk – The Council adopts the principles of Prince2 methodology for managing projects. Incorporated within this methodology is a robust process for the management of risk within a project environment. Programme/project risk registers, including risk registers for Procurement Projects, are created for each new project and are reviewed as part of the project life cycle. These are documented on the Project/Programme Risk Register (PRR).
Quarter 4 Corporate Risk Register 6) A review of the Corporate Risks at the end of quarter 4 compared to Quarter 3 has shown no change to the net risk, this is shown in the table below:
Current Risk Q3 Q4 Red 2 2 Amber 1 1 Green 2 2 Closed 0 0 Total risks 5 5
7) The current Corporate Risk Register (Appendix A) shows two red risks, these are : • Health & Safety - Existence of operational risks (relating to internal as well as public concerns – property not vehicle) • Impact on Homelessness of changes in Housing Benefit - Changes in housing benefit and universal housing benefit increase homelessness
8) These were both red risks in Q3, and continued progress has been made on mitigating actions throughout Q4, but this has not led to a reduction of the risk rating.
110 Quarter 4 Service Risk Register 9) A review of Service risks at the end of Quarter 4 compared to Quarter 3 has shown an overall reduction in the net risk position in the service areas.
Current Risk Q3 Q4 Red 9 6 Amber 49 32 Green 46 35 Total risks 104 73 Closed 15 26
10) There has been a reduction in Red risks in Quarter 4, and a number of risks have been closed completely. Those risks still remaining at red are shown in Appendix B. All of these risks are continuing to be managed and mitigating actions being monitored.
Financial Implications 11) There are no financial implications directly relevant to this report.
Legal Implications 12) There are no legal implications directly relevant to this report.
Name and contact details of author:- Name: Nigel Kennedy/Anna Winship Job title: Head of Finance Service Area / Department: Finance Tel: 01865 252708 e-mail: [email protected]
List of background papers: Version number:
111 This page is intentionally left blank
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Periodic Reporting: Risk 2011/12Report | 35 KB | DownloadRead as text |
PDF |
Risk report A and BReport | 32 KB | Download |
Follow City Executive Board (became Cabinet at Oxford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 May 2019 | Public QuestionsResolved to note the questions and answers provided. | Noted | Open |
| 13 May 2019 | Scrutiny Committee ReportsResolved to thank the Scrutiny Committees and the Scrutiny Panel for their useful input and to accept the recommendat... | Agreed | Open |
| 13 May 2019 | Scrutiny Committee ReportsIt was agreed that the Action Plan could be presented to the Housing Scrutiny Panel for review and monitoring. (4) Pr... | Agreed | Open |
| 13 May 2019 | Scrutiny Committee ReportsResolved to thank the Committee for its input and accept the recommendations in the report. | Decided | Open |
| 13 May 2019 | Scrutiny Committee ReportsResolved, on the Scrutiny Select Committee report on public health:- (1) To endorse each of the recommendations of th... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.