Resolved

RESOLVED to:- a) Note the intention to develop an Enterprise Zone Investment Plan. b) Consider and endorse the proposed Enterprise Zone investment priorities as set out at paragraph 41. c) Conditionally approve an allocation of up to £10m from the retained funding for Enterprise Zone 1 (Science Vale) to enable the delivery of priorities arising from the forthcoming OxRail strategy. d) Conditionally approve an allocation of up to £4m from Enterprise Zone 2 (Didcot Growth Accelerator) for infrastructure that directly enhances access to the Enterprise Zone itself. e) Conditionally approve an allocation of £0.700m in 2025/26 for additional economic strategy and delivery capacity and capability at Oxfordshire County Council and Enterprise Oxfordshire from the Enterprise Zone 1 retained business rate funding. f) Conditionally approve an on-going allocation of up to £1.254m each year for additional economic capacity and capability at Oxfordshire County Council and Enterprise Oxfordshire from 2026/27 – 2027/28, from the Enterprise Zone 1 retained business rate funding. g) Note that, regarding Enterprise Oxfordshire, the acceptance of those funds will be subject to agreement of the Enterprise Oxfordshire Board and Shareholder Committee and will be considered in light of both a revised business plan for 2025/26, and a business plan for 2026 plus. h) Delegate authority to the Director for Economy & Place in consultation with the Cabinet Member for Future Economy & Innovation, to oversee the preparation of business cases for recommendations e) and f). i) Note that the Cabinet Member for Future Economy & Innovation, in conjunction with the Director for Economy & Place, will undertake engagement with district councils regarding the Investment Plan and pipeline of investible propositions. j) Approve switching the use of remaining funding of £15.7m from supporting on-going borrowing costs to a direct contribution to finance the capital investment allocated towards the City Deals & Pinch Point Programme.
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Cabinet, 12 pages

Recommendation

Cabinet is RECOMMENDED to:

a) Note the intention to develop an Enterprise Zone Investment Plan.

b) Consider and endorse the proposed Enterprise Zone investment priorities as set out at paragraph 41.

c) Conditionally approve an allocation of up to £10m from the retained funding for Enterprise Zone 1 (Science Vale) to enable the delivery of priorities arising from the forthcoming OxRail strategy.

d) Conditionally approve an allocation of up to £4m from Enterprise Zone 2 (Didcot Growth Accelerator) for infrastructure that directly enhances access to the Enterprise Zone itself.

e) Conditionally approve an allocation of £0.700m in 2025/26 for additional economic strategy and delivery capacity and capability at Oxfordshire County Council and Enterprise Oxfordshire from the Enterprise Zone 1 retained business rate funding.

f) Conditionally approve an on-going allocation of up to £1.254m each year for additional economic capacity and capability at Oxfordshire County Council and Enterprise Oxfordshire from 2026/27 – 2027/28, from the Enterprise Zone 1 retained business rate funding.

g) Note that, regarding Enterprise Oxfordshire, the acceptance of those funds will be subject to agreement of the Enterprise Oxfordshire Board and Shareholder Committee and will be considered in light of both a revised business plan for 2025/26, and a business plan for 2026 plus.

h) Delegate authority to the Director for Economy & Place in consultation with the Cabinet Member for Future Economy & Innovation, to oversee the preparation of business cases for recommendations e) and f).

i) Note that the Cabinet Member for Future Economy & Innovation, in conjunction with the Director for Economy & Place, will undertake engagement with district councils regarding the Investment Plan and pipeline of investible propositions.

V2.0 Nov 2024 j) Approve switching the use of remaining funding of £15.7m from supporting on- going borrowing costs to a direct contribution to finance the capital investment allocated towards the City Deals & Pinch Point Programme.

Executive summary

1. This report sets out background, principles and conditional proposals for the use of retained business rates funding generated through the two Enterprise Zones in Oxfordshire to support economic development in Oxfordshire.

Background

2. Enterprise Zones (EZs) were established across the UK in 2012 as part of the Governments “Plan for Growth (2011)”, supporting businesses and promoting economic growth and wellbeing.

3. For the first five years of operation, EZs were able to encourage businesses to move to the area by offering substantial discounts on their business rates. Since the conclusion of the discount scheme, businesses continue to see incentives to relocate to an EZ, such as the key industry clusters in the area and the reinvestment of business rates in local infrastructure projects.

4. Oxfordshire has two multi-site EZs and these are located within the South Oxfordshire and Vale of White Horse district council areas. The two EZs sites encompass a total of 16 sites covering 216 hectares of commercial development land.

5. Science Vale EZ1 was created in 2012 and is located around the Harwell Campus and Milton Park sites. The Didcot Growth Accelerator EZ2 was created in 2016 and is located around the Milton Park and areas of the north of Didcot

6. All business rates growth generated within the EZs are retained for 25 years to reinvest in local economic development. Local is defined as the relevant geographic and economic area, i.e. Oxfordshire.

Accountable Bodies and Governance

7. Vale of White Horse District Council is the Accountably Body for the collection and holding of the business rates generated within the Enterprise Zones.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enterprise Zone Business Rates: Forecast and Update on Planned UseReport 12 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Oxfordshire

Search all
  1. Enterprise Zone Business Rates – Forecast and Update on Planned UseThis decision
  2. Cowley Branch Line - Enterprise Zone FundingApproved

More from Oxfordshire Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Response to Motion by Councillor Evans on Motor Neurone DiseaseContact: Izzie Rockingham, Commissioning Manager (Improve Enable) [email protected] Report by the ... Approved Open
15 Sep 2026 DfT Local Transport Delivery PlanContact: Hannah Battye, Head of Place Shaping [email protected] Report by the Director of Environment ... Approved Open
15 Sep 2026 Treasury Management Quarter 1 Report 2026/27RESOLVED to note the council’s treasury management activity at the end of the first quarter of 2026/27. Noted Open
15 Sep 2026 Forward Plan and Future BusinessRESOLVED to note the items currently identified for forthcoming meetings. Noted Open
28 Jul 2026 Proposed Changes to Adult Social Care Contributions PolicyRESOLVED to:- Note the contents of this report and confirm its agreement for a) Reducing the initial Disability Relat... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies