S106 Project – Accelerated Delivery and Corporate Funding

Noted Executive 1 paper

Cabinet noted this item on Tuesday 21 October 2025. Below is the council's own wording, with the papers it was decided on.

Item148/25

Resolved

RESOLVED to :- a) Note the approach to accelerated s106 developer agreement scheme delivery. b) Approve the programme of £27.5m investment as set out in Appendix A c) delegate the approval of procurement, sign off and any detailed changes needed to be made to the programme of schemes to the Director for Economy and Place, in consultation with the Cabinet Member for Place, Environment and Climate Action
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Cabinet, 8 pages

Recommendation

The Cabinet is RECOMMENDED to:

a) Note the approach to accelerated s106 developer agreement scheme delivery.

b) Approve the programme of £27.5m investment as set out in Appendix A

c) To delegate the approval of procurement, sign off and any detailed changes needed to be made to the programme of schemes to the Director for Economy and Place, in consultation with the Cabinet Member for Place, Environment and Climate Action

Executive summary

2.1In November 2024, a report to the Place Overview and Scrutiny Committee highlighted an ongoing need to accelerate delivery and spend against s106 developer agreement schemes. A cross-organisational approach has been implemented to enhance S106 fund management and spending. The programme elements within Phase 2 of the programme included a project to accelerate the delivery of mitigations which will provide improvements/benefits to communities and increase the County’s spend of s106 funding (‘The Accelerated Delivery Programme’).

2.2This paper has identified 33 schemes (6 are development only, and 27 schemes include construction) which span across the North, Central and South place planning areas.

2.3In preparation for this, as part of the 25/26 Budget Setting process, Cabinet approved a £4m Capital Investment, to unlock the spend of approximately £20m S106 funding. This £4m investment is known as ‘S106 Transport Corporate Funding’.

2.4The purpose of the funding, as outlined in the budget papers is to support local improvements that make a big difference to communities and will cover several different schemes. These schemes have S106 funding allocations, but additional funds are required to progress and deliver the projects. 2.5. 10 schemes that are part of the Accelerated Delivery Programme, are also in receipt of this s106 Transport Corporate Funding. The total value of schemes in this paper is £27.5m.

2.6A summary is below:

Total s106 Total s106 Total S106 Total Details Secured Held TCF (s106 + s106 TCF) S106 Transport Corporat e £8,343,883.54 £11,889,379.18 £4,000,000.00 £24,233,262.72 Funded (23) Accelerated Delivery Only £694,142.00 £2,647,138.85 £0.00 £3,341,280.85 (10) Paper Funding Totals (33) £9,038,025.54 £14,536,518.03 £4,000,000.00 £27,574,543.57

3. Accelerated Delivery Programme 3.1. The purpose of both the Accelerated Delivery Programme and the S106 Transport Corporate Funding is to fast-track S106 projects by addressing key barriers - delivery challenges through the Accelerated Delivery Programme, and funding gaps via the S106 Transport Corporate Funding.

3.2As such, both workstreams form part of Oxfordshire County Council’s S106 Improvements Programme.

3.3The S106 Accelerated Delivery programme specifically aims to accelerate the development and delivery of transport schemes, providing a viable delivery route, through an accelerated programme of works during 2025/26-2027/28.

3.4The intention is to implement the necessary mitigations within local communities to support the housing and commercial growth, using the allocated S106 funding.

3.5Some schemes have been delayed due to lack of sufficient developer funding to deliver the schemes on the ground. The S106 Transport Corporate Funding serves as top-up funding to unlock existing S106 allocations.

3.6This additional funding is necessary when the original S106 allocation is no longer sufficient to cover the development or delivery of works. It may be required for:

 Scheme development (e.g. feasibility studies, preliminary design work)

 Supplementing delivery costs, where costs have gone up or there are complications on the ground which have increased the cost of implementing a scheme and for it to be in line with the original S106 obligation as set out in the relevant obligation (or undertaking).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
S106 Project: Accelerated Delivery and Corporate FundingReport 8 pages DownloadRead as text

At this meeting

Whole meeting

More from Oxfordshire Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Response to Motion by Councillor Evans on Motor Neurone DiseaseContact: Izzie Rockingham, Commissioning Manager (Improve Enable) [email protected] Report by the ... Approved Open
15 Sep 2026 DfT Local Transport Delivery PlanContact: Hannah Battye, Head of Place Shaping [email protected] Report by the Director of Environment ... Approved Open
15 Sep 2026 Treasury Management Quarter 1 Report 2026/27RESOLVED to note the council’s treasury management activity at the end of the first quarter of 2026/27. Noted Open
15 Sep 2026 Forward Plan and Future BusinessRESOLVED to note the items currently identified for forthcoming meetings. Noted Open
28 Jul 2026 Proposed Changes to Adult Social Care Contributions PolicyRESOLVED to:- Note the contents of this report and confirm its agreement for a) Reducing the initial Disability Relat... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies