Oxfordshire County Council
Cabinet, Tuesday 17 March 2026 at 2.00pm

Household Waste Recycling Centres (HWRC) - Management Reprovision

Approved Key decision Executive 3 papers

AI summaryCabinet approved procurement of a new 8 year household recycling centre management contract from 1 October 2027, with checks on buying plant and equipment and delegated award authority. [D] [P3] [P4] [P5] The current contracts cost a combined £3.7m in 2024. [P23]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedStarts 1 October 2027; award authority delegated. [P3] [P5]
MoneyCurrent contracts: £3.7m in 2024 [P23]Historic combined cost; new price will be set by tender. [P23] [P10]
What happens nextProcurement launch expected April 2026 [P58]Award approval expected in late March 2027. [P59]
Who it affectsOxfordshire residents and seven HWRCs [P6]Main procurement covers six sites; Dix Pit is a variant. [P76]

What was decided

Cabinet chose the preferred reprovision approach: a single provider under a long term 8 year management contract, with reorganisation flexibility. [D] [P9] [P54] Report P9, P54

Officers may prepare and start procurement for a contract starting 1 October 2027 after mobilisation, with options to reflect reorganisation changes. [D] [P3] [P59] Report P3, P59

Cabinet approved testing a council purchase of plant and equipment during bidding. [D] [P4] Award decisions and any extension are delegated to the Director of Environment and Highways, in consultation with the Cabinet Member for Place, Environment and Climate Action. [D] [P5] Report P4, P5

Why

The appraisal ranked seven delivery options by cost and qualitative risk. [P40] [P52] An earlier appraisal found outsourcing favourable when balancing service cost against risk. [P17] The long term procurement option later scored highest for quality and lowest cost. [P54] Report P17, P40, P52, P54

Eight years was considered optimal because vehicle, plant and equipment costs can be spread over the term. [P48] Four years could allow reorganisation to conclude, but soft market testing found short contract terms were not of interest to potential bidders. [P48] Report P48

The current contract cannot be extended and ends on 30 September 2027. [P6] [P29] Procurement must therefore be ready before the new council or councils come into being on 1 April 2028. [P29] Report P6, P29

What happens next

The service and Commercial Delivery lead will develop a procurement strategy. [P70] The Competitive Flexible Procedure is expected to launch in April 2026, with the questionnaire stage ending in June 2026. [P58] Report P58, P70

The initial tender is expected to finish by September 2026 and the final tender by early March 2027. [P58] Final evaluation and director approval for award are expected in March 2027, with award and mobilisation in late March 2027. [P59] Report P58, P59

Test buying plant and equipment during bidding and agree the final revenue and capital cost at the final tender stage. [D] [P4] Include reorganisation allowances, disaggregation and break clauses. [P55] [P60] Report P4, P55, P60

The money

  • £2.2m Combined cost of the HWRC management contracts in 2017. [P23] Report P23
  • £3.7m Combined cost of the HWRC management contracts in 2024. [P23] Report P23

Options considered

  • Chosen: Long term contractor procurement, 8 years. It scored highest for quality, had the lowest costs and allowed reorganisation flexibility. [P54] Report P9, P54
  • Rejected: Short term contractor procurement, 4 years. Four years could allow reorganisation to conclude, but short contract terms were not of interest to potential bidders. [P48] Report P48
  • Rejected: Council staff service, short or long term. An earlier appraisal found outsourcing favourable when balancing service cost against risk. [P17] Report P17, P42, P48
  • Rejected: Council owned trading company, short or long term Report P43, P45, P48
  • Rejected: Joint local authority trading company, short or long term Report P44, P48
  • Rejected: Delegation to Oxford City Council via ODS, short or long term Report P46, P48
  • Rejected: Joint venture between public bodies, short or long term Report P47, P48
  • Rejected: Joint venture between a public body and private provider, short or long term Report P47, P48

Implications

  • Legal: The council has a statutory duty to provide HWRCs under section 51 of the Environmental Protection Act 1990. [P74] The tender for six sites is not exempt and must follow the full Procurement Act 2023 regime. [P75] [P76] Report P74, P75, P76
  • Financial: The combined contract cost rose from £2.2m in 2017 to £3.7m in 2024, partly because of inflation and service changes. [P23] The appraisal says increased revenue and potentially capital funding will be required, and new assets are likely. [P55] Council ownership of plant and equipment could provide more flexibility over contract duration and the timing of a reorganisation break clause. [P55] Final contract costs will be negotiated and presented to the Director of Environment and Highways. [P56] Report P23, P55, P56
  • Risk: Failure to award a new contract or other service model by March 2027 would leave the council without a service to meet its statutory duty. [P94] Report P94
  • Risk: Reorganisation uncertainty is managed through disaggregation and a break clause. [P54] Future authorities could exit from year 3 or 4, subject to negotiation, and manage the contract independently if there is more than one authority. [P54] Report P54
  • Staffing: If the provider changes, staff may transfer from the current provider to the new provider. [P81] A minimum six month mobilisation period is considered ideal, alongside new plant, equipment and waste commodity contracts. [P81] [P82] Report P81, P82
  • Equalities: No negative impact is anticipated for protected characteristic groups, the armed forces, carers, staff or other council services. [P86] The procurement could benefit rural communities and deprived areas through local employment and social value measures. [P86] Social value will form a key award assessment, and weighting may include local jobs, small and medium sized businesses and climate actions. [P87] [P71] Report P71, P86, P87
  • Climate: The new contract is intended to support the target of a zero carbon Oxfordshire by 2050. [P89] It should adopt the latest innovations and technologies, reduce carbon use and emissions, and support recycling through access and reuse. [P89] [P90] A climate impact assessment has been completed. [P91] Report P89, P90, P91
  • Other: The service receives around 1 million customer visits and manages approximately 50,000 tonnes of waste per annum. [P13] Bookings, charges for out of county customers and waste sorting requirements were introduced on 14 January 2026. [P13] Report P13

Who and where

  • Oxfordshire residents who use household waste recycling centres. [P6] [P13] Report P6, P13
  • Staff delivering the service, who may transfer if the provider changes. [P81] Report P81
  • Weymouth and Sherborne Recycling, the current provider. [P14] [P15] Report P14, P15
  • FCC Environment Ltd, the Dix Pit landfill contract provider. [P16] Report P16
  • Prospective bidders and any new service provider. [P18] [P10] Report P10, P18
  • Future unitary council or councils. [P29] [P54] Report P29, P54
  • Local communities and areas of deprivation. [P86] Report P86
  • Oxfordshire County Council project and contract management staff. [P83] [P84] Report P83, P84

Timeline

  • 17 March 2026: Cabinet approved the management model. [D] [P62] Report P62
  • April 2026; June 2026: Competitive Flexible Procedure launch, followed by completion of the Procurement Specific Questionnaire. [P58] [P62] Report P58, P62
  • Summer 2026: Government decision on the preferred reorganisation proposal. [P62] Report P62
  • September 2026: Initial tender stage completed. [P62] Report P62
  • early March 2027; late March 2027: Final tender stage completed, then director approval, contract award and mobilisation. [P59] [P62] Report P59, P62
  • 1 October 2027: The new contract starts. [P59] [P62] Report P59, P62
  • 1 April 2028: New reorganisation authority or authorities come into effect. [P62] Report P62
  • October 2030 or 2031: Proposed contract break clause. [P63] Report P63

Plain English for the jargon

  • HWRC: A Household Waste Recycling Centre for disposing of household waste. [P6]
  • LGR: Local Government Reorganisation, involving possible new unitary councils in Oxfordshire. [P25] [P29]
  • CFP: Competitive Flexible Procedure, a staged procurement method allowing dialogue and negotiation. [P10] [P70]
  • TUPE: A staff transfer arrangement used when the service provider changes. [P81]
  • LATCo: Local Authority Trading Company, a separate legal entity that can trade commercially and is run by a council. [P43] [P45]
  • ODS: Oxford Direct Services, identified as the operator under the delegation option. [P46]
  • ERF: Ardley Energy Recovery Facility, which receives residual waste from all seven centres under exclusivity clauses until 2039. [P33]
  • Break clause: A contract exit option, proposed for October 2030 or 2031. [P54] [P63]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item44/26

Resolved

that the public be excluded for the duration of this item since it is likely that if they were present during that item there would be disclosure of exempt information as defined in Part I of Schedule 12A to the Local Government Act 1972 (as amended) and specified below in relation to those items and since it is considered that, in all the circumstances of the case, the public interest in maintaining the exemption outweighs the public interest in disclosing the information Cabinet had before it a report This document details a proposal for the procurement of a new management contract for Household Waste Recycling Centres (HWRCs). The contract was intended to cover the management of HWRCs across Oxfordshire for an 8-year period starting 1 October 2027, with flexibility provisions related to Local Government Reorganisation (LGR). The report includes background information, options appraisal, financial and legal considerations, and outlines key dates for the procurement process . Councillor Judy Roberts, Cabinet Member for Place, Environment and Climate Action presented the report. Councillor Roberts moved and Councillor Hannaby seconded the recommendations and they were approved. RESOLVED to:- a) Approve the preferred approach to the reprovision of the Household Waste Recycling Centre (HWRC) management as set out in paragraphs 5 and 31. b) Authorise Officers to prepare and commence the procurement of a new 8-year HWRC management contract to start on 1 October 2027 (following a mobilisation period) with options to support flexibility in Local Government Reorganisation (LGR). c) Endorse exploration and feasibility of the capital purchase of HWRC plant and equipment during the tender bidding, with a view to having an agreed final revenue and capital cost of the contract at the final tender stage. d) Delegate the decision to award the contract, and any extension to that contract to the Director of Environment and Highways in consultation with the Cabinet Member for Place, Environment and Climate Action.
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Cabinet, 12 pages

Recommendation

1. Cabinet is RECOMMENDED to

a) Approve the preferred approach to the reprovision of the Household Waste Recycling Centre (HWRC) management as set out in paragraphs 5 and 31.

b) Authorise Officers to prepare and commence the procurement of a new 8- year HWRC management contract to start on 1 October 2027 (following a mobilisation period) with options to support flexibility in Local Government Reorganisation (LGR).

c) Endorse exploration and feasibility of the capital purchase of HWRC plant and equipment during the tender bidding, with a view to having an agreed final revenue and capital cost of the contract at the final tender stage.

d) Delegate the decision to award the contract, and any extension to that contract to the Director of Environment and Highways in consultation with the Cabinet Member for Place, Environment and Climate Action.

Executive summary

2. Under section 51 of the Environmental Protection Act 1990, the council has a statutory duty to provide HWRCs for Oxfordshire residents to dispose of their household waste. For Oxfordshire the minimum requirement is 2 and in line with the council’s policy it currently provides 7. The current contract for the management of 6 of the 7 HWRCs terminates on 30 September 2027. The 7th site, Dix Pit, is managed via a legacy landfill contract which is anticipated to end by late 2027.

3. Following Cabinet approval in February 2025 to commence work evaluating the options for the HWRC management reprovision, waste specialists Eunomia were appointed to work with officers to determine the most appropriate approach to reprovision of the service.

4. The current known timetable, risks and opportunities of LGR have been fully considered as part of the evaluation of options.

V2.1 Sept 2025 5. The outcome of this work has identified that the appointment of a single provider via a long-term 8-year management contract with early in-contract options centred around flexibility post LGR to be the most appropriate HWRC management model for the council. This need has been tested with the market and is accepted.

6. The final contract costs will be established through a “Competitive Flexible Procedure procurement process”, with the final costs agreed through the most advantageous tender scoring the highest against tender evaluation criteria.

7. To ensure the most suitable bidder is appointed, and the tender is compliant, detailed evaluation themes are currently being developed and designed to support a Competitive Flexible Procedure, allowing dialogue and negotiation to take place to ensure the successful bidder will provide a cost effective and high quality HWRC management service, supporting the council in delivering of its key priorities.

Background

8. There is a network of 7 HWRCs within the county in the following locations and shown on the plan in Annex 1.  Alkerton HWRC, near Banbury  Ardley Fields HWRC, Bicester  Redbridge HWRC, Oxford  Drayton HWRC, Vale of White Horse  Oakley Wood HWRC, South Oxfordshire  Stanford in the Vale HWRC, Vale of White Horse  Dix Pit HWRC, West Oxfordshire district

9. These facilities receive around 1 million customer visits and manage approximately 50,000 tonnes of waste per annum. A series of service changes were implemented on 14 January 2026 including a requirement to make a booking before visiting, charges for out of county customers and the requirement to sort waste into recyclable waste streams before or on arrival. There are currently 2 contracts in place for the management of HWRCs.

10. In 2016 following an open tender procedure a 10-year contract (7-year main term plus up to 3-year extension) commencing on 1 October 2017 was awarded to sole trader Geoffrey David Thompson trading as Weymouth and Sherborne Recycling (W&S) for the management of 6 HWRCs and materials management at Dix Pit.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HWRC Management Contract Reprovision ANNEX 1_Map of HWRC Locations in Oxfordshire (1) /26Appendix 1 pages Download
PDF
HWRC Management Contract Reprovision ANNEX 2_HWRC Service Model Type Definitions (1) /26Appendix 1 pages Download
PDF
Household Waste Recycling Centres (HWRC): Management ReprovisionReport 12 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Oxfordshire

Search all
  1. Household Waste Recycling Centres (HWRC) - Management ReprovisionThis decision
  2. Proposed changes to the Waste Acceptance Policy (WAP) for Oxfordshire’s household waste recycling centres (HWRCs)Approved
  3. Household Waste Recycling Centre Service Delivery ModelApproved
  4. Household Waste Recycling Centre Network: Introduction of Booking SystemApproved
  5. Management of Household Waste Recycling Centres in Oxfordshire - Contract ExtensionApproved
  6. Household Waste Recycling Centre Strategy 2023 - 2043Approved

More from Oxfordshire Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Response to Motion by Councillor Evans on Motor Neurone DiseaseContact: Izzie Rockingham, Commissioning Manager (Improve Enable) [email protected] Report by the ... Approved Open
15 Sep 2026 DfT Local Transport Delivery PlanContact: Hannah Battye, Head of Place Shaping [email protected] Report by the Director of Environment ... Approved Open
15 Sep 2026 Treasury Management Quarter 1 Report 2026/27RESOLVED to note the council’s treasury management activity at the end of the first quarter of 2026/27. Noted Open
15 Sep 2026 Forward Plan and Future BusinessRESOLVED to note the items currently identified for forthcoming meetings. Noted Open