Oxford City Council
Cabinet, Wednesday 19 August 2026 at 6.00pm

Procurement of a GO strategic partner

Noted Executive 3 papers

AI summaryOxford City Council Cabinet noted progress on procuring a strategic partner to design and implement the Greater Oxford Council and delegated contract award to the Chief Executive, with consultancy value up to approximately £850,000 including VAT over 24 months from autumn 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted update and delegated award to Chief Executive
MoneyUp to approx £850,000 inc VATEx VAT approx £710,000, over 24 months from autumn 2026
What happens nextRun compliant procurement, then awardUnder Procurement Act 2023 via delegated authority
Who it affectsGreater Oxford Council programmeDesign and implementation of the new council

What was decided

Cabinet noted the update on the progression of procuring a strategic partner for the design and implementation of the Greater Oxford Council.

Authority to award the contract was delegated to the Chief Executive, in consultation with the Group Finance Director and Monitoring Officer. Report P11

Why

The estimated contract value of up to approximately £710,000 excluding VAT exceeds the threshold under the Procurement Act 2023, so a compliant competitive exercise is required. Report P1, P8, P9

Because the value is a key decision under Part 4.5 of the Council's Constitution, it must be taken through Cabinet and the delegation routes set out. Report P10, P11

Officers warn that failing to secure the right specialist support quickly would put the programme, its timescales and outcomes at risk. Report P14

What happens next

Procure a strategic partner under the Procurement Act 2023 and the Council's Contract Rules, with break clauses allowing the new Greater Oxford Council to review or terminate after vesting. Report P3, P9

If the proposed award is over the key decision threshold, publish it on the forward plan 28 days before a further officer delegated decision is taken to award. Report P12

Spending will be tracked through a notional budget profile linked to the programme, with monitoring through the Medium Term Financial Plan. Report P4, P5

The money

  • approximately £710,000 excluding VAT Estimated value of consultancy services, 24 month period from autumn 2026 Report P1
  • approximately £850,000 including VAT Estimated value of consultancy services, 24 month period from autumn 2026 Report P1

Implications

  • Legal: Procurement must comply with the Procurement Act 2023, related regulations and the Council's Contract Rules, including transparency, fair competition and value for money. Report P9
  • Legal: The decision is a key decision under Part 4.5 of the Constitution; delegation to officers is permitted under the Local Government Act 2000. Report P10, P11
  • Equalities: The procurement integrates the Public Sector Equality Duty and Social Value; an initial Equalities Impact Assessment is at Appendix Two, with fuller work expected in programme design. Report P17, P18, P19
  • Financial: Funding is available within approved budgets and reserves, aligned with the Medium Term Financial Plan, with no commitment entered into until contract award. Report P5, P6
  • Risk: A risk register is set out at Appendix One; the headline risk is that without the right specialist support, programme delivery, timescales and outcomes could suffer. Report P14, P15
  • Climate: No direct climate or environmental implications arise from the delegation decision; relevant climate considerations will be reflected in programme delivery where appropriate. Report P21, P22

Who and where

  • Future Greater Oxford Council and its vesting arrangements Report P3, P26
  • Internal LGR Transition Board and senior officers Report P24

Timeline

  • autumn 2026: Start of the 24 month strategic partner consultancy contract Report P1
  • 24 month period from autumn 2026: Planned duration of the consultancy contract, with break clauses for review post vesting Report P1, P3
  • 28 days in advance of award decision: Forward plan entry required if officer delegated award exceeds the key decision threshold Report P12

Plain English for the jargon

  • LGR: Local Government Reorganisation, the programme creating new unitary councils
  • GO: Greater Oxford, the proposed new unitary council referenced as the Greater Oxford Council
  • PSED: Public Sector Equality Duty, the equality obligations public bodies must consider
  • S151 Officer: The Council's statutory chief finance officer, responsible for proper financial administration
  • Key decision: An executive decision of significant financial or service impact, subject to the Council's Constitution rules
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item38

Resolved

Cabinet resolved to: Note the update as to the progression of the procurement of a strategic partner for the design and implementation of the Greater Oxford Council. Delegate authority to the Chief Executive, in consultation with the Group Finance Director and Monitoring Officer to award the contract.
Word for word from the decision Oxford published for this meeting. Source: mycouncil.oxford.gov.uk

Follow this further

Built from Oxford's papers

What the report saysPro

Report to Cabinet

Agenda Item 9

To: Cabinet Date: 19 August 2026 Report of: Mish Tullar, Transition Director Title of Report: Procurement of a strategic partner to support implementation of the Greater Oxford Council.

Summary and recommendations Decision being This report seeks Cabinet approval to procure a strategic taken: partner for the design and implementation of a Greater Oxford Council, and working within an established systemwide LGR implementation governance framework. It also seeks to delegate authority to the Chief Executive, in consultation with the Group Finance Director and Monitoring Officer, to award and appoint the strategic partner consultancy support, except where there is an existing officer delegation within the Council’s Constitution. Key decision: Yes. FORWARD PLAN ENTRY Cabinet Member: Councillor Susan Brown, Leader of the Council Corporate Priority: The Council Strategy Policy Framework: The Governments English Devolution White Paper.

Recommendation(s): That Cabinet resolves to: 1. Note the update as to the progression of the procurement of a strategic partner for the design and implementation of the Greater Oxford Council. 2. Delegate authority to the Chief Executive, in consultation with the Group Finance Director and Monitoring Officer to award the contract.

Information Exempt From Publication

25 State in here what None information is to be exempt from publication – where it is, attach it as an appendix and name the appendix as you describe It here

Appendix No. Appendix Title Exempt from Publication Appendix One Appendix One: Risk No Register Appendix Two Equality Impact No Assessment

Introduction and background

1. Following an invitation from Government, in November 2025, the Council submitted a 3 Councils (3Cs) proposal for Local Government Reorganisation (LGR) in Oxfordshire and West Berkshire.

2. On 16 July 2026, the Government announced its decision as a 3 Councils model for its preferred model for LGR in Oxfordshire and West Berkshire.

3. All councils in Oxfordshire and West Berkshire are working collaboratively in preparations for the transition to new unitary local authority structures.

4. It is expected that specialist consultancy support will be procured to support the systemwide LGR Programme Implementation Team, which will involve senior officers of all existing councils. Support will be needed at a systemwide level to navigate the complex disaggregation of existing councils and integration of systems, assets and workforces into new authorities.

5. As architect of the 3 Councils proposal, Oxford City Council will also require specialist consultancy support to develop and implement detailed designs for a Greater Oxford Council. The contract would be a smaller and more focused assignment than the systemwide consultancy contract, with both providers working in partnership with the overall LGR Implementation Team.

6. The contract is considered necessary to ensure smooth transition of LGR and therefore critical. There was urgency in moving ahead with procurement ahead of - and contingent upon - the Government’s decision for Oxfordshire and West Berkshire due to competition in the market nationally for limited specialist consultancy resources, given 21 county areas re going through LGR at the same time.

26 7. On 13 July 2026 a Single Member decision was taken to initiate the procurement process for a Strategic Partner, with the requirement that any contract award was subject to Cabinet approval (Decision - Project approval to initiate procurement).

8. Carrying out the procurement exercise early to be ready to swiftly appoint the necessary consultancy support enabled the Council to mobilise at pace following the Government’s decision, while ensuring full compliance with procurement legislation and the Council’s established governance arrangements. This approach mitigated the risk of delay to programme delivery and ensured the Council was well-positioned to meet the Government’s timeline and mobilisation expectations.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk Assessment (1)Appendix One 128 KB Download
PDF
EQIA (1)Appendix Two 255 KB Download
PDF
Procurement of a GO strategic partnerReport 120 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 15 attended
AR
Alistair RushCouncil Officer/ adviser, present
CS
Catherine StoneOfficer, expected
BL
Bill LewisCouncil Officer/ adviser, expected
HC
Hannah Carmody-BrownCommittee Services Officer, expected
CR
Celeste ReyeslaoCommittee Services Officer, expected
UK
Uswah KhanCommittee Services Officer, expected
SB
Councillor Susan Brown Leader, and Cabinet Member for Partnership Working, Inclusive Economic Growth and CultureCommittee Member, present
ET
Councillor Ed Turner Deputy Leader (Statutory), and Cabinet Member for Finance and Asset ManagementCommittee Member, apologies
AR
Councillor Anna Railton Deputy Leader, and Cabinet Member for Planning and Zero Carbon OxfordCommittee Member, present
LA
Councillor Lubna Arshad Cabinet Member for a Safer OxfordCommittee Member, present
NC
Councillor Nigel Chapman Cabinet Member for Citizen Focused Services and Council CompaniesesCommittee Member, apologies
LS
Councillor Linda Smith Cabinet Member for Housing and CommunitiesCommittee Member, apologies

All 15 on the meeting page

More from Oxford Cabinet

All decisions
MeetingDecisionOutcome
19 Aug 2026 Controlled Parking Zones (CPZ) Review of existing zones and CIL spendCabinet resolved to: Approve the request to add the West Oxford Controlled Parking Zone (CPZ) to the approved list of... Approved Open
19 Aug 2026 Oxfordshire Infrastructure Strategy (OxIS)Cabinet resolved to: Endorse the Oxfordshire Infrastructure Strategy (OxIS) which has already been endorsed by the Ox... Decided Open
19 Aug 2026 Use of CIL funding to support infrastructure and public realm related to the Cowley Branch LineCabinet resolved to: Ringfence 30% of future CIL income arising from development within 1.5 km of either of the two C... Agreed Open
8 Jul 2026 Thames Valley Strategic Authority Proposal: Update and Implications for Oxford CityCabinet resolved to: 1. Note Oxfordshire County Council’s decision to veto the Thames Valley Foundation Strategic Aut... Agreed Open
8 Jul 2026 Local Development Scheme 2026-2031Cabinet resolved to: 1. Approve the ; 2. Authorise the Director of Planning and Regulation Services to make any neces... Approved Open