RESOLVED to a) approve the commencement of work to explore and consider options for the household waste recycling centre management service delivery provision, noting that the current contract is coming to an end in September 2027. b) endorse the proposed approach for developing the options and key procurement stages as set out in this paper. c) approve the use of Extended Producer Responsibility funding for consultancy work to support the future household waste recycling centre model development.
Word for word from the decision Oxfordshire published for this meeting.Source: mycouncil.oxfordshire.gov.uk
a. Approve the commencement of work to explore and consider options for the household waste recycling centre management service delivery provision, noting that the current contract is coming to an end in September 2027.
b. Endorse the proposed approach for developing the options and key procurement stages as set out in this paper.
c. Approve the use of Extended Producer Responsibility funding for consultancy work to support the future household waste recycling centre model development.
Executive summary
2. Under Section 51 of the Environmental Protection Act 1990, Oxfordshire County Council (the Council) has a legal duty to provide household waste recycling centres for Oxfordshire residents.
3. The Council’s current household waste recycling centres management contract has been extended and comes to an end on 30 September 2027. A future model for the service delivery is required to be in place and mobilised prior to the expiry of the existing contract.
4. Due to the changing nature of the household waste recycling centre sector, the model for how the Council manages its household waste recycling centre provision needs to be fully explored before determining the best option for the new arrangement. This will aim to maximise reuse and recycling, and reduce waste to landfill or energy recovery and so help tackle the climate emergency and assist with delivering the Circular Economy. 5. To undertake the new household waste recycling centres management service delivery model, it is proposed there will be three main decision points for Cabinet:
a. This report seeking support for commencement of work to explore and consider the new service delivery options.
b. When initial options have been explored, a key decision will be made to commence procurement of the preferred service delivery model (June 2025).
c. To seek a key decision to implement /award the new service and any related contracts (March 2027), allowing the commencement of the mobilisation of the preferred service delivery model.
Current contract arrangements
Background
6. The Council is the Waste Disposal Authority and, together with the districts and City Council, has one of the highest recycling rates in England, along with very low waste arisings per head. Working together under the Oxfordshire Resources and Waste Partnership, and with the household waste recycling centres strategy, the Council aims to deliver targets on recycling and reducing waste to landfill. The Council’s network of 7 household waste recycling centres are a key component in delivering the Council’s obligations to the partnership and the strategy. Collectively they handle around 15% of the total household waste arisings in Oxfordshire, recycling, composting and reusing around 65% of the waste delivered to the sites and receiving around 1 million visits per annum.
7. The current contract commenced on the 1 October 2017 being awarded to Geoffrey David Thompson trading as Weymouth and Sherborne Recycling (W&S). W&S run and operate 6 of the 7 sites, the exception being the Dix Pit site though at that site W&S provide all the logistics and the majority of the containers. The site staff and day to day management of Dix Pit is carried out by FCC Environment. This exception is due to a long-term arrangement and contract linked to the 1986 Dix Pit landfill contract and the transfer station which shares the same site and is also operated by FCC Environment under a different contract.
8. Historically contracts have tended to pass financial risks to the contractor however this is considered to be unlikely to be acceptable in the current market.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.