Oxfordshire County Council
Finance, Friday 14 February 2025 at 10.00am

Wood Green School, Witney

Approved Finance 2 papers

Finance approved this item on Friday 14 February 2025. Below is the council's own wording, with the papers it was decided on.

Item10/25

Resolved

RESOLVED to Approve the completion of the Funding Agreement with Acer Trust which will release funding greater than £1m to Acer Trust to enable the construction of a new teaching block at Wood Green Secondary School in Witney.
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Finance, 4 pages

Recommendation

1. The Cabinet Member is RECOMMENDED to

Approve the completion of the Funding Agreement with Acer Trust which will release funding greater than £1m to Acer Trust to enable the construction of a new teaching block at Wood Green Secondary School in Witney.

Executive summary

2. Wood Green School is an academy managed by Acer Trust.

3. Due to local housing growth and rising primary school numbers, there is a pupil- place pressure for secondary places in Witney. The council agreed with Acer Trust that they would expand the admission number at Wood Green School by 150 places, from 7 forms of entry to 8 forms of entry, using funding provided by the council.

4. The expansion will be achieved by constructing a new teaching block which has planning approval from WODC. Acer Trust have tendered the project and the tender sum for construction forms part of the project budget.

5. The budget for this project is £4.239m, approved in the Outline Business Case in May 2024. The Full Business Case will be submitted for approval In February 2025, and once that has been approved, it will enable Acer Trust to commence construction.

Corporate Policies and Priorities

6. This proposed course of action supports the council’s statutory duty to provide pupil places.

Financial implications

7. This expansion project has obtained Capital Governance approval as below:

 Initial Business Case, approved June 2023 with a £3.3m budget

V2.0 Nov 2024  Outline Business Case, approved May 2024 with a £4.239m budget

 Full Business Case to be submitted for approval at Property Capital Board on 19 February 2025.

8. The project is fully funded from S106 contributions received by the council.

9. There are no revenue implications for the council as Wood Green School is an academy, under the management of Acer Trust.

Comments checked by:

Drew Hodgson, Strategic Finance Business Partner Email: [email protected]

10. The council has a statutory duty including under section 14(1) of the Education Act 1996 and all other relevant Acts of Parliament, regulations to secure additional school places for children within the County. This funding arrangement to Acer Trust will enable the council to fulfil its statutory function.

11. As the funding under the Funding Agreement will be passed directly to works contractors to cover the building and other professional costs, there is no benefit to Acer Trust, this being a mere pass-through arrangement. Therefore, there are no Subsidy law implications of transferring this funding to Acer Trust.

12. Under the terms of the funding agreement, in selecting contractors and consultants for the building works, Acer Trust is required to go through a procurement process which would be compliant with the Public Contract Regulations 2015 (“PCR 2015”). This ensures that the works contracts represent value and comply with the council’s obligations under PCR 2015, under the Subsidy Control Act 2022 and under the council’s Contract Procedure Rules. Acer Trust will also be required to comply with all applicable legislation in carrying out the building project.

Comments checked by:

Busola Akande Solicitor Email: [email protected]

Staff Implications

13. The course of action will result in further staff costs for OCC Property, Legal and Highways, which will be recharged against the project budget, as previous staff costs have been. Equality & Inclusion Implications

14. The project does not have any equality and inclusion implications with no change to current operations.

Sustainability Implications

15. The scheme has been designed to meet very high standards of sustainable design. Working with the DfE Output Specification as a starting point, this sets a target of Net Zero Carbon in Operation. The scheme has been future proofed to be able to achieve this.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CMDF20250214R1: Annex: Business Case /25Appendix 6 pages Download
PDF
Wood Green School, WitneyReport 4 pages DownloadRead as text

At this meeting

Whole meeting
9/25Minutes of the Previous MeetingOn the agenda
10/25Wood Green School, WitneyThis decision

More from Oxfordshire Finance

All decisions
MeetingDecisionOutcome
16 May 2025 Tender for Insurance coverage and associated service (not brokering services)RESOLVED to: a) approve, as a key decision, the commencement of the procurement of insurance cover for the Council; a... Approved Open
11 Apr 2025 Fire Remedial Project Phase 2&3RESOLVED to: approve the entering into contract with Hughes & Associates to deliver the £3.7m capital funded Fire Com... Approved Open
11 Apr 2025 Outline business case for Property decarbonisation programme 2025/26RESOLVED to: a) Note that the total Property Decarbonisation Programme Budget included in the capital programme for 2... Approved Open
10 Jan 2025 Marlborough School, WoodstockRESOLVED to: approve the sealing of a funding agreement to enable the Council to release funding greater than £1 mill... Approved Open
13 Dec 2024 Union Street Phase 1.5 & 2 - Refurbishment and Decarbonisation ProjectRESOLVED to: a) Approve the release of funding greater than £1m for the provision of construction services to carry o... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies