Resolved
Resolved that the Committee noted the progress with the 2024/25 Internal Audit Plan and the outcome of the completed audits.
Audit & Governance Committee noted this item on Wednesday 18 September 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the Committee noted the progress with the 2024/25 Internal Audit Plan and the outcome of the completed audits.
1. The Committee is RECOMMENDED to
Note the progress with the 2024/25 Internal Audit Plan and the outcome of the completed audits.
Executive Summary 2. This report provides an update on the Internal Audit Service, including resources, completed and planned audits.
3. The report includes the Executive Summaries from the individual Internal Audit reports finalised since the last report to the May 2024 Committee. Since the last update, there have been no red reports issued.
Progress Report: Resources: 4. A full update on resources was made to the Audit and Governance Committee in May 2024 as part of the Internal Audit Strategy and Plan for 2023/24. Since May 2024 our new Senior Auditor has started (June 2024), and our new audit apprentice joined us at the beginning of September 2024. One of our Principal Auditors is currently on maternity leave but will be returning from the beginning of October 2024.
5. We continue to support team members to compete professional training. Two of our apprentices (one for Counter Fraud and one for Internal Audit) are now in permanent posts within the team.
2024/25 Internal Audit Plan: 6. The 2024/25 Internal Audit Plan, which was agreed at the May 2024 Audit & Governance Committee, is attached as Appendix 1 to this report. This shows current progress with each audit and any amendments made to the plan. The plan and plan progress is reviewed regularly with senior management. There have been two amendments to the plan (additions), these are included in Appendix 1. 7. There have been 4 audits concluded since the last update, summaries of findings and current status of management actions are detailed in Appendix 2. The completed audits are as follows:
Final Reports 2024/25:
Directorate Audit Opinion
Resources Property Strategy Implementation Green
Resources IT Corporate Website Amber Library Management System IT Libraries Amber Application Review Primary School 1 - Governance & Childrens Amber Financial Management Audit
PERFORMANCE 6. The following performance indicators are monitored on a monthly basis.
Performance Target % Performance Comments Measure Achieved for 24/25 audits (as at 14/08/24) Elapsed time between Target date 100% Previously start of the audit agreed for each reported year- (opening meeting) and assignment by end figures: Exit Meeting. the Audit 2023/24 67% manager, stated 2022/23 71% on Terms of 2021/22 59% Reference, but should be no more than 3 X the total audit assignment days (excepting annual leave etc) Elapsed Time for 15 days 75% Previously completion of audit work reported year- (exit meeting) to issue of end figures: draft report. 2023/24 96% 2022/23 89% 2021/22 86% Elapsed Time between 10 days 100% Previously receipt of management reported year- responses to draft report end figures: and issue of final report. 2023/24 100% 2022/23 92% 2021/22 66%
The other performance indicators are:
% of 2024/25 planned audit activity completed by 30 April 2025 - reported at year end.
% of management actions implemented (as at 14/08/24) – 72.3% of actions have been implemented. Of the remaining 27.7% there are 11.6% of actions that are overdue, 7.1% partially implemented and 9% of actions not yet due.
(At May 2024 A&G Committee the figures reported were 68.7% implemented, 5.8% overdue, 7.5% partially implemented and 18% not yet due)
Extended Management Team satisfaction with internal audit work - reported at year end.
Appendix 3
The table in Appendix 3 lists all audits with outstanding open actions, it does not include audits where full implementation has been reported. It shows the split between Priority 1 and Priority 2 actions implemented.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit 2023/24: Progress ReportReport | 17 pages | DownloadRead as text |
Follow Audit & Governance Committee at Oxfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jul 2026 | Treasury Management- Outturn report 2025/26RESOLVED to note Council’s treasury management activity and outcomes in 2025/26. | Noted | Open |
| 15 Jul 2026 | Statement of Accounts 2025/26RESOLVED to approve the draft Statement of Accounts for 2025/26. | Approved | Open |
| 15 Jul 2026 | Counter Fraud Plan and UpdateRESOLVED to note the annual summary of counter fraud activity for 2025/26 and approve the Counter Fraud Plan for 2026... | Noted | Open |
| 15 Jul 2026 | Risk Management UpdateRESOLVED to note the risk management update. | Noted | Open |
| 15 Jul 2026 | Local Government and Social Care Ombudsman's Annual Review ReportRESOLVED to note, having received and commented on, the Local Government and Social Care Ombudsman’s Annual Review of... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.