Controlled Parking Zones (CPZ) Review of existing zones and CIL spend
ApprovedExecutive3 papers
AI summaryOxford City Cabinet approves adding West Oxford Controlled Parking Zone to ongoing review programme, funded from existing CIL monies already released to the county council.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedDelegation to Director of Planning and Regulation
Money£281,675 total programme costNo new CIL funding requested
What happens nextReview to complete by 2027-28Year 2 works already underway
Who it affectsWest Oxford residents and driversOne of city's oldest CPZs
What was decided
Cabinet approved adding the West Oxford Controlled Parking Zone to the list of existing CPZs being reviewed by Oxfordshire County Council, using previously agreed CIL monies. Report P4
Any further underspend from the programme will be returned to the CIL pot for strategic infrastructure. Report P10
Authority was delegated to the Director of Planning and Regulation to make any further amendments to the list of CPZs in the review. Report P5
Why
Oxfordshire County Council reported cost savings on Year 1 reviews, reducing actual spend from an estimated £241,760 to £146,514, which allows the West Oxford zone to be added without further CIL funding. Report P9
The county council cited ongoing resident and councillor complaints, the impact of the Botley Road closure, and the age of the West Oxford zone with many developments affecting on-street parking. Report P9
CIL can be used to fund infrastructure supporting development, and CPZs are listed in the council's infrastructure funding statement as projects that may be wholly or partly funded by CIL. Report P13
What happens next
Oxfordshire County Council will deliver the West Oxford CPZ review alongside Headington West, Florence Park and Cuttleslow in Year 2 (2026-27), subject to further Cabinet approval. Report P9
All reviews and associated works are expected to complete by financial year 2027-28, before any implications of Local Government Reorganisation arise. Report P7, P11
Once Year 2 reviews are complete, any remaining underspend will be returned to the CIL pot for strategic infrastructure. Report P10, P12
The money
£500,000 Original CIL contribution agreed in 2018 for CPZ programme to 2028 Report P7
£33,000 Released for Donnington CPZ (new) Report P7
£24,000 Released for Upper Wolvercote CPZ (new) Report P7
£358,080 CIL monies released in December 2024 for 7 CPZ reviews Report P7
£241,760 Original estimated cost for Year 1 reviews Report P9
£146,514 Actual cost of Year 1 reviews after savings Report P9
£281,675 Revised total cost of the full 8-zone review programme Report P9
Options considered
Chosen: Add West Oxford CPZ to the review list using existing CIL monies. Year 1 cost savings allow inclusion without additional funding; addresses ongoing resident complaints and Botley Road closure impact Report P8, P9
Chosen: Return any further underspend to the CIL pot for strategic infrastructure. CIL funds should be applied to infrastructure supporting development of the area Report P10, P13
Chosen: Delegate authority to amend the list of CPZs in the review. Allows flexibility to respond to county council requests without further cabinet approval Report P5
Implications
Financial: No additional CIL funding requested; the £358,080 already released will cover all 8 zone reviews, with anticipated underspend returned to the CIL pot. Report P8, P12
Legal: Release of CIL spend is in accordance with CIL regulations; CPZs are listed in the council's infrastructure funding statement. Report P13
Equalities: Equalities Impact Assessment from December 2024 remains unchanged and applicable. Report P15
Climate: CPZs restrict overall parking and support transport strategies promoting sustainable or lower carbon travel, helping reduce car emissions and improve air quality. Report P16
Risk: A risk register has been prepared and is attached as an appendix. Report P14
Who and where
Residents and drivers in West Oxford affected by the CPZ review Report P9
Oxford City Council ward members for affected areas Report P9
Oxfordshire County Council, which manages and delivers CPZs Report P3
Timeline
2018: Initial agreement to contribute £500,000 of CIL to CPZ programme to 2028 Report P7
December 2024: Cabinet approved release of £358,080 of CIL monies for 7 CPZ reviews Report P7
Year 1 (2025-26): Reviews completed for East Oxford, Headington Central, Summertown and Temple Cowley CPZs Report P9
Year 2 (2026-27): Reviews underway for Headington West, Florence Park and Cuttleslow CPZs; West Oxford now added Report P9
Financial year 2027-28: All reviews and associated works expected to complete Report P7, P11
Plain English for the jargon
CIL: Community Infrastructure Levy, a charge local authorities can levy on new development to fund infrastructure
CPZ: Controlled Parking Zone, an area where parking is only permitted in designated bays with yellow line restrictions elsewhere
TRO: Traffic Regulation Order, the legal instrument used to introduce parking restrictions
Forward plan: A document setting out key decisions the council expects to make over coming months
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item39
Resolved
Cabinet resolved to: Approve the request to add the West Oxford Controlled Parking Zone (CPZ) to the approved list of existing CPZ’s in the city being reviewed by Oxfordshire County Council using previously agreed CIL monies. Approve the return of any further underspend to the CIL pot for strategic infrastructure. Delegate authority to the Director of Planning and Regulation to make any further amendments to the list of CPZs included in the review.
Word for word from the decision Oxford published for this meeting.Source: mycouncil.oxford.gov.uk
To: Cabinet Date: 19 August 2026 Report of: Director of Planning and Regulation Title of Report: Controlled Parking Zones (CPZ’s) and Community Infrastructure Levy (CIL) Monies
Summary and recommendations Decision being Approve the request to add the West Oxford Controlled taken: Parking Zone (CPZ) to the approved list of existing CPZ’s in the city that are being reviewed by Oxfordshire County Council using previously agreed CIL monies. Key decision: Yes - Forward plan - May 2026 - August 2026<,. | Oxford City Council Cabinet Member: Councillor Anna Railton, Deputy Leader, and Cabinet Member for Planning and Zero Carbon Oxford title Corporate Priority: Good, affordable homes, Strong, fair economy, Thriving communities, Zero carbon Oxford, A well-run council Policy Framework: The Community Infrastructure Levy (CIL) was introduced by the Planning Act 2008 as a tool for local authorities to help the funding of and delivery of infrastructure to support the development of their area. Oxford City Council is the charging authority for the CIL in Oxford. A Controlled Parking Zone (CPZ) is a type of parking restriction where parking is only permitted in designated parking bays and the rest of the kerbside is restricted by yellow lines. CPZ’s are defined in statute by Schedule 4 of the Traffic Signs Regulations and General Directions 2016. CPZs in Oxford City are managed, maintained and developed by the local highway authority, Oxfordshire County Council.
Recommendation(s): That Cabinet resolves to: 1. Approve the request to add the West Oxford Controlled Parking Zone (CPZ) to the approved list of existing CPZ’s in the city being reviewed by Oxfordshire County Council using previously agreed CIL monies.
49 2. Approve the return of any further underspend to the CIL pot for strategic infrastructure. 3. Delegate authority to the Director of Planning and Regulation to make any further amendments to the list of CPZs included in the review.
Appendix No. Appendix Title Exempt from Publication Appendix 1 Risk Register No Appendix 2 Equality Impact No Assessment
Introduction and background 1. Oxford City Council has previously agreed to contribute £500,000 of CIL to the roll out of a programme of CPZ’s across the city in the period to 2028. This agreement was initially made in 2018 to support the planning and transport policies of both the city and county councils, more specifically for Oxford City to help enable residential sites to come forward for development at a higher density and with reduced parking provision. 2. In December 2024, the City Council’s Cabinet approved the release of £358,080 of CIL monies to Oxfordshire County Council for the delivery of 7 reviews of existing Controlled Parking Zones (CPZ’s) within the city boundary. At this time, £57,000 of the initially agreed £500,000 had been released to deliver new CPZs at Donnington (£33,000) and Upper Wolvercote (£24,000). There was therefore £443,000 remaining. 3. The review was expected to last a period of three years, with all reviews and associated works expected to complete by the financial year 2027-28. The review was split into a two year programme with 4 zones included in Year 1 (2025-2026) and 3 zones in Year 2 (2026-2027). The zones, funding requirements and delivery year in which they were to be reviewed are set out in Table 1 below. Table 1 - Controlled Parking Zones, Funding Requirements and Delivery Year Controlled Parking Zone Total* Delivery Year East Oxford £65,440 Year 1 (2025-26) Headington Central £65,440 Year 1 (2025-26) Summertown £65,440 Year 1 (2025-26) Temple Cowley £45,440 Year 1 (2025-26) Headington West £40,440 Year 2 (2026-27) Florence Park £40,440 Year 2 (2026-27) Cuttleslow £35,440 Year 2 (2026-27) TOTAL £358,080 *Note the Total column is inclusive of TRO fees, Project Management and Works costs
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Procurement of a GO strategic partnerCabinet resolved to: Note the update as to the progression of the procurement of a strategic partner for the design a...
Local Development Scheme 2026-2031Cabinet resolved to: 1. Approve the ; 2. Authorise the Director of Planning and Regulation Services to make any neces...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.