Finance, Friday 11 April 2025 at 10.00am

Outline business case for Property decarbonisation programme 2025/26

Approved Finance 1 paper

Finance approved this item on Friday 11 April 2025. Below is the council's own wording, with the papers it was decided on.

Item16/25

Resolved

RESOLVED to: a) Note that the total Property Decarbonisation Programme Budget included in the capital programme for 2025/26 will be £10m for works to 20 sites b) Approve the commencement of the procurement of decarbonisation works for the sites in the programme of works, noting that where sites are batched together into a single procurement exercise these may have a combined value in excess of £2m c) Delegate authority to the Executive Director of Resources & Section 151 Officer to agree the procurement strategy and approve the award of contracts associated with the 2025/26 Property Decarbonisation Programme
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Finance, 6 pages

Recommendation

1. The Cabinet Member Finance is RECOMMENDED to

a) Note that the total Property Decarbonisation Programme Budget included in the capital programme for 2025/26 will be £10m for works to 20 sites

b) Approve the commencement of the procurement of decarbonisation works for the sites in the programme of works, noting that where sites are batched together into a single procurement exercise these may have a combined value in excess of £2m

c) Delegate authority to the Executive Director of Resources & Section 151 Officer to agree the procurement strategy and approve the award of contracts associated with the 2025/26 Property Decarbonisation Programme

Executive summary

2. The Council has secured central government grant funding of £0.36m, requiring £10m match funding, to conduct full scale property decarbonisation of 20 buildings, putting these buildings on the pathway to net zero. This includes the electrification of heating, building fabric improvements, electrical efficiency improvements and deployment of renewable electricity generation technology.

V2.0 Nov 2024 3. This funding is time limited and need to be spent by 31 March 2026. A complex programme of works to replace aged equipment in a poor state of repair will generate potential carbon savings of 333 Tonnes of CO2e1.

4. A range of options are presented within the report, with the recommendation to approve the full set of works to achieve the maximum decarbonisation benefits.

Exempt Information

5. The table 2 in appendix 1 is to be exempted on the basis that the information relates to the financial or business affairs of the council. The Council has yet to procure these works. Disclosing the budget per site would distort the proper process of open competition and prejudice the position of the council in the future procurement of the contracts and the Council’s standing generally in relation to such procurements in future, to the detriment of the Council’s ability to properly discharge its fiduciary and other duties as a public authority.

Background

6. The Council declared a climate emergency in 2019 with a target of 2030 to bring the Council’s operations and activities to carbon neutrality. This target is reflected in the Council’s Climate Action Framework and Property Strategy.

7. In 2023/24 the Council’s property accounted for approximately 35% (2,706 tCO2e) of the emissions that need to be reduced to meet the carbon neutrality target by 2030. In addition, a reactive only maintenance approach has left much of the Council’s estate in very poor-quality condition, with many components past their expected working life and in need of replacement irrespective of the carbon neutrality target.

8. To reduce emissions the aim is to stop fossil fuelled activities within the Council’s properties, which is predominantly heating, via the electrification of these components. Although there will be a carbon component remaining by 2030 from the use of electricity, this will be much reduced according to the government’s Clean Power 2030 Action Plan and will be on the pathway to fully net zero by 2050 in line with the decarbonisation of the electricity grid. This should enable an ever-reducing need for carbon offsetting by 2030 and beyond which is outside of this scope of works but is recognised by the industry to be a significant unknown, given the currently few recognised and accepted methods of carbon offsetting.

9. The transition to electric heating will predominantly be via heat pumps and infrared heating. Due to the lower operating temperatures of the heat pumps improvements are required in thermal building fabric (e.g. single glazing to double or triple glazing, insulation installations, etc.) to decrease the potential

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Outline business case for Property decarbonisation programme 2025/26Report 6 pages DownloadRead as text

At this meeting

Whole meeting
14/25Minutes of the Previous MeetingOn the agenda 15/25Fire Remedial Project Phase 2&3Approved
16/25Outline business case for Property decarbonisation programme 2025/26This decision

On this subject at Oxfordshire

Search all
  1. Outline business case for Property decarbonisation programme 2025/26This decision
  2. ERP Outline Business Case - A Programme for Transforming the Council's Enterprise Business Systems and ProcessesApproved

More from Oxfordshire Finance

All decisions
MeetingDecisionOutcome
16 May 2025 Tender for Insurance coverage and associated service (not brokering services)RESOLVED to: a) approve, as a key decision, the commencement of the procurement of insurance cover for the Council; a... Approved Open
11 Apr 2025 Fire Remedial Project Phase 2&3RESOLVED to: approve the entering into contract with Hughes & Associates to deliver the £3.7m capital funded Fire Com... Approved Open
14 Feb 2025 Wood Green School, WitneyRESOLVED to Approve the completion of the Funding Agreement with Acer Trust which will release funding greater than £... Approved Open
10 Jan 2025 Marlborough School, WoodstockRESOLVED to: approve the sealing of a funding agreement to enable the Council to release funding greater than £1 mill... Approved Open
13 Dec 2024 Union Street Phase 1.5 & 2 - Refurbishment and Decarbonisation ProjectRESOLVED to: a) Approve the release of funding greater than £1m for the provision of construction services to carry o... Approved Open